Requests similar to 'Te Huia Safety Case' (page 6)
Good morning please find attached the response to your request.
Kind regards
Dave
Dave Allard | Government Relations Advisor
Level...
NIMT electric locomotives and Electrification
Response by KiwiRail to Iain Palmer on .
Partially successful.
Good morning Mr Palmer
We refer to your Official Information Act 1982 request dated 1 January
2016 containing the following questions:
Dur...
Detailed Plan to commission and fully operationalise the Auckland CRL
Response by KiwiRail to Jon Eriksen on .
Long overdue.
Good afternoon Jon
Thank you for your request, as per the below.
A quick email to acknowledge receipt, we are just scoping your request out at the mom...
Support/Cost to Mainstream Green
Response by Hamilton City Council to Geoff Kreegher on .
Successful.
Kia ora,
We refer to your information request below. Hamilton City Council provides
the following response.
Your request:
Mainstream...
Good afternoon Julian
Please find attached the list as requested.
Any further questions, please get in touch.
Kind regards
Dave
Dave Allard | Gov...
Monies paid to consultants and other stakeholders for station renaming
Response by Auckland Transport to Jai Ganesh on .
Information not held.
Good afternoon
Please find our response to your OIA request, Transferred to KiwiRail from
Auckland Transport.
Kind regards
Dave
...
Reuse of Addington Junction site to reinstate eastward facing track
Response by KiwiRail to Patrick Dunford on .
Successful.
Good afternoon Patrick
Please find attached our response to your query.
Kind regards
Dave
Dave Allard | Government Relations Advisor
Level 4, Well...
Good afternoon
Please find the attached.
Kind regards
Dave
Dave Allard | Senior Government Relations Advisor
DDI: 027 201 8182...
Total number of freight trains using rail leaving Tauranga Port travelling North
Response by KiwiRail to Janene Pearce on .
Successful.
Good afternoon Janene
Please find the table below in response to your query.
Any further questions, please get in touch.
Total Freigh...
DL class locomotives mean distance before failure
Response by KiwiRail to Lewis Holden on .
Successful.
Good afternoon Lewis
As clarification, can you please advise where in 2012 KiwiRail published a
comparison between the new DL class locomotives...
Good morning
Please find our response below.
Response:
Please be advised we are declining your request for all responses to the
tend...
Information relating to the track closures announced 3rd October
Response by Auckland Transport to J Turner on .
Successful.
Kia ora J Turner
I’ve attached the official information you asked for
On 4/10/2022 you asked for information relating to the recently announced...
Good afternoon Cody
Our response below -
KiwiRail does not have any current upgrade plans for the Amyes/ Shand Road level crossing in the next 10 yea...
Correspondence KiwiRail has about the business park development at Benmore Crescent, Manor Park Lower Hutt
Response by KiwiRail to Anne Alkema on .
Successful.
Good afternoon Anne
Apologies, it seems we are having issues with responding to FYI.org requests.
Please find our response below.
I have checked in...
Good afternoon
Please find the attached.
Kind regards
Dave
Dave Allard | Government Relations Advisor
Level 4, Wellington Ra...
Request for Arrangement Plans for the Interislander Ferry 'DEV Aratere'.
Response by KiwiRail to Bryce Ivey on .
Successful.
Good evening Bryce
Apologies in the delay in responding, it appears the response didn't send.
Please find the attached, let me know if these work for...
Meterage for locations on the Kiwirail network
Information not held.
Good afternoon John
Thank you for your request for - a spreadsheet containing the meterage (i.e., km from the beginning of the line) for all named loc...
Good afternoon Ryan
Please find our response below.
Information on the sale and purchase can be found at the links below that
are publicly...
Dear Trainluva7
We are writing in response to your Official Information Act 1982 requests
dated 9 December 2016 requesting information on the st...
Good morning Stephen, please find attached our response to your OIA
request in regard to KiwiRail locomotive statuses.
Kind regards
Helen...
Details of funding the Capital Connection
Response by New Zealand Transport Agency to Lance Watson on .
Successful.
Good afternoon Lance
As per the below, we received the transfer of your OIA request asking:
1. What was the revenue made from ticket sales?...
GETS 24371794 - (601002) Contract Management P2P - Award details
Response by KiwiRail to Charlene van der Merwe on .
Successful.
Good afternoon Charlene
I can advise that this tender has not been awarded as yet.
If you would like to email me at [email address] then we can keep...
OIA request on Kiwirail Auckland Rail Network Rebuild
Response by Michael Wood to Kris Bainbridge on .
Successful.
Good afternoon Kris
Please find our response below.
I refer to your request dated 10 October 2022, transferred to KiwiRail
from Minister W...
Government funding increase to fix train lateness on the Wairarapa Line
Response by New Zealand Transport Agency to Tony Randle on .
Partially successful.
Dear Tony
Please find attached Dave Brash’s response to your further request for
information on funding for the Wairarapa Line, as per your 9 Oc...
Critical Path Project Plan for upgrading the Picton Rail Enabled Ferry Terminal
Response by KiwiRail to Jon Eriksen on .
Awaiting classification.
Good morning Jon
We have received your request, as per the below.
This information however is not held by KiwiRail, and instead is the responsibility...