Northland Rail Line beyond Kauri
Response by KiwiRail to Andrew Jones on .
Successful.
Good afternoon Andrew,   The planned rail upgrades between Kauri and Otiria are currently paused, pending the Government's decision about building...
Parker Street level crossing and cycleway integration design delays
Response by KiwiRail to Cody C on .
Information not held.
Good afternoon Cody Reading your query, there isn't a succinct answer that one person made the decision. As the email of 28 Feb notes the decision to...
In progress and planned construction/maintenance
Response by KiwiRail to Connor Johnson on .
Partially successful.
Good afternoon Connor Thank you for your request. Information on our major projects, including the Northland Rail Rejuvenation, Wellington/Wairarapa...
Wairopa logging trains
Response by KiwiRail to Niall Robertson on .
Awaiting classification.
Good evening Niall Thank you for your enquiry on price increases for logging trains on the Wairoa line. We note that you are stating that "KiwiRail s...
Good evening David Please find our reply below. 1. How many train movements occurred on the Shands Rd/Hornby branch spur in the last 12 months? The...
Options for ballast replacement in Auckland
Response by KiwiRail to R S Grant on .
Partially successful.
Good afternoon Grant. If you have a look at document three under the release, I think you will find that will answer your query about the various opti...
Non-refundable costs paid to HMD
Response by KiwiRail to Michael Steere on .
Refused.
Good morning Michael   Thank you for your enquiry, asking for information on:   1. Please inform me how much money has already been paid to Hyu...
West Coast (SI) Coal Various
Response by KiwiRail to Lindon Boyce on .
Successful.
Good afternoon Lindon   Please find our responses below.   * The key coal loading facility on the West Coast is Ngakawau.  We also regularly load...
Golden Triangle Electrification Detailed Business Case aka GTEP DBC
Response by KiwiRail to Bob on .
Awaiting classification.
Good morning Bob We have proactively published the detailed business case - this can be found here https://www.kiwirail.co.nz/who-we-are/sustainabilit...
Locomotive Mean Distance Between Failures (MDBF)
Response by KiwiRail to LJ Holden on .
Successful.
Good afternoon Lewis   Please find the attached.   As noted previously there is considerable fluctuation in the figures from month to month, w...
Progress on Halswell Junction Road realignment
Response by KiwiRail to Cody C on .
Partially successful.
Good afternoon Cody   Just to clarify, I had thought the information would have been sufficient to answer your queries, but to be definitive.   Wh...
Passenger rail diesel consumption
Response by KiwiRail to Peter King on .
Successful.
Good afternoon Peter   Please find our response below.   These figures include the generator vans which are critical to the service operating....
Spend on staff transport
Response by KiwiRail to Sam Ballantine on .
Partially successful.
Good afternoon Sam Thank you for your enquiry. This is a simple on to answer as all that information is reported on publicly as part of KiwiRail's res...
Good afternoon Regan, and thank you for your enquiry. We are declining your request in full under sections 9(2)(b)(ii) and 9(2)(i) – Commercial inform...
Wairarapa Line tunnel works
Response by KiwiRail to Lloyd Davies on .
Awaiting classification.
Good afternoon Lloyd Please find our response below. Please note we have taken your query to mean the work completed at Easter, and any further work....
Interislander using google suit (google docs, sheets ect)
Response by KiwiRail to Luna on .
Information not held.
Apologies, I had your request noted as being due on 6 August 2024. I have enquired as to your request and am advised that KiwiRail uses the Microsoft...
Good afternoon Liam   Further to my email below, I am advised that we do not hold these plans in our current records. We are willing to have a l...
Proposed closure of Ava railway bridge footpath
Response by KiwiRail to Mike Mellor on .
Successful.
Good afternoon Mike I'd like to acknowledge receipt of your official information requests for information on the proposed removal of the Ava railway b...
Master fleet list
Response by KiwiRail to Connor Johnson on .
Successful.
Good afternoon Connor A quick email to acknowledge we have received your request for the Masterfleet and call sign for all KiwiRail trains. I note you...
Process behind alternatively fueled vehicles policy
Response by KiwiRail to Matt Johnston on .
Long overdue.
Good afternoon Matt I'd like to acknowledge receipt of your official information request for information on KiwiRail/Interislander's policy on transpo...
Wellington Ferry Terminal Infrastructure and Linkspan
Response by KiwiRail to T.J. Pohl on .
Refused.
Good afternoon TJ This email is to advise we are transferring part of your request to Ferry Holdings Ltd. Any information post 5 March 2025 on the reu...
Good morning Jon We have received your request, as per the below. This information however is not held by KiwiRail, and instead is the responsibility...
Request for Information on Gender Diversity at KiwiRail
Response by KiwiRail to Anna on .
Successful.
Good afternoon   Please find our response below.   1) The percentage of women holding Project Manager positions. Using our Project Management...
Good afternoon   I’d like to acknowledge that we have had part of your request asking for details on the announced rail closures transferred to Ki...
Track rebuild Papakura to Pukekohe
Response by KiwiRail to Niall Robertson on .
Partially successful.
Good afternoon Niall. Please find our response below. As part of Stage 3b of the Rail Network Rebuild (RNR), drainage work is planned between Puhinui...