How was a red zone boundary boundary was drawn (or not)

Judy Grindell made this Official Information request to Canterbury Earthquake Recovery Authority

The request was refused by Canterbury Earthquake Recovery Authority.

From: Judy Grindell

Dear Canterbury Earthquake Recovery Authority,

SOUTHSHORE RED ZONE NORTH BOUNDARY:
I would like data for the criteria, 'tipping points' or parameters for each criterion, the weighting given to the various criteria within the decision framework, the margins of error for each and how these margins of error were factored in to the decision.

SOUTH NEW BRIGHTON TC3 AREAS:
I would also like the same data relating to the areas along Kibblewhite Street and estuary end of Beatty Street in South New Brighton to explain why these areas were zoned TC3.

BACKGROUND:
My previous request for this information was partially (slightly)successful in that I had a short discussion with Jan Kupec and I did get access to the geotechnical database and technical reports from GNS etc. While this has provided some of the previously 'missing data', I still have not had an explanation of the parameters used to determine where the boundary should go.

Explanations to date for the Southshore red zone boundary have been subjective: 'I didn't draw the boundary', 'the boundary has to go somewhere' and 'there's probably some buffer zones'. And various vague responses to my earlier request do not make sense in explaining why the northern boundary was drawn where it is. For example, Cera said in 30 Sept "the location of those properties zoned green in Southshore were done so on the basis that damage to land and homes can be addressed on an individual basis by homeowners working with EQC and their insurance company. This is in contrast to the properties on that Southshore boundary that ended up being zoned red. To fix the damage to land and properties in this area would have required area-wide engineering works (such as deep and wide zone of ground improvements along the estuary coastline) to address the potential for extensive area-wide lateral spread." This is true of houses immediately bordering the estuary along the spit. However, given that the TC3 house to the north of the red zone boundary is only 1 m from the fenceline (the boundary), I cannot see that explanation makes sense. The 4-6 houses in last block of Estuary Road before Halsey Street are some distance from the estuary. The lateral spread is concentrated along the estuary margins as was obvious on the ground and as is shown in the GNS Lidar report.

This weekend (15th & 16th Dec 2012) had higher tides than normal, which was interesting for the end of Kibblewhite Street ... TC3. The land inside the stopbank (which had to have emergency repairs to raise it considerably after Feb 2011) is lower than the high tide so river / estuary water pours up through the stormwater system and ponds behind the stopbank. Water was almost to the door of the last house. The houses along Kibblewhite St are very close to the estuary, and houses / drives show obvious lateral spread etc. Drilling indicates shallow aquifers at 26m.

Flooding, liquefaction and cracks were severe around the bridge after the earthquakes. The area around Beatty Street also showed very severe land cracking and lateral spreading after all the quakes. These areas are TC3.

I have been through a lot of the geotechnical database, GNS reports & T&T reports ... and the boundary decisions for both Southshore and South New Brighton seem to make less sense than ever.

SUBJECTIVE OR OBJECTIVE DECISIONS?:
Please inform me whether there were subjective decisions.

If not subjective, then please provide the information on which the decsions were made ... the criteria, 'tipping points' or parameters for each criterion, the weighting given to the various criteria within the decision framework, the margins of error for each and how these margins of error were factored in to the decision.

I look forward to your explanations so that I (and others) can see the clear evidence for your decisions and decision processes.

Yours faithfully,
Judy Grindell

Link to this

From: info (CERA)
Canterbury Earthquake Recovery Authority

Thank you for emailing the Canterbury Earthquake Recovery Authority.

We will respond to your request as soon as possible

In the meantime, please visit our website
[1]http://www.cera.govt.nz/ where answers to a number of frequently asked
questions can be found.

Thank you for your patience.

Regards

Canterbury Earthquake Recovery Authority.

------------------------------- This email and any attachments may contain
information that is confidential and subject to legal privilege. If you
are not the intended recipient, any use, dissemination, distribution or
duplication of this email and attachments is prohibited. If you have
received this email in error please notify the author immediately and
erase all copies of the email and attachments. The Canterbury Earthquake
Recovery Authority (CERA) accepts no responsibility for changes made to
this message or attachments after transmission from CERA. For further
information about CERA, please visit www.cera.govt.nz.
-------------------------------

References

Visible links
1. http://www.cera.govt.nz/

Link to this

From: info (CERA)
Canterbury Earthquake Recovery Authority

Dear Judy

Thank you for your email requesting information under the Official Information Act. A response will be supplied within 20 working days from 20 December 2012 in accordance with the requirements of the Act.

Best Regards
Kimberley
Community and Customer Services
Social and Cultural Recovery
Canterbury Earthquake Recovery Authority

T: 0800 7464 2372
W: www.cera.govt.nz

-----Original Message-----
From: Judy Grindell [mailto:[OIA #708 email]]
Sent: Thursday, 20 December 2012 11:37 a.m.
To: info (CERA)
Subject: Official Information Act request - How was a red zone boundary boundary was drawn (or not)

Dear Canterbury Earthquake Recovery Authority,

SOUTHSHORE RED ZONE NORTH BOUNDARY:
I would like data for the criteria, 'tipping points' or parameters
for each criterion, the weighting given to the various criteria
within the decision framework, the margins of error for each and
how these margins of error were factored in to the decision.

SOUTH NEW BRIGHTON TC3 AREAS:
I would also like the same data relating to the areas along
Kibblewhite Street and estuary end of Beatty Street in South New
Brighton to explain why these areas were zoned TC3.

BACKGROUND:
My previous request for this information was partially
(slightly)successful in that I had a short discussion with Jan
Kupec and I did get access to the geotechnical database and
technical reports from GNS etc. While this has provided some of the
previously 'missing data', I still have not had an explanation of
the parameters used to determine where the boundary should go.

Explanations to date for the Southshore red zone boundary have been
subjective: 'I didn't draw the boundary', 'the boundary has to go
somewhere' and 'there's probably some buffer zones'. And various
vague responses to my earlier request do not make sense in
explaining why the northern boundary was drawn where it is. For
example, Cera said in 30 Sept "the location of those properties
zoned green in Southshore were done so on the basis that damage to
land and homes can be addressed on an individual basis by
homeowners working with EQC and their insurance company. This is in
contrast to the properties on that Southshore boundary that ended
up being zoned red. To fix the damage to land and properties in
this area would have required area-wide engineering works (such as
deep and wide zone of ground improvements along the estuary
coastline) to address the potential for extensive area-wide lateral
spread." This is true of houses immediately bordering the estuary
along the spit. However, given that the TC3 house to the north of
the red zone boundary is only 1 m from the fenceline (the
boundary), I cannot see that explanation makes sense. The 4-6
houses in last block of Estuary Road before Halsey Street are some
distance from the estuary. The lateral spread is concentrated along
the estuary margins as was obvious on the ground and as is shown in
the GNS Lidar report.

This weekend (15th & 16th Dec 2012) had higher tides than normal,
which was interesting for the end of Kibblewhite Street ... TC3.
The land inside the stopbank (which had to have emergency repairs
to raise it considerably after Feb 2011) is lower than the high
tide so river / estuary water pours up through the stormwater
system and ponds behind the stopbank. Water was almost to the door
of the last house. The houses along Kibblewhite St are very close
to the estuary, and houses / drives show obvious lateral spread
etc. Drilling indicates shallow aquifers at 26m.

Flooding, liquefaction and cracks were severe around the bridge
after the earthquakes. The area around Beatty Street also showed
very severe land cracking and lateral spreading after all the
quakes. These areas are TC3.

I have been through a lot of the geotechnical database, GNS reports
& T&T reports ... and the boundary decisions for both Southshore
and South New Brighton seem to make less sense than ever.

SUBJECTIVE OR OBJECTIVE DECISIONS?:
Please inform me whether there were subjective decisions.

If not subjective, then please provide the information on which the
decsions were made ... the criteria, 'tipping points' or parameters
for each criterion, the weighting given to the various criteria
within the decision framework, the margins of error for each and
how these margins of error were factored in to the decision.

I look forward to your explanations so that I (and others) can see
the clear evidence for your decisions and decision processes.

Yours faithfully,
Judy Grindell

-------------------------------------------------------------------

Please use this email address for all replies to this request:
[OIA #708 email]

Is [CERA request email] the wrong address for Official Information Act
requests to Canterbury Earthquake Recovery Authority? If so, please
contact us using this form:
http://fyi.org.nz/help/contact

Disclaimer: This message and any reply that you make will be
published on the internet. Our privacy and copyright policies:
http://fyi.org.nz/help/officers

If you find this service useful as an OIA officer, please ask your
web manager to link to us from your organisation's FOI page.

-------------------------------------------------------------------

-------------------------------
This email and any attachments may contain information that is confidential and subject to legal privilege. If you are not the intended recipient, any use, dissemination, distribution or duplication of this email and attachments is prohibited. If you have received this email in error please notify the author immediately and erase all copies of the email and attachments. The Canterbury Earthquake Recovery Authority (CERA) accepts no responsibility for changes made to this message or attachments after transmission from CERA.

For further information about CERA, please visit www.cera.govt.nz.

-------------------------------

hide quoted sections

Link to this

From: Therese Davel
Canterbury Earthquake Recovery Authority


Attachment 479 Grindell letter.pdf
97K Download View as HTML


Dear Judy

 

Thank you for your request for information received on 20 December 2012.
Please find attached a letter relating to your request from Benesia Smith,
Acting Chief Executive. 

 

 

Kind regards,

 

Therese

 

 

 

Therese Davel

Team Administrator

Office of the Chief Executive

Canterbury Earthquake Recovery Authority (CERA)

 

Private Bag 4999 Christchurch 8140

 

W: [1]www.cera.govt.nz

 

 

------------------------------- This email and any attachments may contain
information that is confidential and subject to legal privilege. If you
are not the intended recipient, any use, dissemination, distribution or
duplication of this email and attachments is prohibited. If you have
received this email in error please notify the author immediately and
erase all copies of the email and attachments. The Canterbury Earthquake
Recovery Authority (CERA) accepts no responsibility for changes made to
this message or attachments after transmission from CERA. For further
information about CERA, please visit www.cera.govt.nz.
-------------------------------

References

Visible links
1. http://www.cera.govt.nz/
http://www.careers.cera.govt.nz/
http://www.cera.govt.nz/
http://www.cera.govt.nz/

Link to this

From: Judy Grindell

Dear Cera

Thank you for your reply. Alas, it does not provide the information I requested.

Your response is merely a rehash of the general, area-wide information already provided and which is in the public domain. I had already been through all that information but it does not provide the data I am seeking. For example, nowhere have a seen a definition or criteria explaining ‘potential for future lateral spreading’. Given that the CPTs for the end of Kibblewhite Street area seem to hit a shallow aquifer at 26m and given the proximity to the estuary / river, the land subsiding and flooding at high tides plus the lateral spreading that was and is still apparent, I would have expected that area (TC3) would have greater ‘potential for lateral spreading’. I have asked for the data (as per my OIA request) so that I can better understand the zoning processes and criteria used.
I did have a meeting with Jan Kupec (I did appreciate this), which was useful for seeing the information previously missing (e.g., CPT testing for the last block of Estuary Rd, and LiDAR data for the maps that, in the published reports, had been covered by the map legend or the map did not extend as far as the red / TC3 boundary. Jan went over the same general ‘area-wide’ decision stuff again but would not (or could not) provide any specific explanation as to how the boundaries were drawn where they are; his responses were ‘I did not draw the boundary’, ‘the boundary has to be somewhere’, and ‘there’s probably a buffer in there’.
I have been through the Project Orbit Database (I do have access) and the various reports (T&T, GNS etc) … and while it provided access to much interesting data, it provides no judgement or evidence as to how boundary decisions were made based on what data.
The first house after the red /TC3 boundary for the Southshore north area is only 1 metre from the red zone boundary and the property extends all the way back to the campground. There are two properties in the red zone at the red / green boundary; one of which backs on to the campground and one nearest the road obviously does extend to the campground. I would like to be able to understand how your data and evidence-based decision-making process justify the differences over 1 metre.
The various criteria relating to lateral spreading (existing or potential, whatever that might be), land elevation or subsidence appear to be applied inconsistently across the areas. So I repeat again, I would like an explanation and evidence explaining the rationale for the different areas as I requested.
I repeat, I have asked for the data (as per my OIA request) so that I can better understand the zoning processes and criteria used. While a number of residents in the Southshore and South New Brighton areas are satisfied with general, area-wide information, there are many others who would like to understand more.

Please provide the data and explanations as requested.

Yours sincerely,

Judy Grindell

Link to this

From: oce (CERA)
Canterbury Earthquake Recovery Authority

Dear Judy

Thank you for your email requesting information under the Official Information Act. A response will be supplied within 20 working days from 18 January 2013 in accordance with the requirements of the Act.

Kind regards

Therese

Therese Davel
Team Administrator
Office of the Chief Executive
Canterbury Earthquake Recovery Authority (CERA)

Private Bag 4999 Christchurch 8140

W: www.cera.govt.nz

-----Original Message-----
From: Judy Grindell [mailto:[OIA #708 email]]
Sent: Friday, 18 January 2013 11:32 a.m.
To: Therese Davel
Subject: Re: Official Information Act Request

Dear Cera

Thank you for your reply. Alas, it does not provide the information
I requested.

Your response is merely a rehash of the general, area-wide
information already provided and which is in the public domain. I
had already been through all that information but it does not
provide the data I am seeking. For example, nowhere have a seen a
definition or criteria explaining ‘potential for future lateral
spreading’. Given that the CPTs for the end of Kibblewhite Street
area seem to hit a shallow aquifer at 26m and given the proximity
to the estuary / river, the land subsiding and flooding at high
tides plus the lateral spreading that was and is still apparent, I
would have expected that area (TC3) would have greater ‘potential
for lateral spreading’. I have asked for the data (as per my OIA
request) so that I can better understand the zoning processes and
criteria used.
I did have a meeting with Jan Kupec (I did appreciate this), which
was useful for seeing the information previously missing (e.g., CPT
testing for the last block of Estuary Rd, and LiDAR data for the
maps that, in the published reports, had been covered by the map
legend or the map did not extend as far as the red / TC3 boundary.
Jan went over the same general ‘area-wide’ decision stuff again but
would not (or could not) provide any specific explanation as to how
the boundaries were drawn where they are; his responses were ‘I did
not draw the boundary’, ‘the boundary has to be somewhere’, and
‘there’s probably a buffer in there’.
I have been through the Project Orbit Database (I do have access)
and the various reports (T&T, GNS etc) … and while it provided
access to much interesting data, it provides no judgement or
evidence as to how boundary decisions were made based on what data.
The first house after the red /TC3 boundary for the Southshore
north area is only 1 metre from the red zone boundary and the
property extends all the way back to the campground. There are two
properties in the red zone at the red / green boundary; one of
which backs on to the campground and one nearest the road obviously
does extend to the campground. I would like to be able to
understand how your data and evidence-based decision-making process
justify the differences over 1 metre.
The various criteria relating to lateral spreading (existing or
potential, whatever that might be), land elevation or subsidence
appear to be applied inconsistently across the areas. So I repeat
again, I would like an explanation and evidence explaining the
rationale for the different areas as I requested.
I repeat, I have asked for the data (as per my OIA request) so that
I can better understand the zoning processes and criteria used.
While a number of residents in the Southshore and South New
Brighton areas are satisfied with general, area-wide information,
there are many others who would like to understand more.

Please provide the data and explanations as requested.

Yours sincerely,

Judy Grindell

-----Original Message-----

Dear Judy

 

Thank you for your request for information received on 20 December
2012.
Please find attached a letter relating to your request from
Benesia Smith,
Acting Chief Executive. 

 

 

Kind regards,

 

Therese

 

 

 

Therese Davel

Team Administrator

Office of the Chief Executive

Canterbury Earthquake Recovery Authority (CERA)

 

Private Bag 4999 Christchurch 8140

 

W: [1]www.cera.govt.nz

 

 

------------------------------- This email and any attachments may
contain
information that is confidential and subject to legal privilege.
If you
are not the intended recipient, any use, dissemination,
distribution or
duplication of this email and attachments is prohibited. If you
have
received this email in error please notify the author immediately
and
erase all copies of the email and attachments. The Canterbury
Earthquake
Recovery Authority (CERA) accepts no responsibility for changes
made to
this message or attachments after transmission from CERA. For
further
information about CERA, please visit www.cera.govt.nz.
-------------------------------

References

Visible links
1. http://www.cera.govt.nz/
http://www.careers.cera.govt.nz/
http://www.cera.govt.nz/
http://www.cera.govt.nz/

-------------------------------------------------------------------
Please use this email address for all replies to this request:
[OIA #708 email]

Disclaimer: This message and any reply that you make will be
published on the internet. Our privacy and copyright policies:
http://fyi.org.nz/help/officers

If you find this service useful as an OIA officer, please ask your
web manager to link to us from your organisation's FOI page.

-------------------------------------------------------------------

-------------------------------
This email and any attachments may contain information that is confidential and subject to legal privilege. If you are not the intended recipient, any use, dissemination, distribution or duplication of this email and attachments is prohibited. If you have received this email in error please notify the author immediately and erase all copies of the email and attachments. The Canterbury Earthquake Recovery Authority (CERA) accepts no responsibility for changes made to this message or attachments after transmission from CERA.

For further information about CERA, please visit www.cera.govt.nz.

-------------------------------

hide quoted sections

Link to this

From: Judy Grindell

Dear oce (CERA),

my letter of 18 Jan was not a new request. It was clarification as to why your response (18 Jan) to my 19 December request did not meet that request and clarification that I still do want the information as requested. I am still seeking that information and am expecting this will be provided within 20 working days of 20 December.

Yours sincerely,

Judy Grindell

Link to this

From: oce (CERA)
Canterbury Earthquake Recovery Authority


Attachment 496 Grindell letter.pdf
79K Download View as HTML


Dear Judy

 

 

Thank you for your request for information received on 19 December 2012
and follow up email of 18 January 2013. Please find attached a letter
relating to your request from Roger Sutton, Chief Executive of Canterbury
Earthquake Recovery Authority. 

 

Kind regards

 

Therese

 

 

 

Therese Davel

Team Administrator

Office of the Chief Executive

Canterbury Earthquake Recovery Authority (CERA)

 

Private Bag 4999 Christchurch 8140

 

W: [1]www.cera.govt.nz

 

 

------------------------------- This email and any attachments may contain
information that is confidential and subject to legal privilege. If you
are not the intended recipient, any use, dissemination, distribution or
duplication of this email and attachments is prohibited. If you have
received this email in error please notify the author immediately and
erase all copies of the email and attachments. The Canterbury Earthquake
Recovery Authority (CERA) accepts no responsibility for changes made to
this message or attachments after transmission from CERA. For further
information about CERA, please visit www.cera.govt.nz.
-------------------------------

References

Visible links
1. http://www.cera.govt.nz/
http://www.careers.cera.govt.nz/
http://www.cera.govt.nz/
http://www.cera.govt.nz/

Link to this

From: Judy Grindell

Dear Roger (CERA),

I am very disappointed in your response and your unwillingness to provide the data as requested.

Given that no CPT testing had been done at all in that block of Estuary Road when the zoning decision was made, I cannot see how you can state "the key factor in declaring an area as green zone was whether individual foundation solutions were feasible for the particular ground conditions".

Ground conditions can, in some circumstances, change over a few metres but no drilling had been done anywhere near the red/green boundary to check this. There is no surface indication of a drastic change in soil type in this area and one would not expect it.

There are inherent margins of error in the accuracy of the original DTMs and the LiDAR data so you need to be very cautious in claiming how definitive that data is for decisions.

You recommendation that I seek independant advice from a qualified geotechnical engineer is unhelpful and really rather silly ... how is that going to provide me with the detailed evidence as to how CERA decided where boundaries should go and how CERA decided what was red and what was green for the areas I am seeking clarification for?????

Besides, I already have access to (and regularly discuss these issues with)some of the country’s best remote sensing and LiDAR scientists,pedologists and geomorphologists. I also have access to a retired geotechnical engineer who worked overseas on such issues.

While CERA have made it abundantly clear they will not overturn any zoning decision, I do believe a public decision-making body has an incumbent responsibility to explain how and why the decision has been made in a particular situation. This is particularly so when people and communities are so significantly affected. Moreover, I also believe that CERA should have provided
data as requested when first requested rather than go through these nebulous explanations wasting your time and mine.

Yours sincerely,

Judy Grindell

Link to this

Luke C left an annotation ()

Judy said:

“I do believe a public decision-making body has an incumbent responsibility to explain how and why the decision has been made in a particular situation.”

The basis for the decision-making is explained further in the 4 Feb 2013 letter. CERA said:

“In our reply of 18 January it was explained that the decisions made have been objective ones. There is no additional technical information we can provide you with because the boundary lines were drawn on expert geotechnical assessment of a range of data sets available, rather than one particular measurement or data set.”

“... expert judgement was used...”

Despite the fact that CERA have not supplied the criteria, ‘tipping points’, parameters or weightings, you need to accept that CERA have answered your request by supplying you with as much information as can. It may not be the information you are after, but they have appeared to have done their best.

My advice would be for you to contact the person at CERA who is the geotechnical subject-matter expert responsible for overseeing the “expert geotechnical assessment” to which CERA refers. By way of conversation, rather than an OIA request, they may be able to explain to you who carried out the assessment. From there, you can contact the assessors directly to find out more.

If the assessors were contracted by CERA, then any information held by the assessors in their official capacity for undertaking work by CERA, is deemed to be held by CERA itself. Therefore, you may submit an OIA request to CERA for data/information held by the contractor; but you should only make such a request once you are very clear as to the exact name of the thing (data(set) or documentation) you are requesting.

It may be that the assessors have a manual or guidelines (decision system) that assists the engineer in making a ‘objective’ decision (professional judgement). In this case, the manual/guidelines are requestable under the OIA, but the actual professional judgement is much harder to request and in that case, conversation with the assessors may be more enlightening as to how they arrived at their decision.

I hope this is helpful.

Link to this

Luke C left an annotation ()

For example, the engineers who carried out the assessments may have based their decisions on a manual such as this: http://www.icevirtuallibrary.com/content....

Link to this

Things to do with this request

Anyone:
Canterbury Earthquake Recovery Authority only: