SH49 intersection and Teitei Drive formation
Ohakune Ratepayers and Residents' Society Inc made this Official Information request to Ruapehu District Council
This request has an unknown status. We're waiting for Ohakune Ratepayers and Residents' Society Inc to read recent responses and update the status.
From: Ohakune Ratepayers and Residents' Society Inc
Dear Ruapehu District Council,
I write to you with regards to contents of response document LGOIMA 000055.pdf dated 20 September 2024
References:
- Original Construction cost $802k as documented on Page 9 - Briefing form: Project Sheet
- Estimated Construction cost for Option A at $920k, Option B $770k
- RDC to fund $150k on page 44
- Page 68 - project completion report
Questions
1./ Originally estimated to be ~$773k and also documented as 802,500. Please provide the total cost of the project
2./ Page 44, RDC to fund $150k, please provide actual costs RDC paid after completion
3./ MBIE provided funding of $622,500 (Claim #MFF-R2-004, the project tasks included the relocation of powerlines & the shifting of road access onto road reserve, this is also stated in the grant application forms to MBIE.
3.1./ Please provide dates the powerlines were moved
3.2./ Please provide costs incurred for moving the powerlines
3.3./ If the powerlines were not moved, please provide the quotes, estimates or discussions around the moving of powerlines
3.4./ Please provide evidence that the access was shifted onto road reserve
4./ Please provide other funding sources and the amounts, terms and agreements for funding.
5./ We have obtained the COC (#22903) for the public toilet. Please provide any other COC's or Consents or onsite project sign off documents associated with this project
Yours faithfully,
Ohakune Ratepayers and Residents' Society Inc
From: Info
Ruapehu District Council
Kia ora,
REQUEST FOR INFORMATION
LOCAL GOVERNMENT OFFICIAL INFORMATION AND MEETINGS ACT 1987
Thank you for your Request for Official Information received on 4 November 2024 relating to formation costs of Teitei Drive.
We will endeavour to respond to your request as soon as possible with a decision and in any event no later than 2 December 2024, being 20 working days after the day your request was received. If we are unable to respond to your request by then, we will notify you of an extension of that timeframe.
If you have any queries, please feel free to contact [Ruapehu District Council request email]. If any additional factors come to light which are relevant to your request, please do not hesitate to contact us so that these can be considered.
Please note that requests may incur a reasonable charge. We will contact you with an approximate cost, before we proceed, if applicable.
Ngā mihi
INFO TEAM
show quoted sections
Original Message-----
From: Ohakune Ratepayers and Residents' Society Inc <[FOI #29045 email]>
Sent: Monday, 4 November 2024 12:51 pm
To: Info <[Ruapehu District Council request email]>
Subject: Official Information request - SH49 intersection and Teitei Drive formation
Warning: This email is from an External Sender. Do not click links or open attachments unless you recognize the sender and know the content is safe.
Dear Ruapehu District Council,
I write to you with regards to contents of response document LGOIMA 000055.pdf dated 20 September 2024
References:
- Original Construction cost $802k as documented on Page 9 - Briefing form: Project Sheet
- Estimated Construction cost for Option A at $920k, Option B $770k
- RDC to fund $150k on page 44
- Page 68 - project completion report
Questions
1./ Originally estimated to be ~$773k and also documented as 802,500. Please provide the total cost of the project
2./ Page 44, RDC to fund $150k, please provide actual costs RDC paid after completion
3./ MBIE provided funding of $622,500 (Claim #MFF-R2-004, the project tasks included the relocation of powerlines & the shifting of road access onto road reserve, this is also stated in the grant application forms to MBIE.
3.1./ Please provide dates the powerlines were moved 3.2./ Please provide costs incurred for moving the powerlines 3.3./ If the powerlines were not moved, please provide the quotes, estimates or discussions around the moving of powerlines 3.4./ Please provide evidence that the access was shifted onto road reserve
4./ Please provide other funding sources and the amounts, terms and agreements for funding.
5./ We have obtained the COC (#22903) for the public toilet. Please provide any other COC's or Consents or onsite project sign off documents associated with this project
Yours faithfully,
Ohakune Ratepayers and Residents' Society Inc
-------------------------------------------------------------------
This is an Official Information request made via the FYI website.
Please use this email address for all replies to this request:
[FOI #29045 email]
Is [Ruapehu District Council request email] the wrong address for Official Information requests to Ruapehu District Council? If so, please contact us using this form:
https://scanmail.trustwave.com/?c=8510&a...
Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://scanmail.trustwave.com/?c=8510&a...
If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.
-------------------------------------------------------------------
From: Info
Ruapehu District Council
Kia ora
Please find attached a letter of extension in relation to road formation costs on Teitei Drive as part of the Carrot Park Project.
Ngā mihi
INFO TEAM
show quoted sections
Original Message-----
From: Ohakune Ratepayers and Residents' Society Inc <[FOI #29045 email]>
Sent: Monday, 4 November 2024 12:51 pm
To: Info <[Ruapehu District Council request email]>
Subject: Official Information request - SH49 intersection and Teitei Drive formation
Warning: This email is from an External Sender. Do not click links or open attachments unless you recognize the sender and know the content is safe.
Dear Ruapehu District Council,
I write to you with regards to contents of response document LGOIMA 000055.pdf dated 20 September 2024
References:
- Original Construction cost $802k as documented on Page 9 - Briefing form: Project Sheet
- Estimated Construction cost for Option A at $920k, Option B $770k
- RDC to fund $150k on page 44
- Page 68 - project completion report
Questions
1./ Originally estimated to be ~$773k and also documented as 802,500. Please provide the total cost of the project
2./ Page 44, RDC to fund $150k, please provide actual costs RDC paid after completion
3./ MBIE provided funding of $622,500 (Claim #MFF-R2-004, the project tasks included the relocation of powerlines & the shifting of road access onto road reserve, this is also stated in the grant application forms to MBIE.
3.1./ Please provide dates the powerlines were moved 3.2./ Please provide costs incurred for moving the powerlines 3.3./ If the powerlines were not moved, please provide the quotes, estimates or discussions around the moving of powerlines 3.4./ Please provide evidence that the access was shifted onto road reserve
4./ Please provide other funding sources and the amounts, terms and agreements for funding.
5./ We have obtained the COC (#22903) for the public toilet. Please provide any other COC's or Consents or onsite project sign off documents associated with this project
Yours faithfully,
Ohakune Ratepayers and Residents' Society Inc
-------------------------------------------------------------------
This is an Official Information request made via the FYI website.
Please use this email address for all replies to this request:
[FOI #29045 email]
Is [Ruapehu District Council request email] the wrong address for Official Information requests to Ruapehu District Council? If so, please contact us using this form:
https://scanmail.trustwave.com/?c=8510&a...
Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://scanmail.trustwave.com/?c=8510&a...
If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.
-------------------------------------------------------------------
Ohakune Ratepayers and Residents' Society Inc left an annotation ()
16th of December 2024
From: Info
Ruapehu District Council
Kia ora,
Please find attached a response in relation to your LGOIMA request.
Ngā mihi
show quoted sections
References
Visible links
1. http://www.ruapehudc.govt.nz/
2. https://eservices.ruapehudc.govt.nz/onli...
Things to do with this request
- Add an annotation (to help the requester or others)
- Download a zip file of all correspondence
Ohakune Ratepayers and Residents' Society Inc left an annotation ()
2 December
Link to this