Requests similar to 'Auckland Rail Network Questions' (page 6)
Central interceptor - non transparency
Response by Auckland Council to C Stuart C on .
Partially successful.
Good Afternoon C Stuart C
Attached is the response from Watercare Services Limited to your Official Information Request dated 25 May 2019
Rob Fisher
C...
And trying again
From: Dave Allard
Sent: Monday, November 4, 2024 6:15 PM
To: [FOI #28668 email]
Subject: RE: Official Information request - P...
Train Punctuality, Delay Reasons, and Mitigation (Wellington-bound Services, 7:00–9:30am)
Awaiting classification.
Tçnâ koe
Request for information 2025-200
I refer to your request for information dated 27 June 2025, which was
received by Greater Wellin...
Dear Sir/Madam
We are writing in response to your Official Information Act 1982 request
dated 4 September 2016 requesting information on the fut...
Available Heritage Crews for Mainline Operations
Response by KiwiRail to Iain Palmer on .
Successful.
Good afternoon Iain
Thank you for your email dated 23 May 2017, received by KiwiRail on 24 May
2017, in which you make the following request:...
Dear Sir/Madam
We are writing in response to your Official Information Act 1982 requests
dated 4 November 2016 requesting information on various...
Dear Benjamin, please find attached our response for your OIA request for
the a copy of the Wellington Risk Study.
Kind regards
The OCU Te...
Good evening Andrew,
Please find attached a response from Hon Simeon Brown.
Regards,
Office of Hon Simeon Brown
Minister of Transpo...
Dear Sir/Madam
We are writing in response to your Official Information Act 1982 request
dated 4 November 2016 requesting information on the stat...
Does KiwiRail pay rates on vacant land it owns?
Response by KiwiRail to Brent Hubbard on .
Successful.
Dear Mr Hubbard
Thank you for your email to KiwiRail of 29 March 2017, in which you make
the following request:
· Does your organi...
Good afternoon Peter.
I’m pleased to respond to your recent OIA request asking for information
on our freight business.
Please find below a li...
Project Outcomes
Response by New Zealand Transport Agency to Stephanie Pretorius on .
Awaiting classification.
Kia ora Stephanie
Please find attached the response to your request of 26 May 2025 for
information under the Official Information Act 1982.
...
Dear Mr Mills
Thank you for your email dated 13 January 2015 requesting the following information under the Official Information Act 1982 "if KiwiRail...
Track activity on the Shands Spur, Hornby, Christchurch
Response by KiwiRail to David Palmer on .
Successful.
Good evening David
Please find our reply below.
1. How many train movements occurred on the Shands Rd/Hornby branch spur in the last 12 months?
The...
Stratford - Okahukura Line Feasibility Report
Response by KiwiRail to Peter Hodkinson on .
Successful.
Good morning Peter
My apologies I had it noted that you had received these reports - clearly not the case.
Please find the attached.
Cheers
Dave...
Kia ora Peter,
I'd like to acknowledge receipt of your official information request for information on passenger rail diesel consumption.
We received...
Request for ATs CCFAS2 Project Information
Response by Auckland Transport to Ben Hassall on .
Partially successful.
Kia Ora Mr Hassell
We refer to your request for official information dated 7 March 2019
regarding Auckland Transport's Centre City Future Access...
Opus Redoubt Road - Mill Road Corridor Study
Response by Auckland Transport to Redoubt Ridge Environmental Action Group on .
Handled by post.
Dear Sir/Madam,
Please find attached the “Redoubt Road – Mill Road Corridor Study Final
Project Feasibility Report” requested from Auckland Tran...
Dear Mr Hawke
We refer to your last correspondence concerning this matter of 21 November
2016 and wish to apologise for the delayed response to...
Good afternoon Mike
Please find the attached.
Kind regards
Dave
Dave Allard | Government Relations Advisor
DDI: +64 4 498 3218
Level 4, Wellingto...
In progress and planned construction/maintenance
Response by KiwiRail to Connor Johnson on .
Partially successful.
Good afternoon Connor
Thank you for your request.
Information on our major projects, including the Northland Rail Rejuvenation, Wellington/Wairarapa...
Request for revenue and expenditure information used in calculating the 2018 Farebox Recovery Ratio in the 2018 Fare Review
Response by Wellington Regional Council to Tony Randle on .
Partially successful.
Dear Mr Randle
Attached is our response to your recent OIA 2018-100 plus two attachments.
Yours sincerely
Helen Plant
Helen Plant | Exe...
Re-request for 2018/19 and 2019/20 Annual Plan and Fare Review calculation information
Response by Wellington Regional Council to Tony Randle on .
Partially successful.
Dear Mr Randle,
Please see attached the response to OIA 2019-349.
Thank you.
Yours sincerely,
Daniela Theodorou |
Kaiāwhina M...
Good afternoon Cody
Please find the attached which covers your three requests.
Apologies for the delay.
Kind regards
Dave
Dave Allard | Senior Gov...
Tender Award - Rail Network Growth Impact Management (RNGIM) programme.
Response by KiwiRail to Charlene van der Merwe on .
Successful.
Dear Charlene,
I refer to your request asking –
GETS 24188020 - Rail Network Growth Impact Management (RNGIM) programme.
Please may you k...