Northland Rail Upgrade Kauri to Otiria status of current work
Daniel Palenski made this Official Information request to KiwiRail
The request was successful.
From: Daniel Palenski
Dear KiwiRail,
I would like to what process is being made on work being done on the Kauri to Otiria stage of the Northland Rail Upgrade programme.
Yours faithfully,
Daniel
From: Dave Allard
KiwiRail
Good afternoon Daniel
Please find below our brief statement on the work done to the Kauri to Otiria stage of the Northland line.
The line is to be reopened at the end of 2022.
Physical works to achieve that will begin in early 2022 - our focus in 2021 is to complete track works between Swanson and Whangarei
We are currently carrying out track inspections of the Kauri to Otiria section so we can scope the necessary work.
Kind regards
Dave