20160711 To KiwiRail from Save Our Rail Northland: Official Information Act Request for update on the status quo on the North Auckland Line
Save Our Rail Northland made this Official Information request to KiwiRail
The request was partially successful.
From: Save Our Rail Northland
Dear KiwiRail,
( copied from e-mail sent directly to KiwiRail earlier today )
20160711 To KiwiRail from Save Our Rail Northland:
Official Information Act Request for update on the status quo on the North Auckland Line
Kia ora.
Could you please provide us with an update of the current status quo on the North Auckland Line.
The following request for information is made under the auspices of the Official Information Act - which requires that the information requested be provided ' as soon as reasonably practicable, and in any case not later than 20 working days after the day on which the request is received'.
The information we are requesting will be made available to the public, candidates in the 2016 Local Government Elections and media on the Save Our Rail Northland web-site
What sections of the North Auckland Line are currently being used ?
Please provide a detailed breakdown of information about each train using the North Auckland Line :
What is the locomotive power being used to pull this train?
Is this a regular ( scheduled ) service ?
How frequently does this train run ?
How many carriages is it pulling ?
What is the approximate tonnage being transported ?
What is the tonnage comprised of ?
Is this a dedicated service - to a contracted customer ?
What is this train's point of departure - destination ?
What time of day / week is this train in operation ?
What is the distance travelled ?
How long does this trip take ?
What is the average / maximum speed that this train travels at ?
What is the likely future of freight services on the the North Auckland Line ?
Has KiwiRail received inquiries / requests from other businesses to transport their freight ?
What other companies / organisations have requested that KiwiRail transport their freight ?
Has there been any undue political influence in the decision for KiwiRail to not renew its contract with Marasumi ?
Is KiwiRail making any long term plans that take into consideration the completion of the proposed connection with Northport ?
Where can the public read KiwiRail's investigation into this potential opportunity ?
Does KiwiRail have any plans to extend passenger services along any section of the North Auckland Line ( beyond the extent to which they currently travel ) ?
Is KiwiRail interested in developing passenger rail services along the North Auckland Line - for commuters, inter-city travellers and domestic and international tourists ?
e.g. between Opua and Auckland.
Does KiwiRail still own the rail corridor between Otiria and Kawakawa ?
Does KiwiRail have any plans to rebuild the rail connection between Otiria and Kawakawa ?
What is the status with regard to removal of asbestos from drivers' compartments of the trains on the North Auckland Line ?
What significant repairs or improvements are presently being carried out on the North Auckland Line ?
What significant repairs or improvements have recently ( in the last year ) been carried out on the North Auckland Line ?
What significant repairs or improvements need to be carried out on the North Auckland Line in the near future ?
What significant repairs or improvements need to be carried out on the North Auckland Line in the long term future to enable it to carry HiCube containers and passenger wagons?
What costs are likely to be associated with each of these maintence/ repair jobs ?
How long are these jobs likely to take to complete ?
What is the makeup of maintenance crews operating along the North Auckland Line ?
Has any part of the infrastructure on the North Auckland Line been removed ?
Is there any plan to remove any part of the infrastructure within the rail corridor - or to relinquish ownership of any part of the rail corridor ?
As a State Owned Enterprise , considering its inherent responsibilities to the people of New Zealand : -
-is KiwiRail aware of or made any study to quantify the social and economic impact of discontinuation of KiwiRail's operations along the North Auckland Line ? ( see our Social Impact Assessment )
-is KiwiRail aware of or made any study to quantify the effect on Northland's long term strategic robustness and resilience that the discontinuation of the North Auckland Line would have in the event that fossil fuel becomes unaffordable or supplies become limited ( see Oil Prices and Transport Sector Resilience )
-is KiwiRail aware of or made any study to quantify the costs of transitioning freight from rail to road transport ?
What are those costs ?
-is KiwiRail aware of or made any study to quantify the differential in diesel fuel consumption - and associated green-house gases that will be emitted if freight currently being transported by KiwiRail's trains has to be transported by road-haulage contractors ? ( see : The Bolland Report )
Is KiwiRail required to consider the effects of its greenhouse gas emissions in its planning model ?
A prompt response to this enquiry would be greatly appreciated.
Thank you in advance.
Naku noa na...
Alan Preston for Save Our Rail Northland ( and the 13,700 people who signed our petition to keep this strategically essential component in Northland's transport infrastructure operational. )
11th of July 2016
============================================================
contact Alan Preston in Mangawhai, Northland ( web-site) Tel: +64 9 4315389 .
e-mail @ e-mail:[email address]
web-site:https://sites.google.com/site/saveourrai...
facebook : https://www.facebook.com/groups/saveourr...
Yours faithfully,
Save Our Rail Northland
From: Louise Jago
KiwiRail
Good morning Alan
We acknowledge receipt of the below Official Information Act 1982 request.
Under the Act, KiwiRail has up to 20 working days from the date of
receiving your request to respond. Therefore, you can expect a response
on or before Monday 8 August 2016.
We note that you have also submitted this request under the Save Our Rail
Northland email address which we acknowledged earlier today. To avoid any
doubt, we intend to provide the same response to both email addresses.
We will be in touch with you if it is necessary to clarify any aspect of
your request.
Kind regards
Louise
Louise Jago | Communications Co-ordinator
Ph: +64-4-498 3372 (internal extn 43372) | Fax: +64-4-473 1589 | Mob:
+64-027 407 1718
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO
Box 593, Wellington 6140, New Zealand
[1]Description: Description: KiwiRail Logo email
Backbone of integrated transport networks
Please consider the environment before printing
-----Original Message-----
From: Save Our Rail Northland
[2][mailto:[FOI #4241 email]]
Sent: Monday, July 11, 2016 4:25 PM
To: KiwiRail
Subject: Official Information request - 20160711 To KiwiRail from Save Our
Rail Northland: Official Information Act Request for update on the status
quo on the North Auckland Line
Dear KiwiRail,
( copied from e-mail sent directly to KiwiRail earlier today )
20160711 To KiwiRail from Save Our Rail Northland:
Official Information Act Request for update on the status quo on the North
Auckland Line Kia ora.
Could you please provide us with an update of the current status quo on
the North Auckland Line.
The following request for information is made under the auspices of the
Official Information Act - which requires that the information requested
be provided ' as soon as reasonably practicable, and in any case not later
than 20 working days after the day on which the request is received'.
The information we are requesting will be made available to the public,
candidates in the 2016 Local Government Elections and media on the Save
Our Rail Northland web-site
What sections of the North Auckland Line are currently being used ?
Please provide a detailed breakdown of information about each train using
the North Auckland Line :
What is the locomotive power being used to pull this train?
Is this a regular ( scheduled ) service ?
How frequently does this train run ?
How many carriages is it pulling ?
What is the approximate tonnage being transported ?
What is the tonnage comprised of ?
Is this a dedicated service - to a contracted customer ?
What is this train's point of departure - destination ?
What time of day / week is this train in operation ?
What is the distance travelled ?
How long does this trip take ?
What is the average / maximum speed that this train travels at ?
What is the likely future of freight services on the the North Auckland
Line ?
Has KiwiRail received inquiries / requests from other businesses to
transport their freight ?
What other companies / organisations have requested that KiwiRail
transport their freight ?
Has there been any undue political influence in the decision for KiwiRail
to not renew its contract with Marasumi ?
Is KiwiRail making any long term plans that take into consideration the
completion of the proposed connection with Northport ?
Where can the public read KiwiRail's investigation into this potential
opportunity ?
Does KiwiRail have any plans to extend passenger services along any
section of the North Auckland Line ( beyond the extent to which they
currently travel ) ?
Is KiwiRail interested in developing passenger rail services along the
North Auckland Line - for commuters, inter-city travellers and domestic
and international tourists ?
e.g. between Opua and Auckland.
Does KiwiRail still own the rail corridor between Otiria and Kawakawa ?
Does KiwiRail have any plans to rebuild the rail connection between Otiria
and Kawakawa ?
What is the status with regard to removal of asbestos from drivers'
compartments of the trains on the North Auckland Line ?
What significant repairs or improvements are presently being carried out
on the North Auckland Line ?
What significant repairs or improvements have recently ( in the last year
) been carried out on the North Auckland Line ?
What significant repairs or improvements need to be carried out on the
North Auckland Line in the near future ?
What significant repairs or improvements need to be carried out on the
North Auckland Line in the long term future to enable it to carry HiCube
containers and passenger wagons?
What costs are likely to be associated with each of these maintence/
repair jobs ?
How long are these jobs likely to take to complete ?
What is the makeup of maintenance crews operating along the North
Auckland Line ?
Has any part of the infrastructure on the North Auckland Line been removed
?
Is there any plan to remove any part of the infrastructure within the rail
corridor - or to relinquish ownership of any part of the rail corridor ?
As a State Owned Enterprise , considering its inherent responsibilities to
the people of New Zealand : - -is KiwiRail aware of or made any study to
quantify the social and economic impact of discontinuation of KiwiRail's
operations along the North Auckland Line ? ( see our Social Impact
Assessment ) -is KiwiRail aware of or made any study to quantify the
effect on Northland's long term strategic robustness and resilience that
the discontinuation of the North Auckland Line would have in the event
that fossil fuel becomes unaffordable or supplies become limited ( see
Oil Prices and Transport Sector Resilience ) -is KiwiRail aware of or made
any study to quantify the costs of transitioning freight from rail to road
transport ?
What are those costs ?
-is KiwiRail aware of or made any study to quantify the differential in
diesel fuel consumption - and associated green-house gases that will be
emitted if freight currently being transported by KiwiRail's trains has to
be transported by road-haulage contractors ? ( see : The Bolland Report )
Is KiwiRail required to consider the effects of its greenhouse gas
emissions in its planning model ?
A prompt response to this enquiry would be greatly appreciated.
Thank you in advance.
Naku noa na...
Alan Preston for Save Our Rail Northland ( and the 13,700 people who
signed our petition to keep this strategically essential component in
Northland's transport infrastructure operational. ) 11th of July 2016
============================================================
contact Alan Preston in Mangawhai, Northland ( web-site) Tel: +64 9
4315389 .
e-mail @ e-mail:[email address]
web-site:https://sites.google.com/site/saveourrai...
facebook : [3]https://www.facebook.com/groups/saveourr...
Yours faithfully,
Save Our Rail Northland
-------------------------------------------------------------------
This is an Official Information request made via the FYI website.
Please use this email address for all replies to this request:
[4][FOI #4241 email]
Is [5][KiwiRail request email] the wrong address for Official Information
requests to KiwiRail? If so, please contact us using this form:
[6]https://fyi.org.nz/change_request/new?bo...
Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
[7]https://fyi.org.nz/help/officers
If you find this service useful as an Official Information officer, please
ask your web manager to link to us from your organisation's OIA or LGOIMA
page.
-------------------------------------------------------------------
References
Visible links
1. http://www.kiwirail.co.nz/
2. mailto:[mailto:[FOI #4241 email]]
3. https://www.facebook.com/groups/saveourr...
4. mailto:[FOI #4241 email]
5. mailto:[KiwiRail request email]
6. https://fyi.org.nz/change_request/new?bo...
7. https://fyi.org.nz/help/officers
hide quoted sections
From: Louise Jago
KiwiRail
Dear Mr Preston
We are writing in response to your Official Information Act 1982 request
dated 13 July 2016 requesting information on the status of the North
Auckland Line. Your questions and KiwiRail’s responses are outlined below:
“What sections of the North Auckland Line are currently being used?
Currently freight services are running on all sections of the North
Auckland Line (NAL). However, from late August freight services will cease
operating on the section of the Line between Otiria and Kauri.
Please provide a detailed breakdown of information about each train using
the North Auckland Line:
Four DC – Diesel electric - class locomotives use the NAL.
Two services run on the NAL from Monday – Friday:
· The 126 service departs from Auckland at 09:30am and arrives at
Whangarei at 16:15pm.
· The 129 service departs from Whangarei at 18:40pm and arrives at
Auckland at 00:25am.
A third service runs as required from Monday – Friday, but is dependent on
demand:
· The 125 service departs from Whangarei at 07:05am and arrives at
Auckland at 13:51pm.
In addition the following services run on the NAL:
· The 124 service runs between Monday and Thursday. It departs
from Auckland at 20:30pm and arrives at Whangarei at 03:23am.
· The 120 service runs on Sundays only. It departs from Auckland
at 19:00pm and arrives at Whangarei at 00:21am.
In September, the two Auckland to Whangarei services (126 & 124) will
amalgamate into a single service and the two Whangarei to Auckland
services (125 & 129) will also merge into a single service. However, the
total capacity carried on the line will not change.
What is the locomotive power being used to pull this train?
The output power of DC Locomotives is 1230kW.
Is this a regular (scheduled) service?
Please see above.
How frequently does this train run?
Please see above.
How many carriages is it pulling?
KiwiRail does not hold information on the number of wagons each service
carries as the number varies according to demand. However, between 20 and
23 wagons can run on each service, if fully loaded.
What is the approximate tonnage being transported?
199,195 tonnes of customer freight was carried on the NAL in financial
year ended June 30 2016.
What is the tonnage comprised of?
The majority of tonnage transported on the NAL is comprised of forestry
and dairy commodities including: logs, wood chips and butter exports.
Is this a dedicated service - to a contracted customer?
No. Services on the NAL are for all customers.
What is this train's point of departure - destination?
Please see above.
What time of day / week is this train in operation?
Please see above.
What is the distance travelled?
The distance between Whangarei to Auckland is 212km.
How long does this trip take?
A one way trip to Whangarei from Auckland takes six hours.
What is the average / maximum speed that this train travels at?
The average speed that each train travels on the NAL at is 50kmph.
What is the likely future of freight services on the North Auckland Line?
At present there is little demand for freight services on the NAL. If, in
the future, the demand for freight services is present in commercial
quantities and customers are prepared to pay commercial rates, KiwiRail
will carry that freight. The line north of Kauri will remain open so that
it may be used again if and when it becomes economic to do so.
Has KiwiRail received inquiries / requests from other businesses to
transport their freight?
Yes. KiwiRail has received inquiries from businesses that wish to use the
NAL line to transport their freight. To date, it has been uneconomic for
KiwiRail to carry the freight volumes discussed with potential clients as
they are not of a commercial quantity.
What other companies / organisations have requested that KiwiRail
transport their freight?
This information is commercially sensitive and has been withheld under
sections(2)(b)(i) of the Act.
Has there been any undue political influence in the decision for KiwiRail
to not renew its contract with Marasumi?
No. This is an operational matter for KiwiRail.
Is KiwiRail making any long term plans that take into consideration the
completion of the proposed connection with [1]Northport ?
KiwiRail has an open mind on the prospect of rail connections to Marsden
Point, and supports the retention of the designation. However, any
decision to establish the link to Marsden Port and to rebuild the North
Auckland Line for an export business would need to be determined by wider
decisions regarding future port strategies in the Upper North Island.
Where can the public read KiwiRail's investigation into this potential
opportunity?
Please see above.
Does KiwiRail have any plans to extend passenger services along any
section of the North Auckland Line (beyond the extent to which they
currently travel)?
KiwiRail has no plans to provide a long distance passenger service on the
NAL that links Whangarei to Auckland. KiwiRail does not hold any
information that suggests Auckland Transport have any immediate plans to
extend their commuter services beyond the current terminus at Swanson. For
further information on commuter services please contact Auckland
Transport.
Is KiwiRail interested in developing passenger rail services along the
North Auckland Line - for commuters, inter-city travellers and domestic
and international tourists?
KiwiRail has no current plans to operate commuter services on the NAL as
Auckland Transport is responsible for the provision of commuter services
on the line as far as Swanson. KiwiRail will consider opening a new
passenger services on the NAL for tourists if, in the future, the
forecasted demand and/or tourism growth is present in commercial
quantities.
Does KiwiRail still own the rail corridor between Otiria and Kawakawa?
Yes.
Does KiwiRail have any plans to rebuild the rail connection between Otiria
and Kawakawa?
In the absence of any commercial freight KiwiRail has no plans to upgrade
the Line between Otiria and Kawakawa.
What is the status with regard to removal of asbestos from drivers'
compartments of the trains on the North Auckland Line?
The matter of asbestos removal only applies to drivers' compartments in DL
class locomotives which do not run on the NAL.
What significant repairs or improvements are presently being carried out
on the North Auckland Line?
No repairs or upgrades are currently being undertaken on the NAL but the
line is being maintained to a level that allows freight to be transported
safely.
What significant repairs or improvements have recently (in the last year)
been carried out on the North Auckland Line?
During the last financial year a number of maintenance activities were
completed on the NAL: four track sites and three bridges were
re-sleepered, three sites had new ballast discharged and one location was
re-railed.
What significant repairs or improvements need to be carried out on the
North Auckland Line in the near future?
In the future, structural bridge works will be completed in a number of
locations along the NAL.
What significant repairs or improvements need to be carried out on the
North Auckland Line in the long term future to enable it to carry HiCube
containers and passenger wagons?
To carry HiCube containers on the NAL would require significant investment
to lower the Line’s tunnels. KiwiRail initially estimates that upgrades
would require an investment of $40 –$60million, this figure is based on
similar work undertaken on other Lines.
What costs are likely to be associated with each of these maintenance/
repair jobs?
How long are these jobs likely to take to complete?
Please see above.
What is the makeup of maintenance crews operating along the North Auckland
Line?
The following maintenance crews operate on the NAL:
· 2 track staff at Helensville
· 2 track staff at Maungaturoto
· 4 track staff at Whangarei
· 4 structures staff at Whangarei
· 1 signals staff at Whangarei
· 1 Track Inspector
· 1 Structures Inspector
Has any part of the infrastructure on the North Auckland Line been
removed?
No infrastructure has been removed from the NAL.
Is there any plan to remove any part of the infrastructure within the rail
corridor - or to relinquish ownership of any part of the rail corridor?
No.
As a State Owned Enterprise, considering its inherent responsibilities to
the people of New Zealand : -
-is KiwiRail aware of or made any study to quantify the social and
economic impact of discontinuation of KiwiRail's operations along the
North Auckland Line? (See our [2]Social Impact Assessment )
KiwiRail has not undertaken and is not aware of any detailed analysis in
the discontinuation of freight operations on the NAL.
-is KiwiRail aware of or made any study to quantify the effect on
Northland's long term strategic robustness and resilience that the
discontinuation of the North Auckland Line would have in the event that
fossil fuel becomes unaffordable or supplies become limited ( see [3]Oil
Prices and Transport Sector Resilience )
Please see above
-is KiwiRail aware of or made any study to quantify the costs of
transitioning freight from rail to road transport?
Please see above
What are those costs?
Please see above
-is KiwiRail aware of or made any study to quantify the differential in
diesel fuel consumption - and associated green-house gases that will be
emitted if freight currently being transported by KiwiRail's trains has to
be transported by road-haulage contractors ? (see: [4]The Bolland Report
)
Please see above
Is KiwiRail required to consider the effects of its greenhouse gas
emissions in its planning model? ”
KiwiRail considers social, environmental and economic factors as part of
its standard decision making practices.
Under s28(3) of the Act, you have the right to seek an investigation and
review of this response by way of complaint to the Ombudsman. Refer to
[5]www.ombudsman.govt.nz for more information.
Regards
Louise
Louise Jago | Communications Co-ordinator
Ph: +64-4-498 3372 (internal extn 43372) | Fax: +64-4-473 1589 | Mob:
+64-027 407 1718
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO
Box 593, Wellington 6140, New Zealand
[6]Description: KiwiRail Logo email
Backbone of integrated transport networks
Please consider the environment before printing
From: Louise Jago
Sent: Wednesday, 13 July 2016 11:47 a.m.
To: '[FOI #4241 email]'
Subject: RE: Official Information request - 20160711 To KiwiRail from Save
Our Rail Northland: Official Information Act Request for update on the
status quo on the North Auckland Line
Good morning Alan
We acknowledge receipt of the below Official Information Act 1982 request.
Under the Act, KiwiRail has up to 20 working days from the date of
receiving your request to respond. Therefore, you can expect a response
on or before Monday 8 August 2016.
We note that you have also submitted this request under the Save Our Rail
Northland email address which we acknowledged earlier today. To avoid any
doubt, we intend to provide the same response to both email addresses.
We will be in touch with you if it is necessary to clarify any aspect of
your request.
Kind regards
Louise
Louise Jago | Communications Co-ordinator
Ph: +64-4-498 3372 (internal extn 43372) | Fax: +64-4-473 1589 | Mob:
+64-027 407 1718
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO
Box 593, Wellington 6140, New Zealand
[7]Description: Description: KiwiRail Logo email
Backbone of integrated transport networks
Please consider the environment before printing
-----Original Message-----
From: Save Our Rail Northland
[8][mailto:[FOI #4241 email]]
Sent: Monday, July 11, 2016 4:25 PM
To: KiwiRail
Subject: Official Information request - 20160711 To KiwiRail from Save Our
Rail Northland: Official Information Act Request for update on the status
quo on the North Auckland Line
Dear KiwiRail,
( copied from e-mail sent directly to KiwiRail earlier today )
20160711 To KiwiRail from Save Our Rail Northland:
Official Information Act Request for update on the status quo on the North
Auckland Line Kia ora.
Could you please provide us with an update of the current status quo on
the North Auckland Line.
The following request for information is made under the auspices of the
Official Information Act - which requires that the information requested
be provided ' as soon as reasonably practicable, and in any case not later
than 20 working days after the day on which the request is received'.
The information we are requesting will be made available to the public,
candidates in the 2016 Local Government Elections and media on the Save
Our Rail Northland web-site
What sections of the North Auckland Line are currently being used ?
Please provide a detailed breakdown of information about each train using
the North Auckland Line :
What is the locomotive power being used to pull this train?
Is this a regular ( scheduled ) service ?
How frequently does this train run ?
How many carriages is it pulling ?
What is the approximate tonnage being transported ?
What is the tonnage comprised of ?
Is this a dedicated service - to a contracted customer ?
What is this train's point of departure - destination ?
What time of day / week is this train in operation ?
What is the distance travelled ?
How long does this trip take ?
What is the average / maximum speed that this train travels at ?
What is the likely future of freight services on the the North Auckland
Line ?
Has KiwiRail received inquiries / requests from other businesses to
transport their freight ?
What other companies / organisations have requested that KiwiRail
transport their freight ?
Has there been any undue political influence in the decision for KiwiRail
to not renew its contract with Marasumi ?
Is KiwiRail making any long term plans that take into consideration the
completion of the proposed connection with Northport ?
Where can the public read KiwiRail's investigation into this potential
opportunity ?
Does KiwiRail have any plans to extend passenger services along any
section of the North Auckland Line ( beyond the extent to which they
currently travel ) ?
Is KiwiRail interested in developing passenger rail services along the
North Auckland Line - for commuters, inter-city travellers and domestic
and international tourists ?
e.g. between Opua and Auckland.
Does KiwiRail still own the rail corridor between Otiria and Kawakawa ?
Does KiwiRail have any plans to rebuild the rail connection between Otiria
and Kawakawa ?
What is the status with regard to removal of asbestos from drivers'
compartments of the trains on the North Auckland Line ?
What significant repairs or improvements are presently being carried out
on the North Auckland Line ?
What significant repairs or improvements have recently ( in the last year
) been carried out on the North Auckland Line ?
What significant repairs or improvements need to be carried out on the
North Auckland Line in the near future ?
What significant repairs or improvements need to be carried out on the
North Auckland Line in the long term future to enable it to carry HiCube
containers and passenger wagons?
What costs are likely to be associated with each of these maintence/
repair jobs ?
How long are these jobs likely to take to complete ?
What is the makeup of maintenance crews operating along the North
Auckland Line ?
Has any part of the infrastructure on the North Auckland Line been removed
?
Is there any plan to remove any part of the infrastructure within the rail
corridor - or to relinquish ownership of any part of the rail corridor ?
As a State Owned Enterprise , considering its inherent responsibilities to
the people of New Zealand : - -is KiwiRail aware of or made any study to
quantify the social and economic impact of discontinuation of KiwiRail's
operations along the North Auckland Line ? ( see our Social Impact
Assessment ) -is KiwiRail aware of or made any study to quantify the
effect on Northland's long term strategic robustness and resilience that
the discontinuation of the North Auckland Line would have in the event
that fossil fuel becomes unaffordable or supplies become limited ( see
Oil Prices and Transport Sector Resilience ) -is KiwiRail aware of or made
any study to quantify the costs of transitioning freight from rail to road
transport ?
What are those costs ?
-is KiwiRail aware of or made any study to quantify the differential in
diesel fuel consumption - and associated green-house gases that will be
emitted if freight currently being transported by KiwiRail's trains has to
be transported by road-haulage contractors ? ( see : The Bolland Report )
Is KiwiRail required to consider the effects of its greenhouse gas
emissions in its planning model ?
A prompt response to this enquiry would be greatly appreciated.
Thank you in advance.
Naku noa na...
Alan Preston for Save Our Rail Northland ( and the 13,700 people who
signed our petition to keep this strategically essential component in
Northland's transport infrastructure operational. ) 11th of July 2016
============================================================
contact Alan Preston in Mangawhai, Northland ( web-site) Tel: +64 9
4315389 .
e-mail @ e-mail:[email address]
web-site:https://sites.google.com/site/saveourrai...
facebook : [9]https://www.facebook.com/groups/saveourr...
Yours faithfully,
Save Our Rail Northland
-------------------------------------------------------------------
This is an Official Information request made via the FYI website.
Please use this email address for all replies to this request:
[10][FOI #4241 email]
Is [11][KiwiRail request email] the wrong address for Official Information
requests to KiwiRail? If so, please contact us using this form:
[12]https://fyi.org.nz/change_request/new?bo...
Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
[13]https://fyi.org.nz/help/officers
If you find this service useful as an Official Information officer, please
ask your web manager to link to us from your organisation's OIA or LGOIMA
page.
-------------------------------------------------------------------
References
Visible links
1. https://sites.google.com/site/saveourrai...
2. https://sites.google.com/site/saveourrai...
3. https://sites.google.com/site/saveourrai...
4. https://sites.google.com/site/saveourrai...
5. http://www.ombudsman.govt.nz/
6. http://www.kiwirail.co.nz/
7. http://www.kiwirail.co.nz/
8. mailto:[mailto:[FOI #4241 email]]
9. https://www.facebook.com/groups/saveourr...
10. mailto:[FOI #4241 email]
11. mailto:[KiwiRail request email]
12. https://fyi.org.nz/change_request/new?bo...
13. https://fyi.org.nz/help/officers
hide quoted sections
Things to do with this request
- Add an annotation (to help the requester or others)
- Download a zip file of all correspondence