Dear Auckland Transport,

I hereby request the following information under the Official Information Act 1982 regarding recent design changes to Project K (Karanga-a-hape Station precinct integration project):

1. Consultation Documentation
a) Provide all records of consultation (including dates, participants, and methodologies) used to justify the redesign of:
- East Street cycleway replacement with sharrows
- Cross Street footpath reductions

b) Specifically identify which business owners/residents provided feedback that led to these changes, including:
- Full correspondence/meeting notes
- Quantitative analysis showing how this feedback outweighed 2023 consultation results (349 survey responses, 391 Social Pinpoint comments, 45 postal submissions)

2. Strategic Justification
a) Explain how the redesign aligns with:
- Auckland 2050 Plan
- City Centre Masterplan (specifically Transformational Move 5)
- Access for Everyone (A4E) strategy
- Transport Emissions Reduction Pathway (TERP)
- Vision Zero commitments

b) Provide the cost-benefit analysis showing how vehicle access improvements outweigh:
- Loss of pedestrian space for 40,000 daily CRL users
- Removal of existing cycle infrastructure
- Contradiction of City Centre Targeted Rate funding conditions

3. Design Process Records
a) All internal communications (2024-present) regarding:
- Rationale for bypassing Waitematā Local Board approval
- Consideration of CCO obligations under Local Government Act
- Risk assessments regarding $4.5M City Centre Targeted Rate funding

b) Technical reports justifying claims that redesigned features:
- "Maintain pedestrian safety" without raised crossings
- "Maximise CRL benefits" while reducing pedestrian priority
- Align with CRL's $5.5B investment objectives

Please respond in writing within 20 working days. If any information cannot be released, cite specific OIA provisions and provide redacted versions where possible.

Regards,
Zak Morrison

Link to this

From: AT Official Information (AT)
Auckland Transport


Attachment image.png
19K Download


Kia ora Isaac,

Auckland Transport (AT) acknowledges receipt of your request for official
information dated 1 May 2025 for consultation documentation,
correspondence, strategic alignment, cost benefit analysis, design process
records, and technical reports in relation to Project K.

 

We hope to respond to your request as soon as possible, but no later
than 29 May 2025, which is 20 working days after the day your request was
received.

We may contact you if we require clarification, more time to respond, or
if your requested information is held by another agency. 

Your case is being managed by Varsha, who is one of our LGOIMA Business
Partners. If you have any further queries, you can contact the team on
(09) 355 3553 during business hours, quoting Local Government Official
Information request number CAS-1105925-L2G3J7. 

 

Ngā mihi, 

Ane | Customer Care Coordinator 
Customer and Network Performance 
Auckland Transport
20 Viaduct Harbour Avenue, Auckland 1010
[1]www.at.govt.nz

[2]image

 

show quoted sections

Link to this

From: AT Official Information (AT)
Auckland Transport


Attachment image.png
27K Download


Kia ora Isaac 

 

I’m the LGOIMA Business Partner who’s looking into your official
information request

My name is Varsha and I’m a LGOIMA Business Partner at Auckland Transport.

 

I’m responsible for looking into the official information request you made
on 1/05/2025 for consultation documentation, correspondence, strategic
alignment, cost benefit analysis, design process records, and technical
reports in relation to Project K.

 

We searched our email database for all emails relating to Project K, our
search returned approximately 3000 emails which is a substantial result.
It was take us approximately 150 hours to complete this part of your
request. Auckland Transport offers five hours of non-chargeable
administration time for free. This means the 145 additional hours will be
at a cost to you if you wish to obtain the full request as it's currently
framed. If you are unable to refine your request or if no refinement is
received, it is likely your request will be refused under section 17(f) of
the Local Government Official Information and Meetings Act 1987 (LGOIMA)
because it amounts to substantial collation.

We want to help you with this request and ask if you are able to refine
what you are requesting, such as the timeframe or if you are after a
specific piece of information? If you can get back to  me with a
refinement by Friday, May 30, 2025, that would be much appreciated.

Please let me know how you want me to proceed. 

 

You have the right to seek an investigation and review by the Ombudsman of
this decision. Information about how to make a complaint is available
at [1]www.ombudsman.parliament.nz or freephone 0800 802 602.

 

Ngā mihi

Varsha 

LGOIMA Business Partner 

 

Auckland Transport 

20 Viaduct Harbour Avenue, Auckland 1010

[2]www.at.govt.nz

 

Important notice: The contents of this email and any attachments may be
confidential and subject to legal privilege. If you have received this
email message in error please notify us immediately and erase all copies
of the message and attachments; any use, disclosure or copying of this
message or attachments is prohibited. Any views expressed in this email
may be those of the individual sender and may not necessarily reflect the
views of Auckland Transport.

References

Visible links
1. http://www.ombudsman.parliament.nz/
http://www.ombudsman.parliament.nz/
2. http://www.at.govt.nz/

Link to this

From: Isaac Morrison

Kia ora Varsha,

Thank you for your reply, I understand that there is a lot of information however I have two questions. First how much would it cost to obtain the full request? Secondly, if I was to re-frame the timescale then I would like to know when AT first started to be contacted by/contacted with external parties that led to these changes being considered?

I look forward to hearing from you.

Ngā mihi,

Isaac Morrison

Link to this

From: AT Official Information (AT)
Auckland Transport

Hi Isaac, 

 

The search results provided to you is dated from May 2024 which is when
conversations began regarding Project K changes. 

 

AT charges $47.50 per half hour, so 145 hours would cost $13,050. That
said, I'd like to remove the need for a charge by working with you on
refinements until it reaches a stage that it doesn't affect our day to day
operations. 

 

Is there something specific you after in terms of correspondence? 

 

Thanks,

Varsha

LGOIMA Business Partner 

 

 

------------------- Original Message

show quoted sections

Please use this email address for all replies to this request:
[FOI #30876 email]

Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
[4]https://urldefense.com/v3/__https://fyi....

If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.

-------------------------------------------------------------------

Important notice: The contents of this email and any attachments may be
confidential and subject to legal privilege. If you have received this
email message in error please notify us immediately and erase all copies
of the message and attachments; any use, disclosure or copying of this
message or attachments is prohibited. Any views expressed in this email
may be those of the individual sender and may not necessarily reflect the
views of Auckland Transport.

References

Visible links
1. https://urldefense.com/v3/__http://www.o...
2. https://urldefense.com/v3/__http://www.o...
3. https://urldefense.com/v3/__http://www.o...
4. https://urldefense.com/v3/__https://fyi....

Link to this

From: Isaac Morrison

Kia ora Varsha,

I think that might be a tad outside my budget, I guess from the date the conversations began. What I am wanting to understand is how these changes came to be implemented seemingly out of nowhere, what conversations and considerations took place. How did a project with popular broad and public approval get changed into something that flies in the face of not only local support but international practice.

Also just to reaffirm outside of all the communications I would still like to get information in relation to the second and third points I made in the original request.

I am more than happy to clarify other areas if needed. I look forward to hearing from you.

Ngā mihi,
Isaac Morrison

Link to this

From: AT Official Information (AT)
Auckland Transport

Hi Isaac, 

 

Thanks for your email. Your clarification below has been very helpful in
narrowing down the scope of the information. 

 

Regarding the remainder of your request, you are correct — I am currently
working on obtaining the information held by AT. Under the Local
Government Official Information and Meetings Act (LGOIMA), we are required
to notify you of our decision on your request no later than 20 working
days after receiving it. However, due to the scope of your request —
including the recent refinements — we will not be able to meet this
timeframe. We are therefore extending the deadline for our decision to 11
June 2025, or sooner if possible. This extension is made in accordance
with section 14(1) of the LGOIMA, due to the substantial volume of
information involved.

 

You have the right to seek an investigation and review by the Ombudsman of
this decision. Information about how to make a complaint is available
at [1]www.ombudsman.parliament.nz or freephone 0800 802 602.

 

I will be in contact closer to 11 June 2025, or sooner. 

 

Kind regards,

Varsha

LGOIMA Business Partner 

 

 

show quoted sections

Link to this

From: AT Official Information (AT)
Auckland Transport

Kia ora Isaac, 

 

We are granting your request, which means we will be provide you with the
information we hold. We aim to have this with you by Friday 13 June, or
sooner. 

 

Kind regards,

Varsha

LGOIMA Business Partner 

 

 

show quoted sections

Link to this

From: AT Official Information (AT)
Auckland Transport

Kia ora Isaac, 

 

I had hoped to have the information ready today but it's taking us a
little longer. The response is currently with our Group Manager for their
review. I hope to have the information with you by Thursday 19 June 2025. 

 

Kind regards,

Varsha

LGOIMA Business Partner 

 

 

show quoted sections

Link to this

We don't know whether the most recent response to this request contains information or not – if you are Isaac Morrison please sign in and let everyone know.

Things to do with this request

Anyone:
Auckland Transport only: