Commuter cycleway planning and strategy

Michael Brown made this Official Information request to Hutt City Council

The request was successful.

From: Michael Brown

Dear Hutt City Council,

I am interested in knowing more about Hutt City Council planning around cycleways, in particular strategic planning for commuter routes around Lower Hutt and connecting these through to Wellington.

Searching your website and elsewhere reveals only the now out-of-date "Walk and Cycle the Hutt 2014-2019" document (http://iportal.huttcity.govt.nz/Record/R...), plus some information on the recreation-focused Taita-Seaview cycleway. There is also some online documentation about the Wellington to Hutt Valley cycleway or W2HV (https://www.nzta.govt.nz/assets/projects...), recently announced as being funded by central government as a "shovel ready" project.

Can you please supply any current HCC planning and strategy documents, such as they exist, around development or improvement of the commuter cycleway infrastructure in the Hutt Valley?

I'm especially interested in HCC planning for feeder cycleways to connect with the W2HV (such as cross-valley routes or connecting to the riverside trail network), as well as modelling of routes, data gathered on commuter cycle use to and from the Valley, efficacy of the existing network of shared pathways, etc.

Yours faithfully,

Michael Brown

Link to this

From: CONTACT EMAIL QUEUE
Hutt City Council

Thank you for your email. This mailbox is not monitored outside of
business hours, which are Monday to Friday 8am-5pm.
For urgent noise, water, including flooding and animal issues please call
us on 570 6666 24 hours a day.

Please do not reply to this Email.

Link to this

From: Michael Brown

Dear Hutt City Council,

Last month I made an OIA request to you on the FYI website (https://fyi.org.nz/request/13817-commute...). By law, you should normally have responded promptly and by October 13, 2020.

The request is now overdue. Please fulfill your statutory requirements around this request.

Yours faithfully,

Michael Brown

Link to this

From: CONTACT EMAIL QUEUE
Hutt City Council

Thank you for your email. This mailbox is not monitored outside of
business hours, which are Monday to Friday 8am-5pm.
For urgent noise, water, including flooding and animal issues please call
us on 570 6666 24 hours a day.

Please do not reply to this Email.

Link to this

From: Euan Kyle
Hutt City Council


Attachment hccsmalllogo 12fb0640 f486 4c5a a775 f4ab1b1dfb5d.jpg
20K Download

Attachment 12153HaHEmailSignatureFINAL 3cd6181d 2156 4dde 9fbd b6f7f302ed05.JPG.jpg
35K Download


15/10/2020  

   

   

Michael Brown  

[1][FOI #13817 email]  

   

Dear Michael Brown,

 

REQUEST FOR INFORMATION - LOCAL GOVERNMENT OFFICIAL INFORMATION AND
MEETINGS ACT 1987: ACKNOWLEDGEMENT OF REQUEST

 

I am writing to acknowledge receipt of your official information request
dated 15 September for information regarding commuter cycleway planning
and strategy.

 

We received your request on 16 September 2020. We apologise for missing
this request when it first came in. We are in the process of improving our
LGOIMA process and service and unfortunately we missed this email and I
apologise that we were not able to meet your expectations or our
requirements under the legislation. We will get our response to you as
soon as possible.

 

Your request is being coordinated by our infrastructure team. If any
additional factors come to light which are relevant to your request,
please do not hesitate to contact us so that these can be taken into
account.

 

Yours sincerely,

 

 

Euan Kyle
Senior Advisor, Official Information and Privacy

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New
Zealand
T 04 570 6702 W [2]www.huttcity.govt.nz

 

Euan Kyle
Senior Advisor – OIA & Privacy

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New
Zealand
T 04 570 6702, M 022 4155438,  W [3]www.huttcity.govt.nz

         [4][IMG]

 

 

IMPORTANT: The information contained in this e-mail message may be legally
privileged or confidential. The information is intended only for the
recipient named in the e-mail message. If the reader of this e-mail
message is not the intended recipient, you are notified that any use,
copying or distribution of this e-mail message is prohibited. If you have
received this e-mail message in error, please notify the sender
immediately. Thank you.

-----Original Message-----
From: "Michael Brown" <[FOI #13817 email]>
Sent: Tuesday, 15 September 2020 8:56 PM
To: "OIA/LGOIMA requests at Hutt City Council" <[Hutt City Council request email]>
Subject: Official Information request - Commuter cycleway planning and
strategy

Dear Hutt City Council,

I am interested in knowing more about Hutt City Council planning around
cycleways, in particular strategic planning for commuter routes around
Lower Hutt and connecting these through to Wellington.

Searching your website and elsewhere reveals only the now out-of-date
"Walk and Cycle the Hutt 2014-2019" document
(http://iportal.huttcity.govt.nz/Record/R...), plus some
information on the recreation-focused Taita-Seaview cycleway. There is
also some online documentation about the Wellington to Hutt Valley
cycleway or W2HV
(https://www.nzta.govt.nz/assets/projects...),
recently announced as being funded by central government as a "shovel
ready" project.

Can you please supply any current HCC planning and strategy documents,
such as they exist, around development or improvement of the commuter
cycleway infrastructure in the Hutt Valley?

I'm especially interested in HCC planning for feeder cycleways to connect
with the W2HV (such as cross-valley routes or connecting to the riverside
trail network), as well as modelling of routes, data gathered on commuter
cycle use to and from the Valley, efficacy of the existing network of
shared pathways, etc.

Yours faithfully,

Michael Brown

-------------------------------------------------------------------

This is an Official Information request made via the FYI website.

Please use this email address for all replies to this request:
[FOI #13817 email]

Is [Hutt City Council request email] the wrong address for Official Information
requests to Hutt City Council? If so, please contact us using this form:
https://fyi.org.nz/change_request/new?bo...

Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
https://fyi.org.nz/help/officers

If you find this service useful as an Official Information officer, please
ask your web manager to link to us from your organisation's OIA or LGOIMA
page.

-------------------------------------------------------------------

References

Visible links
1. mailto:[FOI #13817 email]
2. http://www.huttcity.govt.nz/
3. http://www.huttcity.govt.nz/
4. http://heart.huttcity.govt.nz/

hide quoted sections

Link to this

From: Euan Kyle
Hutt City Council


Attachment hccsmalllogo 12fb0640 f486 4c5a a775 f4ab1b1dfb5d.jpg
20K Download

Attachment 12153HaHEmailSignatureFINAL 3cd6181d 2156 4dde 9fbd b6f7f302ed05.JPG.jpg
35K Download


16/10/2020  

   

   
Michael Brown

[1][FOI #13817 email]

 

 

 

 

 

 

Dear Michael Brown,

Request for Information – Local Government Official Information and
Meetings Act 1987

We refer to your official information request dated 15 September for
information regarding commuter cycleway planning and strategy.

Part of the information you have requested can be found below. However,
our Senior Project Engineer, Simon Cager, who would be able to give you a
better response with more context, is on sick leave until the end of
October. Once he has returned, he will be able to answer your request in
more detail.

•                  Although the [2]Walk and Cycle the Hutt 2014-2019
document is outside the specified date range, the content is still largely
relevant and is not considered out of date.

•                  HCC has three major cycleway projects, the Wainuiomata
Hill Shared Path is complete, the Beltway is under construction and the
Eastern Bays Shared Path is in the consenting phase. The Eastern Bays
Shared Path was successful in gaining a government grant from the economic
stimulus package (shovel ready) introduced after the Covid 19 level 4
lockdown. We expect construction to commence mid-2021.

•                  NZTA have a cycleway project from Ngauranga to Melling
with the Petone to Melling section under construction and the Ngauranga to
Petone section in the consenting phase.

•                  HCC are very aware of the need to connect and activate
the cycleway network being framed by the three major projects and work is
underway to develop programs of work to achieve this objective. Simon is
best placed to provide the detail around this work.

•                  All transport related projects being considered in the
Hutt have an active mode component. These include the RiverLink and Cross
Valley Transport Connections projects where public transport and active
modes are a major consideration in the development of options.

Apologies that this may not be a satisfactory answer in the meantime,
however Mr Cager will be able to respond to you and supply any current HCC
planning and strategy documents, such as they exist, around development or
improvement of the commuter cycleway infrastructure in the Hutt Valley
upon his return.

You have the right to seek an investigation and review by the Ombudsman of
this decision. Information about how to make a complaint is available at
[3]www.ombudsman.parliament.nz or freephone 0800 802 602.

If you wish to discuss this decision with us, please feel free to contact
our Head of Transport, City and Community Services, John Gloag at
[4][email address].

Yours sincerely,

 

Euan Kyle
Senior Advisor, Official Information and Privacy

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New
Zealand
T 04 570 6702 W [5]www.huttcity.govt.nz

 

From: Euan Kyle
Sent: Thursday, 15 October 2020 10:17 AM
To: [FOI #13817 email]
Subject: RE: Official Information request - Commuter cycleway planning and
strategy [#52E44Q]

 

15/10/2020  

   

   

 
Michael Brown
 
[6][FOI #13817 email]
 
 
 

Dear Michael Brown,

 

REQUEST FOR INFORMATION - LOCAL GOVERNMENT OFFICIAL INFORMATION AND
MEETINGS ACT 1987: ACKNOWLEDGEMENT OF REQUEST

 

I am writing to acknowledge receipt of your official information request
dated 15 September for information regarding commuter cycleway planning
and strategy.

 

We received your request on 16 September 2020. We apologise for missing
this request when it first came in. We are in the process of improving our
LGOIMA process and service and unfortunately we missed this email and I
apologise that we were not able to meet your expectations or our
requirements under the legislation. We will get our response to you as
soon as possible.

 

Your request is being coordinated by our infrastructure team. If any
additional factors come to light which are relevant to your request,
please do not hesitate to contact us so that these can be taken into
account.

 

Yours sincerely,

 

 

Euan Kyle
Senior Advisor, Official Information and Privacy

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New
Zealand
T 04 570 6702 W [7]www.huttcity.govt.nz

 

Euan Kyle
Senior Advisor – OIA & Privacy

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New
Zealand
T 04 570 6702, M 022 4155438,  W [8]www.huttcity.govt.nz

         [9][IMG]

 

 

IMPORTANT: The information contained in this e-mail message may be legally
privileged or confidential. The information is intended only for the
recipient named in the e-mail message. If the reader of this e-mail
message is not the intended recipient, you are notified that any use,
copying or distribution of this e-mail message is prohibited. If you have
received this e-mail message in error, please notify the sender
immediately. Thank you.

-----Original Message-----
From: "Michael Brown" <[FOI #13817 email]>
Sent: Tuesday, 15 September 2020 8:56 PM
To: "OIA/LGOIMA requests at Hutt City Council" <[Hutt City Council request email]>
Subject: Official Information request - Commuter cycleway planning and
strategy

Dear Hutt City Council,

I am interested in knowing more about Hutt City Council planning around
cycleways, in particular strategic planning for commuter routes around
Lower Hutt and connecting these through to Wellington.

Searching your website and elsewhere reveals only the now out-of-date
"Walk and Cycle the Hutt 2014-2019" document
(http://iportal.huttcity.govt.nz/Record/R...), plus some
information on the recreation-focused Taita-Seaview cycleway. There is
also some online documentation about the Wellington to Hutt Valley
cycleway or W2HV
(https://www.nzta.govt.nz/assets/projects...),
recently announced as being funded by central government as a "shovel
ready" project.

Can you please supply any current HCC planning and strategy documents,
such as they exist, around development or improvement of the commuter
cycleway infrastructure in the Hutt Valley?

I'm especially interested in HCC planning for feeder cycleways to connect
with the W2HV (such as cross-valley routes or connecting to the riverside
trail network), as well as modelling of routes, data gathered on commuter
cycle use to and from the Valley, efficacy of the existing network of
shared pathways, etc.

Yours faithfully,

Michael Brown

-------------------------------------------------------------------

This is an Official Information request made via the FYI website.

Please use this email address for all replies to this request:
[FOI #13817 email]

Is [Hutt City Council request email] the wrong address for Official Information
requests to Hutt City Council? If so, please contact us using this form:
https://fyi.org.nz/change_request/new?bo...

Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
https://fyi.org.nz/help/officers

If you find this service useful as an Official Information officer, please
ask your web manager to link to us from your organisation's OIA or LGOIMA
page.

-------------------------------------------------------------------

References

Visible links
1. mailto:[FOI #13817 email]
2. http://iportal.huttcity.govt.nz/Record/R...
3. http://www.ombudsman.parliament.nz/
4. mailto:[email address]
5. http://www.huttcity.govt.nz/
6. mailto:[FOI #13817 email]
7. http://www.huttcity.govt.nz/
8. http://www.huttcity.govt.nz/
9. http://heart.huttcity.govt.nz/

hide quoted sections

Link to this

From: Michael Brown

Dear Euan Kyle,

Thanks for your reply. I appreciate the summary of work currently underway and the intent behind it. I would encourage HCC to consider drafting an updated Walk and Cycle the Hutt strategic statement incorporating current data and strategic contexts, such as the Climate Emergency declared by HCC in 2019.

I await further details from Mr Cager and will keep this OIA request open until then.

Yours sincerely,

Michael Brown

Link to this

From: Michael Brown

Dear Euan Kyle,

Just checking in to see if Mr Cager has been able to return to work and make any progress with this request.

Yours sincerely,

Michael Brown

Link to this

From: Euan Kyle
Hutt City Council


Attachment hccsmalllogo 12fb0640 f486 4c5a a775 f4ab1b1dfb5d.jpg
20K Download

Attachment 12153HaHEmailSignatureFINAL 3cd6181d 2156 4dde 9fbd b6f7f302ed05.JPG.jpg
35K Download

Attachment Hutt City Cycling and Micromobility SSBC draft issued for Waka Kotahi fe....pdf
7.8M Download View as HTML


19/11/2020

 

Michael Brown

[1][FOI #13817 email]

 

 

 

Dear Michael Brown,

 

Request for Information – Local Government Official Information and
Meetings Act 1987

 

We refer to your official information request dated 15 September for
information regarding commuter cycleway planning and strategy.

 

Apologies for the delay, Mr Cager was delayed in his return to work and
then had a large amount of work to catch up on as I’m sure you will
understand.

 

The only aspect Mr Cager had to add to what was already supplied was the
work we have been undertaking on planning for network development and
connectivity.

 

We have recently completed a draft business case on Cycling and
Micromobility which is with Waka Kotahi (NZTA) for endorsement (please see
attached). This includes programmes for short, medium and long term
development and eventually will also need to be consulted on and approved
via Council. This business case was inputted into via a number of
stakeholders including cycling advocates in its development.

 

It includes many linkages that you referred to within your original email.

 

We must stress that this is only a draft document and it is not approved
by either Council or Waka Kotahi currently. It will be subject to
amendments and its affordability given COVID-19. We ask that you do not
circulate without this caveat.

 

Hopefully this provides a satisfactory answer.

 

You have the right to seek an investigation and review by the Ombudsman of
this decision. Information about how to make a complaint is available at
[2]www.ombudsman.parliament.nz or freephone 0800 802 602.

 

If you wish to discuss this decision with us, please feel free to contact
our Head of Transport, City and Community Services, John Gloag at
[3][email address].

 

Regards,

 

Euan Kyle

Senior Advisor, Official Information and Privacy

 

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New
Zealand

T 04 570 6702 W www.huttcity.govt.nz

 

 

Euan Kyle
Senior Advisor – OIA & Privacy

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New
Zealand
T 04 570 6702,  W [4]www.huttcity.govt.nz

         [5][IMG]

 

 

IMPORTANT: The information contained in this e-mail message may be legally
privileged or confidential. The information is intended only for the
recipient named in the e-mail message. If the reader of this e-mail
message is not the intended recipient, you are notified that any use,
copying or distribution of this e-mail message is prohibited. If you have
received this e-mail message in error, please notify the sender
immediately. Thank you.

-----Original Message-----
From: Michael Brown
[mailto:[FOI #13817 email]]
Sent: Wednesday, 18 November 2020 7:44 PM
To: Euan Kyle
Subject: RE: Official Information request - Commuter cycleway planning and
strategy [#52E44Q]

 

Dear Euan Kyle,

 

Just checking in to see if Mr Cager has been able to return to work and
make any progress with this request.

 

Yours sincerely,

 

Michael Brown

 

-----Original Message-----

 

16/10/2020  

 

   

 

   

Michael Brown

 

[1][FOI #13817 email]

 

 

 

 

 

 

 

 

 

 

 

 

 

Dear Michael Brown,

 

Request for Information – Local Government Official Information and

Meetings Act 1987

 

We refer to your official information request dated 15 September for

information regarding commuter cycleway planning and strategy.

 

Part of the information you have requested can be found below. However,

our Senior Project Engineer, Simon Cager, who would be able to give you a

better response with more context, is on sick leave until the end of

October. Once he has returned, he will be able to answer your request in

more detail.

 

•                  Although the [2]Walk and Cycle the Hutt 2014-2019

document is outside the specified date range, the content is still largely

relevant and is not considered out of date.

 

•                  HCC has three major cycleway projects, the Wainuiomata

Hill Shared Path is complete, the Beltway is under construction and the

Eastern Bays Shared Path is in the consenting phase. The Eastern Bays

Shared Path was successful in gaining a government grant from the economic

stimulus package (shovel ready) introduced after the Covid 19 level 4

lockdown. We expect construction to commence mid-2021.

 

•                  NZTA have a cycleway project from Ngauranga to Melling

with the Petone to Melling section under construction and the Ngauranga to

Petone section in the consenting phase.

 

•                  HCC are very aware of the need to connect and activate

the cycleway network being framed by the three major projects and work is

underway to develop programs of work to achieve this objective. Simon is

best placed to provide the detail around this work.

 

•                  All transport related projects being considered in the

Hutt have an active mode component. These include the RiverLink and Cross

Valley Transport Connections projects where public transport and active

modes are a major consideration in the development of options.

 

Apologies that this may not be a satisfactory answer in the meantime,

however Mr Cager will be able to respond to you and supply any current HCC

planning and strategy documents, such as they exist, around development or

improvement of the commuter cycleway infrastructure in the Hutt Valley

upon his return.

 

You have the right to seek an investigation and review by the Ombudsman of

this decision. Information about how to make a complaint is available at

[3]www.ombudsman.parliament.nz or freephone 0800 802 602.

 

If you wish to discuss this decision with us, please feel free to contact

our Head of Transport, City and Community Services, John Gloag at

[4][email address].

 

Yours sincerely,

 

 

 

Euan Kyle

Senior Advisor, Official Information and Privacy

 

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New

Zealand

T 04 570 6702 W [5]www.huttcity.govt.nz

 

 

 

From: Euan Kyle

Sent: Thursday, 15 October 2020 10:17 AM

To: [FOI #13817 email]

Subject: RE: Official Information request - Commuter cycleway planning and

strategy [#52E44Q]

 

 

 

15/10/2020  

 

   

 

   

 

 

Michael Brown

 

[6][FOI #13817 email]

 

 

 

 

Dear Michael Brown,

 

 

 

REQUEST FOR INFORMATION - LOCAL GOVERNMENT OFFICIAL INFORMATION AND

MEETINGS ACT 1987: ACKNOWLEDGEMENT OF REQUEST

 

 

 

I am writing to acknowledge receipt of your official information request

dated 15 September for information regarding commuter cycleway planning

and strategy.

 

 

 

We received your request on 16 September 2020. We apologise for missing

this request when it first came in. We are in the process of improving our

LGOIMA process and service and unfortunately we missed this email and I

apologise that we were not able to meet your expectations or our

requirements under the legislation. We will get our response to you as

soon as possible.

 

 

 

Your request is being coordinated by our infrastructure team. If any

additional factors come to light which are relevant to your request,

please do not hesitate to contact us so that these can be taken into

account.

 

 

 

Yours sincerely,

 

 

 

 

 

Euan Kyle

Senior Advisor, Official Information and Privacy

 

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New

Zealand

T 04 570 6702 W [7]www.huttcity.govt.nz

 

 

 

Euan Kyle

Senior Advisor – OIA & Privacy

 

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New

Zealand

T 04 570 6702, M 022 4155438,  W [8]www.huttcity.govt.nz

 

         [9][IMG]

 

 

 

 

 

IMPORTANT: The information contained in this e-mail message may be legally

privileged or confidential. The information is intended only for the

recipient named in the e-mail message. If the reader of this e-mail

message is not the intended recipient, you are notified that any use,

copying or distribution of this e-mail message is prohibited. If you have

received this e-mail message in error, please notify the sender

immediately. Thank you.

 

-------------------------------------------------------------------

Please use this email address for all replies to this request:

[FOI #13817 email]

 

Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:

https://fyi.org.nz/help/officers

 

If you find this service useful as an Official Information officer, please
ask your web manager to link to us from your organisation's OIA or LGOIMA
page.

 

-------------------------------------------------------------------

 

References

Visible links
1. mailto:[FOI #13817 email]
2. http://www.ombudsman.parliament.nz/
3. mailto:[email address]
4. http://www.huttcity.govt.nz/
5. http://heart.huttcity.govt.nz/

hide quoted sections

Link to this

From: Michael Brown

Dear Euan,

Thanks for this draft SSBC. It has a good level of detail and is quite illuminating about the Council's thinking over the cycleway network. I look forward to the final version.

I may as well take the opportunity to give a couple of pieces of feedback:

1. It may be worth more explicitly noting the benefits of cycling to lowering HV's carbon footprint. In Jorn Scherzer's recent report on carbon neutrality to the Policy and Regulatory Committee (http://infocouncil.huttcity.govt.nz/Open...), there is a chart with 2012-13 data showing that the greatest share of the Hutt Valley's carbon emissions (47%) are from transport, most of which I expect would be cars. Shifting car trips to bike trips would help lower carbon emissions.

2. I was surprised that there is not more consideration of how the HV cycle network will integrate with Te Ara Tupua to best leverage the massive investment in this HV-WGTN commuter route. I think the report downplays the potential to increase HV-WGTN cycle commuting. Although 62% of HV residents may work in the Valley (p.12), the number of residents who commute to Wellington is also very high and I think this should really be noted in the 'take aways' below the table.

Thanks again for following up on my OIA request.

Yours sincerely,

Michael Brown

Link to this

From: Euan Kyle
Hutt City Council

Hi Michael,

Thank you for the feedback, I have passed it on to the relevant officers.

Have a great weekend.

Regards,

Euan Kyle
Senior Advisor, Official Information and Privacy

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New Zealand
T 04 570 6702 W www.huttcity.govt.nz

Euan Kyle
Senior Advisor – OIA & Privacy

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New Zealand
T 04 570 6702, W www.huttcity.govt.nz, F www.facebook.com/huttcitycouncil

IMPORTANT: The information contained in this e-mail message may be legally privileged or confidential. The information is intended only for the recipient named in the e-mail message. If the reader of this e-mail message is not the intended recipient, you are notified that any use, copying or distribution of this e-mail message is prohibited. If you have received this e-mail message in error, please notify the sender immediately. Thank you.
-----Original Message-----
From: Michael Brown [mailto:[FOI #13817 email]]
Sent: Thursday, 19 November 2020 9:15 PM
To: Euan Kyle
Subject: RE: Official Information request - Commuter cycleway planning and strategy [#52E44Q]

Dear Euan,

Thanks for this draft SSBC. It has a good level of detail and is quite illuminating about the Council's thinking over the cycleway network. I look forward to the final version.

I may as well take the opportunity to give a couple of pieces of feedback:

1. It may be worth more explicitly noting the benefits of cycling to lowering HV's carbon footprint. In Jorn Scherzer's recent report on carbon neutrality to the Policy and Regulatory Committee (http://infocouncil.huttcity.govt.nz/Open...), there is a chart with 2012-13 data showing that the greatest share of the Hutt Valley's carbon emissions (47%) are from transport, most of which I expect would be cars. Shifting car trips to bike trips would help lower carbon emissions.

2. I was surprised that there is not more consideration of how the HV cycle network will integrate with Te Ara Tupua to best leverage the massive investment in this HV-WGTN commuter route. I think the report downplays the potential to increase HV-WGTN cycle commuting. Although 62% of HV residents may work in the Valley (p.12), the number of residents who commute to Wellington is also very high and I think this should really be noted in the 'take aways' below the table.

Thanks again for following up on my OIA request.

Yours sincerely,

Michael Brown

-----Original Message-----

19/11/2020

Michael Brown

[1][FOI #13817 email]

Dear Michael Brown,

Request for Information – Local Government Official Information and
Meetings Act 1987

We refer to your official information request dated 15 September for
information regarding commuter cycleway planning and strategy.

Apologies for the delay, Mr Cager was delayed in his return to work and
then had a large amount of work to catch up on as I’m sure you will
understand.

The only aspect Mr Cager had to add to what was already supplied was the
work we have been undertaking on planning for network development and
connectivity.

We have recently completed a draft business case on Cycling and
Micromobility which is with Waka Kotahi (NZTA) for endorsement (please see
attached). This includes programmes for short, medium and long term
development and eventually will also need to be consulted on and approved
via Council. This business case was inputted into via a number of
stakeholders including cycling advocates in its development.

It includes many linkages that you referred to within your original email.

We must stress that this is only a draft document and it is not approved
by either Council or Waka Kotahi currently. It will be subject to
amendments and its affordability given COVID-19. We ask that you do not
circulate without this caveat.

Hopefully this provides a satisfactory answer.

You have the right to seek an investigation and review by the Ombudsman of
this decision. Information about how to make a complaint is available at
[2]www.ombudsman.parliament.nz or freephone 0800 802 602.

If you wish to discuss this decision with us, please feel free to contact
our Head of Transport, City and Community Services, John Gloag at
[3][email address].

Regards,

Euan Kyle

Senior Advisor, Official Information and Privacy

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New
Zealand

T 04 570 6702 W www.huttcity.govt.nz

Euan Kyle
Senior Advisor – OIA & Privacy

Hutt City Council, 30 Laings Road, Private Bag 31912, Lower Hutt 5040, New
Zealand
T 04 570 6702, W [4]www.huttcity.govt.nz

[5][IMG]

IMPORTANT: The information contained in this e-mail message may be legally
privileged or confidential. The information is intended only for the
recipient named in the e-mail message. If the reader of this e-mail
message is not the intended recipient, you are notified that any use,
copying or distribution of this e-mail message is prohibited. If you have
received this e-mail message in error, please notify the sender
immediately. Thank you.

-------------------------------------------------------------------
Please use this email address for all replies to this request:
[FOI #13817 email]

Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://fyi.org.nz/help/officers

If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.

-------------------------------------------------------------------

hide quoted sections

Link to this

Things to do with this request

Anyone:
Hutt City Council only: