(page 4)
- all requests
- successful requests
- unsuccessful requests
- unresolved requests
Bridge strike issues at Main South Line Bridge 43, "Tinwald Viaduct"
Response by KiwiRail to Patrick Dunford on .
Partially successful.
Patrick
What measures have currently or previously been proposed to address bridge
strike issues at Main South Line Bridge 43, the so-called "Ti...
Options for ballast replacement in Auckland
Partially successful.
Hi there - to be honest, I have no idea if ideas like that were explored.
Let me ask the project team and get back to you.
Cheers - and have a great C...
Good afternoon Colby
Thank you for getting in touch with KiwiRail with your ideas for how to
improve our services for all New Zealanders.
Your...
Good afternoon Barry
My apologies - this had been responded to - although sometime our send-aware system blocks external emails with attachments if the...
Total number of non-compliant level rail crossings and how many have been upgraded with financial support or as a joint venture with a developer
Response by KiwiRail to Jessica Dingle on .
Awaiting classification.
Good afternoon
I'd like to acknowledge receipt of your official information request for information on non-compliant rail crossings.
We received your...
Tender Award - Southern Stations Project - Design
Response by KiwiRail to Charlene van der Merwe on .
Successful.
Good afternoon Charlene
We can advise the successful tender was awarded to Aurecon.
Kind regards
Dave
Dave Allard | Government...
Tender Award - Rail Network Growth Impact Management (RNGIM) programme.
Response by KiwiRail to Charlene van der Merwe on .
Successful.
Dear Charlene,
I refer to your request asking –
GETS 24188020 - Rail Network Growth Impact Management (RNGIM) programme.
Please may you k...
GETS 24371794 - (601002) Contract Management P2P - Award details
Response by KiwiRail to Charlene van der Merwe on .
Successful.
Good afternoon Charlene
I can advise that this tender has not been awarded as yet.
If you would like to email me at [email address] then we can keep...
GETS 24761201 - 2021/387 Millennium Centre Refurbishment
Response by KiwiRail to Charlene van der Merwe on .
Successful.
Good afternoon Charlene.
I can advise that this tender has not been awarded as yet.
As noted in an earlier response, you are welcom...
Safety assessments for Marsh's Road Railway Crossing, Rangiora
Response by KiwiRail to Patrick Dunford on .
Successful.
Good afternoon Patrick
I have tried contacting you to see if there was a better contact address
for you, but no luck.
Please find attached our...
Good afternoon
Following up on the below – is there a email to contact you through?
Cheers
Dave
Dave Allard | Senior Government Re...
Locomotive Mean Distance Between Failures (MDBF)
Awaiting classification.
Good afternoon Lewis
Please find the attached.
As noted previously there is considerable fluctuation in the figures from
month to month, w...
Ross Hill Tunnel (NAL Tunnel No.7) Tunnel upgrade design reports
Response by KiwiRail to Andrew Jones on .
Awaiting classification.
Good afternoon
Please find the attached.
Any questions, please get in touch.
This information has been released under the OIA. You have the right to...
Could you please provide all information about the subsidence issue on the Western line train in Auckland in October 2022, including but not limited...
Good afternoon George.
Thank you for your OIA request asking for - a current scheduled completion
date of IRex, and key milestone dates, in part...
Good afternoon Tommi
Please find attached the relevant document which refers to put KiwiRail livery.
We trust this answers your query, but any further...
Afternoon Patrick.
The advice I have received is that while the station building presently houses signals and telecommunications equipment, we aren't...
New Capital Connection Rolling Stock - Provision for bicycles
Response by KiwiRail to Richard Young on .
Long overdue.
Thank you for your email.
I am out of the office returning on Tuesday 5 April 2022.
I have limited access to phone/email but will respond on my ret...
Marsden Point Line NZUP delivery case
Response by KiwiRail to Daniel Palenski on .
Partially successful.
Good afternoon Daniel
We have received your enquiry as to the detailed business case for the Marsden Point line.
Please be advised KiwiRail is curren...
Feasibility study for the stratford - Okahukura line
Response by KiwiRail to Matthew Maxwell on .
Long overdue.
Good afternoon Matthew
I'd like to acknowledge receipt of your official information request for information on the Stratford - Okahukura line.
We rece...
Feasibility report into passenger rail service on West Coast of South Island
Response by KiwiRail to Nick Farlow on .
Successful.
Good afternoon Nick
Please find attached, as requested a copy of the Hokitika to Westport
feasibility study.
You have the right to seek an...
Stratford - Okahukura Line Feasibility Report
Response by KiwiRail to Peter Hodkinson on .
Successful.
Good morning Peter
My apologies I had it noted that you had received these reports - clearly not the case.
Please find the attached.
Cheers
Dave...
Improvements to Midland Line / Main South Line connectivity at Rolleston
Response by KiwiRail to Patrick Dunford on .
Successful.
Good afternoon Patrick.
To answer your query - Waka Kotahi NZTA is suggesting it will be possible
to provide improved connectivity at Rolleston...
Heritage steam ban KiwiRail South Island network
Awaiting classification.
Good afternoon Colby
Thank you for your request asking - I am formally requesting to know the
official reason why Kiwi Rail is (from 2020) not all...
Good afternoon Carl
Please find an update on the progress of the EF class as per below.
As at the last update provided to our stakeholders, good prog...
Only requests made using FYI are shown. ?
More about this authority
Home page of authorityView email address
Ask us to update Official Information email