Further Capacity Improvements (WMUP 7)
Response by KiwiRail to T.J. Pohl on .
Successful.
Good afternoon TJ Please find the attached. We note this document is best read in conjunction with the Wellington Network Programme Business case whic...
Speed Restrictions and Network Rebuild
Response by KiwiRail to Isaac Morrison on .
Successful.
Good evening Isaac Please find our response below. Temporary Speed Restrictions (TSRs) are a standard maintenance tool used internationally to keep t...
P2P Line speed
Response by KiwiRail to Isaac Morrison on .
Waiting clarification.
And trying again   From: Dave Allard Sent: Monday, November 4, 2024 6:15 PM To: [FOI #28668 email] Subject: RE: Official Information request - P...
  Single-Stage Business Case Wellington Metro Railway Network Track Infrastructure Catch-Up Renewals Version 2.1 Document Information Version Des...
Report on Collision Risk at Wellington Station
Response by KiwiRail to Benjamin on .
Successful.
Dear Benjamin, please find attached our response for your OIA request for the a copy of the Wellington Risk Study.   Kind regards   The OCU Te...
Proposed closure of Ava railway bridge footpath
Response by KiwiRail to Mike Mellor on .
Successful.
Good afternoon Please find our response as per the attached. Kind regards Dave Dave Allard  | Senior Government Relations Advisor DDI: 027 201 8182...
Track infrastructure issue near Newmarket
Response by KiwiRail to Tom on .
Successful.
Thomas,   Thanks for contacting us.   KiwiRail monitors the condition of the rail network on an ongoing basis through a variety of inspection...
Good afternoon Patrick I have tried contacting you to see if there was a better contact address for you, but no luck.   Please find attached our...
Good afternoon Wade   Please find our response to your OIA request.   Kind regards   Dave   Dave Allard  | Senior Government Relations...
Class AM EMU Dwell Times
Response by Auckland Transport to Harriet Gale on .
Successful.
Dear Harriet   Thank you for your email this morning.  Please accept my sincere apologies for the delay in sending this response out to you.  We h...
Wairarapa Line tunnel works
Response by KiwiRail to Lloyd Davies on .
Awaiting classification.
Good afternoon Lloyd Please find our response below. Please note we have taken your query to mean the work completed at Easter, and any further work....
Good afternoon Please find the attached. Kind regards Dave Dave Allard  | Senior Government Relations Advisor DDI: 027 201 8182 Level 4, Wellington...
Options for ballast replacement in Auckland
Response by KiwiRail to R S Grant on .
Partially successful.
Good afternoon Grant. If you have a look at document three under the release, I think you will find that will answer your query about the various opti...
DC to AC overhead line conversion
Response by KiwiRail to Carl McCormack on .
Successful.
Good afternoon Carl   Please find our response to your query under the OIA. You asked - I was wondering if work were to be undertaken to convert...
Good afternoon Wendy Thank you for your enquiry regarding the land at 36 Station Road, Te Puke, currently leased by the Western Bay of Plenty District...
Block of line impact on freight share
Response by KiwiRail to Isaac Morrison on .
Long overdue.
Good afternoon Isaac Apologies for the delay in getting the reports loaded, but as per our previous letter, the studies and reports on the Decarbonisa...
NAL Reports
Response by KiwiRail to Iain Palmer on .
Successful.
Dear Mr Palmer   We are writing in response to your Official Information Act 1982 request dated 25 April 2016 for the following information:  ...
Dear W Please find attached a response to your Official Information Act request. Kind regards Office of Hon Simeon Brown Minister of Transport, Min...
Track rebuild Papakura to Pukekohe
Response by KiwiRail to Niall Robertson on .
Partially successful.
Good afternoon Niall. Please find our response below. As part of Stage 3b of the Rail Network Rebuild (RNR), drainage work is planned between Puhinui...
Good afternoon   Please find attached KiwiRail’s response to your OIA request.   Kind regards   Dave     Dave Allard  | Government Re...
Level crossing improvements on Wairarapa Line
Response by KiwiRail to Patrick Dunford on .
Partially successful.
Good afternoon Patrick Please see below the response form our Wairarapa Upgrades Team. KiwiRail has funding from the New Zealand Upgrade Programme (NZ...
Wellington Metro Upgrade
Response by KiwiRail to Iain Palmer on .
Successful.
Good afternoon Iain. I'd like to acknowledge receipt of your official information request dated 27 November 2021, for information on KiwiRail's the We...
Tēnā koe Patrick, Request for information 2023-122 I refer to your request for information dated 15 May 2023, which was received by Greater Wellin...
Hybrid trains vs other options
Response by Wellington Regional Council to Patrick Dunford on .
Successful.
Tēnā koe Patrick Request for information 2023-105 I refer to your request for information dated 30 April 2023, which was received by Greater Welli...
Third Main aka Track - Westfield to Quay Park
Response by KiwiRail to Harriet Gale on .
Successful.
Dear Harriet, Please find attached our response to your OIA request. Apologies for the delay. Ngā mihi Laura Laura Ratuva   |   Senior Communicat...