Wairarapa Line tunnel works

Lloyd Davies made this Official Information request to KiwiRail

This request has an unknown status. We're waiting for Lloyd Davies to read recent responses and update the status.

From: Lloyd Davies

Dear KiwiRail,

I am seeking all information related to any track or formation works undertaken inside the Wairarapa line tunnels after the completion of the block of line works in February 2025. Information should include detailed description of all work undertaken, reasons for the work not being done during the block of line works, costs associated with this work, and what further work is required.

Yours faithfully,

Lloyd Davies

Link to this

From: Lloyd Davies

Dear KiwiRail,

Just following up to ensure my request has been received. Some form of acknowledgement is good practice.

Yours faithfully,

Lloyd Davies

Link to this

From: Dave Allard
KiwiRail

Confirming this one has been received as well.

Cheers
Dave

show quoted sections

Link to this

From: Dave Allard
KiwiRail

Good afternoon Lloyd

Please find our response below.
Please note we have taken your query to mean the work completed at Easter, and any further work.

At Easter we undertook tamping work, after the track had time to go through its consolidation (i.e. the passage of trains causes some minor settlement so we go back to put the track to the design level).
The work could not be done during the block of line at Christmas because there was not enough time to achieve consolidation (i.e. we did run fully loaded trains to get through the critical settlement, but more was needed and there was not enough time to achieve this).
The total cost for the work at easter including both KiwiRail and contracted resources was approx. $270k. This allowed the track speed to be increased from 60kph to 90kph.

We will be going into the tunnel 26-27th July and 16-17th Aug to re-spread some of the ballast in the tunnel where the tamping activity did not use as much as expected.
This will improve the walking surface for our people when they undertake inspections or other work over the coming years. The cost if this work is estimated to be approx. $140k.

We trust this answers your queries.

Kind regards

Dave

Dave Allard  | Senior Government Relations Advisor
DDI: 027 201 8182
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO Box 593, Wellington 6140, New Zealand

www.kiwirail.co.nz

show quoted sections