Requests similar to 'Progress on Halswell Junction Road realignment'
Progress on Halswell Junction Road realignment
Request sent to Christchurch City Council by Cody C on .
Successful.
Re: Halswell Junction Road realignment
What is the current state of this project?
When is this project anticipated to be completed?
What is the...
Parker Street level crossing and cycleway integration design delays
Information not held.
Good afternoon Cody
Please find the attached letter and corresponding documents.
Any further questions please get in touch - I am following up on you...
LED lighting upgrade on Christchurch Southern Motorway
Response by New Zealand Transport Agency to Cody C on .
Successful.
Dear Cody
Please find attached a response from Andrew Thackwray to your email of 23
April 2021.
Regards
_________ ______________________...
Good afternoon Harriet
Thank you for your email response on 13 July 2017 clarifying your request (from the below email dated 18 June 2017) for the fol...
New railway crossing at Halswell Junction Road / Waterloo Road
Response by Christchurch City Council to Patrick Dunford on .
Partially successful.
Dear Patrick,
I refer to your request for information as below.
I have consulted with staff and they have provided the following
informati...
Maintenance arrangements for the underpass in Waltham between Thackeray and Falsgrave Streets
Successful.
Good morning Cody
As noted in my previous email on this one, this was answered in my letter which responded to the three OIA requests you'd asked of u...
Costings for high-use driveway treatment for cycle paths and shared paths
Response by Christchurch City Council to Cody C on .
Successful.
Kia ora Cody,
On 20 March 2024, you requested the following information, under the Local
Government Official Information and Meetings Act 1987 (...
Kia ora Cody,
I'd like to acknowledge receipt of your official information request for information on the Amyes Road Intersection.
We received your r...
Capital Project Management System (CPMS) sheets
Response by Christchurch City Council to Cody C on .
Successful.
Dear Cody,
I refer to your request from 24 May below.
Council staff have provided the following responses to your questions:
1. ...
Main North Line corridor between Christchurch and Rangiora
Response by KiwiRail to Patrick Dunford on .
Successful.
Good afternoon
Please find the attached.
Kind regards
Dave
Dave Allard | Senior Government Relations Advisor
DDI: 027 201 8182
Level 4, Wellington...
Good afternoon TJ
Please find the attached.
We note this document is best read in conjunction with the Wellington Network Programme Business case whic...
Correspondence KiwiRail has about the business park development at Benmore Crescent, Manor Park Lower Hutt
Response by KiwiRail to Anne Alkema on .
Successful.
Good afternoon Anne
Apologies, it seems we are having issues with responding to FYI.org requests.
Please find our response below.
I have checked in...
Good afternoon Harriet,
We refer to your request for information dated 22 June 2017 in which you
ask for:
1. Marsden Point Rail Link...
SH75 Halswell Road improvements project costings
Response by New Zealand Transport Agency to Cody C on .
Successful.
Kia ora Cody
Please find attached the response to your request of 29 April 2024 for
information under the Official Information Act 1982.
N...
Reuse of Addington Junction site to reinstate eastward facing track
Response by KiwiRail to Patrick Dunford on .
Successful.
Good afternoon Patrick
Please find attached our response to your query.
Kind regards
Dave
Dave Allard | Government Relations Advisor
Level 4, Well...
Dear Cody,
Thank you for your email, received on 01.06.2023. You requested the
following information, under the Local Government Official Inform...
Good evening Niall
Thank you for your enquiry on price increases for logging trains on the Wairoa line.
We note that you are stating that "KiwiRail s...
Safety assessments for Halswell Junction Road / Alvaston Drive / Hamill Drive Roundabout
Response by Christchurch City Council to Patrick Dunford on .
Successful.
Dear Patrick
In response to you queries regarding the Halswell Junction Road / Alvaston
Drive / Hamill Drive Roundabout, staff provide the follo...
Low Cost Low Risk transport projects
Response by Canterbury Regional Council to Tim Adriaansen on .
Successful.
Dear Tim
Please find the response attached.
Regards
Courtney MacKenzie ^| Executive Assistant
Commercial & Strategy
[1]Timaru Distr...
Options for ballast replacement in Auckland
Partially successful.
Good afternoon Grant.
If you have a look at document three under the release, I think you will find that will answer your query about the various opti...
Compton St level crossing Tinwald MSL 97.54 km
Response by KiwiRail to Patrick Dunford on .
Successful.
Good afternoon Patrick
Apologies for the delay in responding to your query.
KiwiRail has looked at the Compton Street level crossing in relation to t...
Good morning Michael
Thank you for your enquiry, asking for information on:
1. Please inform me how much money has already been paid to Hyu...
Good afternoon Isaac.
I am responding to your recent OIA request asking:
I would like to make an OIA regarding information to the current p...
Kaitaki Ferry Conversion Project Related to the KiwiRail Turnaround Plan
Partially successful.
Good evening
Please find the attached response and associated documents.
Any questions, please feel free to get in touch with me directly.
Kind reg...
Improvements to Midland Line / Main South Line connectivity at Rolleston
Response by KiwiRail to Patrick Dunford on .
Successful.
Good afternoon Patrick.
To answer your query - Waka Kotahi NZTA is suggesting it will be possible
to provide improved connectivity at Rolleston...