Progress on Halswell Junction Road realignment

Cody C made this Official Information request to KiwiRail

The request was partially successful.

From: Cody C

Dear KiwiRail,

What is the current state of this project?
When is this project anticipated to be completed?
What is the the main hold-up, if any?
What is the approximate cost of this project, both to date and by completion, to KiwiRail?

Please note this same request has also been sent to CCC; however, the questions in this context are directed to KiwiRail.

Yours faithfully,

Cody C

Link to this

From: OCU
KiwiRail

Kia ora Cody,

I'd like to acknowledge receipt of your official information request for information on KiwiRail's Halswell Junction realignment.

We received your request on 1st May 2023, and will endeavour to respond to your request as soon as possible and in any event no later than 29th May 2023, i.e. the 20 working days after the day your request was received.

If we are unable to respond to your request by then, we will notify you of an extension of that timeframe.

Dave Allard, who is cc'd, will be looking after your request, so any questions please get in touch with him at [email address] or on 027 201 8182.

Thanks,
Scarlett Dellow  |  Communications Coordinator
MOB: +64 27 234 0003
Second Floor, KiwiRail Building Millennium Centre, 604 Great South Road, Ellerslie, 1051 | Private Bag 92138, Auckland 1142, New Zealand

www.kiwirail.co.nz
Please consider the environment before printing.

The content of this message and any attachments may be privileged or confidential. If you
have received this email in error please notify the sender and delete the email - unauthorised
use is expressly prohibited. This email may have been corrupted or interfered with. KiwiRail
does not warrant that this email and its contents are free from computer viruses or other defects.

show quoted sections

Link to this

From: Cody C

Dear OCU,

Awaiting your reply, as this request is now due.

Yours sincerely,

Cody C

Link to this

From: Cody C

Dear OCU,

Awaiting your reply, as this request is now due.

Yours sincerely,

Cody C

Link to this

From: Cody C

Dear OCU,

Peter Reidy - CEO Kiwirail - has been contacted this morning to advise that this request is overdue and will be going to the Ombudsman for intervention if an urgent reply is not received as you are now in breach of the OIA.

Yours sincerely,

Cody C

Link to this

From: Dave Allard
KiwiRail


Attachment Meeting minutes 17 Jan 23 Redacted.pdf
594K Download View as HTML

Attachment Meeting minutes 17 March 23 Redacted.pdf
206K Download View as HTML

Attachment Meeting minutes 28 March 23 Redacted.pdf
205K Download View as HTML

Attachment Meeting minutes 31 Jan 23 Redacted.pdf
278K Download View as HTML

Attachment HJR Overview.pdf
489K Download View as HTML

Attachment Meeting minutes 17 Feb 23 Redacted.pdf
176K Download View as HTML

Attachment OIA2023 50 Cody C Halswell Junction.pdf
28K Download View as HTML


Good morning Cody

Please find our response.

Cheers
Dave

Dave Allard  | Senior Government Relations Advisor
DDI: 027 201 8182
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO Box 593, Wellington 6140, New Zealand

www.kiwirail.co.nz

show quoted sections

Link to this

From: Cody C

Dear Dave Allard,

The response is unacceptable as most of the questions I posed in the original request have either not been answered or been redacted. It is unclear when the project will be completed. Lastly, I did not receieve any acknowledgement of the delay on this request.

Accordingly, this has been referred to the Ombudsman for further investigation.

Yours sincerely,

Cody C

Link to this

Cody C left an annotation ()

With Ombudsman

Link to this

From: Dave Allard
KiwiRail

Good afternoon Cody
 
Just to clarify, I had thought the information would have been sufficient
to answer your queries, but to be definitive.
 
What is the current state of this project? - Still in design phase - as
noted signalling design is on-going and physical works can't be completed
until a design is finalised.
When is this project anticipated to be completed? - there isn't one, as
KiwiRail can't provide an estimate completion date until there is a
finalised design.
What is the main hold-up, if any? Is a complex site, and designing the
interface between rail and road has taken longer than anticipated. From
the timeline provided -
Designs
- Civil Design Approved with minor details to be confirmed once signals
design is complete
- Track Design - minor adjustments required
- Signals Design - on-going
Note - prefabrication for signalling equipment required before physical
works can commence
 
What is the approximate cost of this project, both to date and by
completion, to KiwiRail? As noted in response - these details are
commercially sensitive as contracts still being negotiated.
 
Cheers
Dave
 
Dave Allard  | Senior Government Relations Advisor
DDI: 027 201 8182
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO
Box 593, Wellington 6140, New Zealand
 
[1]www.kiwirail.co.nz
 

show quoted sections

Link to this

Things to do with this request

Anyone:
KiwiRail only: