IREX: Cost expended with the ECI Contractor (Downer and HEB) between Feb 2022 and the closing of the Project
Response by KiwiRail to Adrian Sykes on .
Long overdue.
Good afternoon Adrian
I'd like to acknowledge receipt of your official information request dated 4 August 2024, for information on ECI contractor spen...
IREX: Cost expended with the engineering and design team (Jacobs and WSP) from Feb 2022 - the closing of the Project
Response by KiwiRail to Adrian Sykes on .
Awaiting classification.
Good afternoon Adrian
I'd like to acknowledge receipt of your official information request dated 4 August 2024, for information on the design team spe...
Total number of freight trains using rail leaving Tauranga Port travelling North
Response by KiwiRail to Janene Pearce on .
Successful.
Good afternoon Janene
Please find the table below in response to your query.
Any further questions, please get in touch.
Total Freigh...
Good afternoon Joel
Please find the attached which is the current fleet list for 2024.
Please be advised, we have been unable to locate a list of roll...
Detailed Plan to commission and fully operationalise the Auckland CRL
Response by KiwiRail to Jon Eriksen on .
Long overdue.
Good afternoon Jon
Thank you for your request, as per the below.
A quick email to acknowledge receipt, we are just scoping your request out at the mom...
All information regarding meetings and discussions due to SPAD
Response by KiwiRail to Hillman Humffreys on .
Awaiting classification.
Good afternoon Hillman
I'd like to acknowledge your request for “all recorded details of the
meetings and discussions held regarding my SPAD inc...
Good morning Lloyd
Apologies for slightly delay, I was hoping to acknowledge and respond all in one, as I wasn't sure if we'd hold the information req...
Train Punctuality, Delay Reasons, and Mitigation (Wellington-bound Services, 7:00–9:30am)
Awaiting classification.
Good afternoon
We have received your request dated 25 June 2025, for information on the punctuality of Wellington Bound services, and reasons for any...
Good afternoon Niall
Confirming receipt of your request.
We are working on a response for you and will be back in touch shortly.
I note the timefram...
Good afternoon Niall
Confirming receipt of this request as well.
We will combine the two answers, and as noted we are working on a response for you a...
Good afternoon
A quick email to acknowledge receipt of your official information request for information on Train control irregularities as per the b...
Good morning Tony
I'd like to acknowledge receipt of your official information request for information on the Capital Connection.
We received your re...
Good morning Colin, and thank you for your request.
Please note, we are declining your request under Section 9(2)(f)(iv) of the Act - i.e. Active Cons...
Good afternoon Niall
I am advised that there is some investigation work is being done to determine if DL locomotives can run this service at 100km/h....
Good afternoon Steven
No, I'm afraid I can't see any record of a request for Locomotive information being received, and I apologise your request doesn...
DL Class Locomotives Withdrawn or Scrapped
Awaiting classification.
Good afternoon John
Thank you for your enquiry, I've passed this on to our locomotive asset team, and will be back in touch shortly.
Kind regards
Da...
Good morning Colby
Just letting you know we've received your request and I've passed it onto our Rolling Stock team.
The two guys who will have this i...
Uptime for passport, polaris and related interislander applications for the year 2025
Information not held.
Good afternoon Luna
Confirming we have received your request and will be considering what information we have available.
We will be back in touch in...
Request for the detailed Rate Calculations and other information on the GWRC 2021/22 Long Term Plan
Response by Wellington Regional Council to Tony Randle on .
Long overdue.
Dear Mr Randle,
Attached is Greater Wellington’s further response to your request for
information and corresponding attachments.
Kind rega...
Dear Iain
Thank you for your request for information regarding rail heritage groups
If you have any further queries please contact me on 09...
Safety case for Te Huia train operating cab car SRV5893 or equivalent at head of train
Response by New Zealand Transport Agency to Patrick Dunford on .
Successful.
Good morning Patrick
Please find our response below to your recent enquiry, transferred to
KiwiRail from NZTA.
The SRV cabs were built to...
Provincial Growth Fund train services upgrades
Response by Ministry of Business, Innovation & Employment to Tim Frank on .
Awaiting classification.
Good afternoon Tim
We have received the below request, transferred from MBIE - asking about the funding for KiwiRail passenger train service upgrades....
Correspondence with Heritage New Zealand relating to Snapper ticketing machines in Metlink stations
Response by Wellington Regional Council to F. Greig on .
Awaiting classification.
Kia ora,
Attached is Greater Wellington’s response to your recent request for
information and corresponding attachments.
Kind regards,
...
Good afternoon George
Thank you for your request asking for - Please provide the final incident
report for the signal failure event on 22 Feb 20...
Monies paid to consultants and other stakeholders for station renaming
Response by Auckland Transport to Jai Ganesh on .
Information not held.
Good afternoon
Please find our response to your OIA request, Transferred to KiwiRail from
Auckland Transport.
Kind regards
Dave
...