Meeting Record 
KiwiRail Holdings Ltd 
 

 
 
Project:  Halswell Junction Road (HJR) Level Crossing 
Reference: HJR  
Relocation  
 
Location: Teams 
Meeting Date: 31/01/2023 
 
 
Present    Apology    Copy        Circulate     Name:                                                            Organisation:                      
 
 

 
 
 
Privacy 9(2)(a)
 
CCC 
 

 
 
Privacy 9(2)(a)
  
KiwiRail (KR)  

 
 
 
Privacy 9(2)(a)
 
CCC 

 
 
 
Privacy 9(2)(a)
 
KiwiRail (KR) 
✓ 
 
 
 
Privac  
CCC / Advanced Traffic  
✓ 
 
 
 
Privacy 
y 9(2)
9(2)(a)
 
KiwiRail (KR) 

(a)
 
 
 
 
Privacy 9(2)(a)
 
CCC 
Recorded By:   Privacy 9(2)   
Total Pages: 3   
                                
(a)                                           
Subject: Project Meeting 22 
 
Post meeting note. 

Privacy 
– introduced Privacy 9(2)(a)  who will be taking over the Project HJR from Privacy  
soon. 
9(2)(a)
9(2)(a)
Thanks, Privacy   for her hard work and dedication to the Project. 
 

9(2)(a)
                                                   
ID 
Details: 
Action 
By/Date: 

1.0 
General Business  
 
1.1 
Consenting was discussed first due to guests present. Refer to Section 
Note  
13 for details. 
2.0 
Health & Safety 
 
2.01 
TM noted  there was a minor incident in November but only reported 
Note 
to TM, whereby a Downer  vehicle backed into the a concrete pit. TM 
noted that the KR team were content with the actions taken and 
consider the item closed. 
3.00 
Programme  
 
3.01 
TM noted that Downer are still on site completing ballasting but FH will  Note 
 
be given the site on 13th Feb if they have resources to start then. 
 
 
SG to review Downer completion date. 
 
 


Meeting Record 
KiwiRail Holdings Ltd 
 

 
3.02 
SN highlighted that CCC need to confirm to their preferred contractor 
 
how they will proceed on the back of when KR believe they will have 
 
completed their works. Commercial activities- Section 9(2)(i)
 
Note 
   
 
TM explained what he was told pre-christmas break i.e. that HIMA 
 
could take as long as up to December 2023 or January 24. Physical 
 
works would need to follow. Therefore, TM was investigating a Plan B 
 
solution that would enable level crossing to be opened but would 
 
required HIMA to be installed at later date. 
 
 
Commercial activities- Section 9(2)(i)
 
 
 TM indicated noted 
 
a meeting was planned later today and that most of KR were returning 
TM 
to work on the 16th January. TM to progress with utmost urgency.  
Ongoing 
3.03 
TM noted next progress meeting with FH was Thursday coming.  
Note  
3.04 
SN requested an indication on programme. CCC are targeting this 
TM 
Friday to announce preferred tenderer however, if delay with staging of 
works is significant they may reconsider strategy.  
SN flagged construction phasing concern as CCC design includes an 
island which limits access to the business nearest the new level 
crossing.  
TM to discuss options internally after signals meeting on Wednesday 
and advise.  
TM supplied Programme to CCC. 
4.00   Design 
 
4.01 
n/a  
Note 
 
5.00 
Communications  
 
5.01 
CCC and KR to keep in touch regarding programme. 
Note 
 
Going well – with fortnightly meeting. 
 
6.0  
Procurement  
 
6.1 
n/a  
SN 
 
 
7.0  
Finances   
 
7.1 
TM to confirm if any payments to further to invoice issued on the 7th 
TM 
 
December are necessary before 20th 
Complete 
7.2 
SN has requested a forecast for first 6 months of 2023. TM to action.  
TM 
TM Supplied to CCC. 
8.0 
Construction   
 
8.1  
Refer to 2.01 and 3.03 for notes on Downer’s activities on site at 
Note 
 
present relating to the civil and drainage works ongoing at yard and 
down main.  
10.0 
Quality Assurance    
 
10.1 
Nothing to report. 
n/a 
 



Meeting Record 
KiwiRail Holdings Ltd 
 

 
 
11.0 
Risks / Opportunities  
 
11.1 
N/A 
Note 
 
12.0 
Legal/Property  
 
11.01  PMcC noted that water pipe at existing level crossing is to e 
Note 
 
decommissioned. 
 
11.02  DA noted grant application for utility at Halswell Junction Road declined   
as it was too close to the track, Commercial activities- Section 9(2)(i)  
 
 
 
 
NOTE 
TM to discuss install with FH at Thursday progress meeting with FH.  
11.03 
 
 
 
 
 
 
 
 
 
 
 
DA confirmed that a new grant is necessary for ducts required for the 
 
traffic signals. Bill confirmed 100mm orange duct required. SN noted 
 
that CCC were told only one duct could be installed by the Council 
 
though TM highlighted that this may not be accurate.  
 
SN to confirm how many ducts CCC would like to install and provide 
SN 
spec for duct. 
 
TM to check if FH would procure the duct.  
TM 
11.04  Traffic Signal Pole 
 
DA confirmed that a deed of grant is required for the traffic poles. DA 
 
does not required all details. TM and DA to discuss and confirm 
TM 
requirements.  
 
DA to send template to TM to show what details are necessary. TM to 
DA 
issue.  
 
SG to check with KR Signals – if CCC poles can be used by Signals – as 
 
per Riccarton Road. 
SG 
13.0 
Consenting/RMA 
 
13.01  n/a 
Note 
 
 
14.0 
Key Decisions  
 
14.01  Nothing to report. 
Note 
 
15.0 
Other Business  
 
15.01  TM and SG to check when next PCG is scheduled.  
TM 
Next PCG – 23 February 2023. 
 


Meeting Record 
KiwiRail Holdings Ltd 
 

 
 
15.02  TM on leave 28th January to 14th February.  
Note 
 
Next Meeting:  Tuesday 14/2/23 at 10am via Teams 
Attachments: Nil