Requests similar to 'Rolleston suburban passenger proposals' (page 4)

Capital Connection Costs and Patronage
Response by KiwiRail to Tony Randle on .
Successful.
Good morning Tony I'd like to acknowledge receipt of your official information request for information on the Capital Connection. We received your re...
Further Capacity Improvements (WMUP 7)
Response by KiwiRail to T.J. Pohl on .
Successful.
Good afternoon TJ   A quick email to acknowledge receipt of your request. We received your request on 6 January 2025, and will endeavour to respo...
Meterage for locations on the Kiwirail network
Response by KiwiRail to John Voss on .
Information not held.
Good afternoon John Thank you for your request for - a spreadsheet containing the meterage (i.e., km from the beginning of the line) for all named loc...
Good afternoon   Thank you for your enquiry, received through the FYI.org website and noted as the below.   In 2024, has KiwiRail made, /or do...
Options for ballast replacement in Auckland
Response by KiwiRail to R S Grant on .
Partially successful.
Hi there - to be honest, I have no idea if ideas like that were explored. Let me ask the project team and get back to you. Cheers - and have a great C...
Advice on recent Crown investments
Response by KiwiRail to Barry Garrick on .
Long overdue.
Good evening Barry I'd like to acknowledge receipt of your official information request for information as per the below We received your request on...
Interislander using google suit (google docs, sheets ect)
Response by KiwiRail to Luna on .
Information not held.
Good evening I'd like to acknowledge receipt of your official information request for information as per the below. We received your request on 5 July...
Good afternoon Adrian I'd like to acknowledge receipt of your official information request dated 4 August 2024, for information on ECI contractor spen...
Train Control Operating Irregularities
Response by KiwiRail to A. Puohotaua on .
Refused.
Good afternoon A quick email to acknowledge receipt of your official information request for information on Train control irregularities as per the b...
Which DX is to be sedated for preservation
Response by KiwiRail to Colby James on .
Successful.
Good morning Colby Just letting you know we've received your request and I've passed it onto our Rolling Stock team. The two guys who will have this i...
Good afternoon   Please find attached KiwiRail’s response to your OIA request.   Kind regards   Dave     Dave Allard  | Government Re...
Non-refundable costs paid to HMD
Response by KiwiRail to Michael Steere on .
Refused.
Good morning Michael   Thank you for your enquiry, asking for information on:   1. Please inform me how much money has already been paid to Hyu...
Titanic references
Response by KiwiRail to Tony on .
Information not held.
Good afternoon Tony   Thanks for your enquiry.   I can advise that under Section 18(e) we are declining your request, as no such reports or re...
Good afternoon Adrian I'd like to acknowledge receipt of your official information request dated 4 August 2024, for information on the design team spe...
All information regarding meetings and discussions due to SPAD
Response by KiwiRail to Hillman Humffreys on .
Awaiting classification.
Will do Hillman, I'll get our IT team onto that for you. Note - we'll send the links to your personal email (rather than FYI.org) as the files will co...
Good afternoon Nick   I refer to your official information request dated 13 January 2020, for a copy of the feasibility report into the passenger...
North Auckland Line under utilised
Response by KiwiRail to Niall Robertson on .
Long overdue.
Good afternoon Niall Confirming receipt of your request. We are working on a response for you and will be back in touch shortly. I note the timefram...
Track conditions Swanson to Huapai
Response by KiwiRail to Niall Robertson on .
Long overdue.
Good afternoon Niall Confirming receipt of this request as well. We will combine the two answers, and as noted we are working on a response for you a...
KiwiRail Locomotive Information
Response by KiwiRail to Steven on .
Long overdue.
Good afternoon Steven No, I'm afraid I can't see any record of a request for Locomotive information being received, and I apologise your request doesn...
In progress and planned construction/maintenance
Response by KiwiRail to Connor Johnson on .
Partially successful.
Good afternoon Connor Thank you for your request. Information on our major projects, including the Northland Rail Rejuvenation, Wellington/Wairarapa...
Northland Rail Line beyond Kauri
Response by KiwiRail to Andrew Jones on .
Successful.
Good afternoon Andrew,   The planned rail upgrades between Kauri and Otiria are currently paused, pending the Government's decision about building...
This transfer expires on 2023-07-17 [1]Click 'Download images' to view images [2][email address] sent you rpt_4925_Northern_Carterton_230125.pdf 1...
Heritage Train SPAD incidents
Response by KiwiRail to Lloyd Davies on .
Information not held.
Good morning Lloyd Apologies for slightly delay, I was hoping to acknowledge and respond all in one, as I wasn't sure if we'd hold the information req...
West Coast (SI) Coal Various
Response by KiwiRail to Lindon Boyce on .
Successful.
Good afternoon Lindon   Please find our responses below.   * The key coal loading facility on the West Coast is Ngakawau.  We also regularly load...
Good afternoon Regan, and thank you for your enquiry. We are declining your request in full under sections 9(2)(b)(ii) and 9(2)(i) – Commercial inform...