Wairarapa Line tunnel works
Lloyd Davies made this Official Information request to KiwiRail
This request has an unknown status. We're waiting for Lloyd Davies to read recent responses and update the status.
From: Lloyd Davies
Dear KiwiRail,
I am seeking all information related to any track or formation works undertaken inside the Wairarapa line tunnels after the completion of the block of line works in February 2025. Information should include detailed description of all work undertaken, reasons for the work not being done during the block of line works, costs associated with this work, and what further work is required.
Yours faithfully,
Lloyd Davies
From: Lloyd Davies
Dear KiwiRail,
Just following up to ensure my request has been received. Some form of acknowledgement is good practice.
Yours faithfully,
Lloyd Davies
From: Dave Allard
KiwiRail
Confirming this one has been received as well.
Cheers
Dave
-----Original Message-----
From: KiwiRail <[email address]>
Sent: Thursday, 26 June 2025 8:16 am
To: Dave Allard <[email address]>; OCU <[email address]>
Subject: FW: Official Information request - Wairarapa Line tunnel works
Thanks,
Scarlett Dellow | Community Engagement Advisor Second Floor, KiwiRail Building Millennium Centre, 604 Great South Road, Ellerslie, 1051 | Private Bag 92138, Auckland 1142, New Zealand
www.kiwirail.co.nz
Please consider the environment before printing.
The content of this message and any attachments may be privileged or confidential. If you have received this email in error please notify the sender and delete the email - unauthorised use is expressly prohibited. This email may have been corrupted or interfered with. KiwiRail does not warrant that this email and its contents are free from computer viruses or other defects.
-----Original Message-----
From: Lloyd Davies <[FOI #31296 email]>
Sent: Thursday, 26 June 2025 7:23 am
To: KiwiRail <[email address]>
Subject: Re: Official Information request - Wairarapa Line tunnel works
CAUTION EXTERNAL EMAIL: Do not click links or open attachments unless you know the content is safe.
Dear KiwiRail,
Just following up to ensure my request has been received. Some form of acknowledgement is good practice.
Yours faithfully,
Lloyd Davies
-------------------------------------------------------------------
Please use this email address for all replies to this request:
[FOI #31296 email]
Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://fyi.org.nz/help/officers
If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.
-------------------------------------------------------------------
hide quoted sections
From: Dave Allard
KiwiRail
Good afternoon Lloyd
Please find our response below.
Please note we have taken your query to mean the work completed at Easter, and any further work.
At Easter we undertook tamping work, after the track had time to go through its consolidation (i.e. the passage of trains causes some minor settlement so we go back to put the track to the design level).
The work could not be done during the block of line at Christmas because there was not enough time to achieve consolidation (i.e. we did run fully loaded trains to get through the critical settlement, but more was needed and there was not enough time to achieve this).
The total cost for the work at easter including both KiwiRail and contracted resources was approx. $270k. This allowed the track speed to be increased from 60kph to 90kph.
We will be going into the tunnel 26-27th July and 16-17th Aug to re-spread some of the ballast in the tunnel where the tamping activity did not use as much as expected.
This will improve the walking surface for our people when they undertake inspections or other work over the coming years. The cost if this work is estimated to be approx. $140k.
We trust this answers your queries.
Kind regards
Dave
Dave Allard | Senior Government Relations Advisor
DDI: 027 201 8182
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO Box 593, Wellington 6140, New Zealand
www.kiwirail.co.nz
-----Original Message-----
From: Lloyd Davies <[FOI #31296 email]>
Sent: Thursday, 12 June 2025 8:36 pm
To: KiwiRail <[email address]>
Subject: Official Information request - Wairarapa Line tunnel works
CAUTION EXTERNAL EMAIL: Do not click links or open attachments unless you know the content is safe.
Dear KiwiRail,
I am seeking all information related to any track or formation works undertaken inside the Wairarapa line tunnels after the completion of the block of line works in February 2025. Information should include detailed description of all work undertaken, reasons for the work not being done during the block of line works, costs associated with this work, and what further work is required.
Yours faithfully,
Lloyd Davies
-------------------------------------------------------------------
This is an Official Information request made via the FYI website.
Please use this email address for all replies to this request:
[FOI #31296 email]
Is [KiwiRail request email] the wrong address for Official Information requests to KiwiRail? If so, please contact us using this form:
https://fyi.org.nz/change_request/new?bo...
Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://fyi.org.nz/help/officers
If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.
-------------------------------------------------------------------
hide quoted sections
Things to do with this request
- Add an annotation (to help the requester or others)
- Download a zip file of all correspondence (note: this contains the same information already available above).