Train Punctuality, Delay Reasons, and Mitigation (Wellington-bound Services, 7:00–9:30am)
Awaiting classification.
Good afternoon
We have received your request dated 25 June 2025, for information on the punctuality of Wellington Bound services, and reasons for any...
Good afternoon Niall
Confirming receipt of your request.
We are working on a response for you and will be back in touch shortly.
I note the timefram...
Good afternoon Niall
Confirming receipt of this request as well.
We will combine the two answers, and as noted we are working on a response for you a...
Good afternoon
A quick email to acknowledge receipt of your official information request for information on Train control irregularities as per the b...
Good morning Colin, and thank you for your request.
Please note, we are declining your request under Section 9(2)(f)(iv) of the Act - i.e. Active Cons...
Good morning Colby
Just letting you know we've received your request and I've passed it onto our Rolling Stock team.
The two guys who will have this i...
Uptime for passport, polaris and related interislander applications for the year 2025
Information not held.
Good afternoon Luna
Confirming we have received your request and will be considering what information we have available.
We will be back in touch in...
Dear Sir/Madam
We are writing in response to your request dated 5 October 2016 for
information on the status of DC and TR locomotives and detail...
Preservation for DC 4012 and 4951 when retired from service
Response by KiwiRail to Colby James on .
Awaiting classification.
Good afternoon Colby
A quick email to say thank you for your enquiry.
I note it’s not a request for information as such, rather more of a call...
Re Locomotives on the North Auckland Line
Request sent to KiwiRail by Save Our Rail Northland on .
Long overdue.
To KiwiRail Management Team.
We sent the following request on the 7th of March 2014 but have yet to receive a reponse .
Under the terms of the O...
Tender Award - Rail Network Growth Impact Management (RNGIM) programme.
Response by KiwiRail to Charlene van der Merwe on .
Successful.
Dear Charlene,
I refer to your request asking –
GETS 24188020 - Rail Network Growth Impact Management (RNGIM) programme.
Please may you k...
Travel time for freight services between Auckland and Wellington
Partially successful.
Kia ora John,
Please find attached our response to your OIA request regarding freight services between Auckland and Wellington.
Ngā mihi
Laura
Lau...
Good afternoon Jayson
Please find our response below.
1) Why is everything stacked right underneath my window where it is the
most disrupt...
Reuse of Addington Junction site to reinstate eastward facing track
Response by KiwiRail to Patrick Dunford on .
Successful.
Good afternoon Patrick
Please find attached our response to your query.
Kind regards
Dave
Dave Allard | Government Relations Advisor
Level 4, Well...
Distances of stations on the rail network
Response by KiwiRail to Patrick Dunford on .
Handled by post.
Get in touch directly, and I'll see if I can put you in touch with our data guys.
Dave Allard | Senior Government Relations Advisor
DDI: 027 201 8182...
Good morning Finn
Thank you for your enquiry on the current status of the DFT and DC class locomotive fleets.
Following the introduction of electric...
NIMT electric locomotives and Electrification
Response by KiwiRail to Iain Palmer on .
Partially successful.
Good morning Mr Palmer
We refer to your Official Information Act 1982 request dated 1 January
2016 containing the following questions:
Dur...
Marsden Point Line NZUP delivery case
Response by KiwiRail to Daniel Palenski on .
Partially successful.
Good afternoon Daniel
We have received your enquiry as to the detailed business case for the Marsden Point line.
Please be advised KiwiRail is curren...
Good afternoon Mr Palmer
We are writing in response to your email to KiwiRail dated 4 November
2016. Your request has been considered under the...
Good afternoon George.
Thank you for your OIA request asking for - a current scheduled completion
date of IRex, and key milestone dates, in part...
Maintenance arrangements for the underpass in Waltham between Thackeray and Falsgrave Streets
Successful.
Good morning Cody
The response to this question was part of the previous letter answering your questions as you asked three queries at the same time....
Request for correspondence and reports on the New timetable for Johnsonville train line
Response by KiwiRail to Tony Randle on .
Partially successful.
Dear Tony
We refer to your Official Information Act 1982 request dated 27 July 2015 for the following information:
1. Can you please provide me with...
Good afternoon Mike
Please find the attached.
Kind regards
Dave
Dave Allard | Government Relations Advisor
DDI: +64 4 498 3218
Level 4, Wellingto...
Modelling of public transport between Wellington northern suburbs and Lower Hutt
Response by Wellington Regional Council to Andrew Ecclestone on .
Successful.
Tēnā koe Andrew
Request for information 2026-089
I refer to your request for information dated 26 February 2026.
Our response is encl...
Reqest for the rest of the Johnsonville Timetable Reports
Response by KiwiRail to Tony Randle on .
Partially successful.
Dear Tony
We refer to your Official Information Act 1982 request dated 26 August 2015 for the following information:
"The KiwiRail response to the O...