Travel time for freight services between Auckland and Wellington
Partially successful.
Kia ora John,
Please find attached our response to your OIA request regarding freight services between Auckland and Wellington.
Ngā mihi
Laura
Lau...
Request for the 2017 Capital Connection Business Case
Response by Manawatu-Wanganui Regional Council to Tony Randle on .
Partially successful.
Good afternoon Tony,
Thank you for your request under the Official Information Act for
information relating to the business case completed for p...
Rail patronage data by station for January-June 2013
Response by Auckland Transport to Andrew Walters on .
Partially successful.
Good afternoon Mr Walters
Please find attached the response for information requested from Auckland
Transport under the Local Government Official In...
Rail Level Crossing Removal Feasibility Report – Volume 1, Reference 236852, Revision 4 dated 11 February 2014
Response by Auckland Transport to Harriet Gale on .
Partially successful.
Dear Harriet
Thank you for contacting Auckland Transport on 5 February 2017 requesting
the Full Rail Level Crossing Removal Feasibility Report....
Rural school bus routes and school closures
Response by Ministry of Education to F. Darren on .
Awaiting classification.
[IN-CONFIDENCE - RELEASE EXTERNAL]
Tēnā koe Mr Darren
Please find attached a response to your request under the Official
Information Act.
...
Track activity on the Shands Spur, Hornby, Christchurch
Response by KiwiRail to David Palmer on .
Successful.
Good evening David
Please find our reply below.
1. How many train movements occurred on the Shands Rd/Hornby branch spur in the last 12 months?
The...
The Cost and Benefit calculations for the NIRP - North Island Regional Passenger Rail Connector
Response by Ruapehu District Council to Tony Randle on .
Long overdue.
Date 8 November 2022
Tony Randle
Email: [1][FOI #20999 email]
Dear Tony
REQUEST FOR INFORMATION;
LOCAL GOVERNMENT...
Good afternoon Harriet,
We refer to your request for information dated 22 June 2017 in which you
ask for:
1. Marsden Point Rail Link...
Cause of signaling fault for trains.
Response by Wellington Regional Council to Andrew Crow on .
Successful.
Dear Andrew Crow, please find attached our response to your OIA request,
OIA2018.07, seeking information on a signals fault on the Hutt Line in
Febru...
Wiatakere Tunnel upgrade for transport link to Kumeu etc.
Response by KiwiRail to Graeme Hammonds on .
Successful.
Good afternoon
Please find attached KiwiRail’s response to your OIA request.
Kind regards
Dave
Dave Allard | Government Re...
KRL board decision not to build to NorthPort
Request sent to KiwiRail by Niall Robertson on .
Awaiting classification.
Kia ora,
Considering the considerable recent geo-tech investigations and land purchases for a rail line to NorthPort, not to mention the considerabl...
Request for contract to provide Wellington Metro Railway Business Cases
Response by KiwiRail to Tony Randle on .
Long overdue.
Good afternoon
We acknowledge receipt of the below Official Information Act 1982 request.
Under the Act, KiwiRail has up to 20 working days...
Request for ATs CCFAS2 Project Information
Response by Auckland Transport to Ben Hassall on .
Partially successful.
Dear Ben,
We refer to your request for official information dated 30 May 2019.
Please find attached response for information requested unde...
Train Punctuality, Delay Reasons, and Mitigation (Wellington-bound Services, 7:00–9:30am)
Awaiting classification.
Tçnâ koe
Request for information 2025-200
I refer to your request for information dated 27 June 2025, which was
received by Greater Wellin...
Industrial action 8th December 2017
Response by Auckland Transport to David Brotherhood on .
Successful.
Dear Mr Brotherhood
Thank you for your email.
At the outset, I sincerely apologise for the administrative oversight. I
had assumed th...
Airport Rail. Methodology and Video Release for the Airport Line
Response by Auckland Transport to Ben Ross on .
Successful.
Dear Mr Ross
Thank you for your request for information relating to studies into rail
options to the airport.
Please find attached a respo...
Request for reports and correspondence on the New timetable for Johnsonville train line
Response by Wellington Regional Council to Tony Randle on .
Successful.
Dear Mr Randle
Attached is our letter of response to OIA Request No. 2015/067 along with
22 Attachments (this includes the list of attachments)....
Dear Mr Crow
Attached is our response to your recent OIA.
Yours sincerely
Nichola
Nichola Powell |
Kaiāwhina Matua ki te Kaiwhaka...
Request for the Crown business cases for the the Wairarapa Line and to remove rail network constraints
Response by Wellington Regional Council to Tony Randle on .
Partially successful.
Dear Mr Randle
Please find attached three attachments to your OIA request 2017-144.
1. Inform request of transfer
2. A copy of t...
Number of Sworn and Non-sworn Employees
Response by New Zealand Police to Thomas Holmes on .
Successful.
Good afternoon Thomas
Please see attached your response to OIA received by the NZ Police on
09/03/2020. We hope you can accept our apology for th...
Addresses of all in-store Lotto retailers in New Zealand as of September 1, 2025.
Response by New Zealand Lotteries Commission to K Leau on .
Awaiting classification.
Hello
Please find the response to your OIA request make on 12 September 2025.
Please let me know if you have any further questions.
Regards
Desre H...
Double tracking on the NIMT between Amokura and Te Kauwhata and Ngaruawahia Bridge
Response by KiwiRail to Isaac Morrison on .
Partially successful.
Kia ora Isaac,
Please find the below in response to your official information request for
information on whether a business case was performed o...
Warrant and Certificate of Fitness by Area
Response by New Zealand Transport Agency to Adam Ward on .
Successful.
Dear Adam
Please find attached the response to your below request for information
under the Official Information Act 1982 of 2 May 2017.
R...
Good morning TJ
Thanks for your patience.
Please find attached the technical report that underpinned the Further Capacity Improvements Study, we have...
Heritage steam ban KiwiRail South Island network
Awaiting classification.
There has been much speculation as to why Kiwi Rail is not allowing steam trips to run past Kaikōura to Invercargill, for example the“Great Southern...