Critical Path Project Plan for upgrading the Picton Rail Enabled Ferry Terminal
Jon Eriksen made this Official Information request to KiwiRail
This request has an unknown status. We're waiting for Jon Eriksen to read recent responses and update the status.
From: Jon Eriksen
Dear KiwiRail,
Dear KiwiRail,
This is an Official Information Act request.
Please provide the Critical Path Analysis Gantt chart for moving upgrading the Picton rail enabled ferry terminal and related infrastructure to support the operation of the new ferries it has been announced will be purchased this year and operational by 2029..
It would be appreciated if the data was presented in two formats, as follows;
1) A multi-page pdf Gantt Chart, either A3 or A2 size, graphically showing the durations of all activities and the dependencies between them AND
2) An Excel spreadsheet of the data represented in the Gantt Chart that lists the following for each Activity
- ID
- Name
-Duration
- Scheduling method (asap, alap etc)
- Predecessor tasks
- Successor tasks
- Free slack
It is appreciated that this plan will have activities longer than 3 months. Therefore, for all such tasks can the assumptions or relevant data supporting the duration allowed for the task please also be provided.
Regards
Jon Eriksen
From: Dave Allard
KiwiRail
Good morning Jon
We have received your request, as per the below.
This information however is not held by KiwiRail, and instead is the responsibility of Ferry Holdings Ltd, which has been set up for the purpose of procuring and managing the infrastructure projects related to the replacement of the Interislander Ferries.
Accordingly, as required by section 14 of the OIA we are transferring your request.
You will hear further from Ferry Holdings Ltd concerning your request.
Kind regards
Dave
Dave Allard | Senior Government Relations Advisor
DDI: 027 201 8182
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO Box 593, Wellington 6140, New Zealand
www.kiwirail.co.nz
-----Original Message-----
From: Jon Eriksen <[FOI #30912 email]>
Sent: Wednesday, 7 May 2025 4:56 pm
To: KiwiRail <[email address]>
Subject: Official Information request - Critical Path Project Plan for upgrading the Picton Rail Enabled Ferry Terminal
CAUTION EXTERNAL EMAIL: Do not click links or open attachments unless you know the content is safe.
Dear KiwiRail,
This is an Official Information Act request.
Please provide the Critical Path Analysis Gantt chart for moving upgrading the Picton rail enabled ferry terminal and related infrastructure to support the operation of the new ferries it has been announced will be purchased this year and operational by 2029..
It would be appreciated if the data was presented in two formats, as follows;
1) A multi-page pdf Gantt Chart, either A3 or A2 size, graphically showing the durations of all activities and the dependencies between them AND
2) An Excel spreadsheet of the data represented in the Gantt Chart that lists the following for each Activity
- ID
- Name
-Duration
- Scheduling method (asap, alap etc)
- Predecessor tasks
- Successor tasks
- Free slack
It is appreciated that this plan will have activities longer than 3 months. Therefore, for all such tasks can the assumptions or relevant data supporting the duration allowed for the task please also be provided.
Regards
Jon Eriksen
-------------------------------------------------------------------
This is an Official Information request made via the FYI website.
Please use this email address for all replies to this request:
[FOI #30912 email]
Is [KiwiRail request email] the wrong address for Official Information requests to KiwiRail? If so, please contact us using this form:
https://fyi.org.nz/change_request/new?bo...
Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://fyi.org.nz/help/officers
If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.
-------------------------------------------------------------------
hide quoted sections
From: Info
Kia ora Jon,
Thank you for your query dated May 8, 2025
Ferry Holdings Limited is currently working with KiwiRail, CentrePort
Limited, and Port Marlborough New Zealand Limited to confirm the design
requirements and commercial arrangements.
Ferry Holdings is declining to release the requested information on the
following two grounds.
* The information requested in Questions 1 and 2, where it does not yet
exist is being declined under Section 19 of the Official Information
Act ,
* Where the information does exist it is being declined under Section 9
of the Official Information Act due to the release of commercial
sensitivities of the information requested and the potential impact
on the completion of the commercial contracts .
Yours sincerely,
Ferry Holdings team
04 886 3440
[email address]
Ferry Holdings Limited
P O Box 650 Wellington 6140
30 Waring Taylor Street, Wellington, 6011
Things to do with this request
- Add an annotation (to help the requester or others)
- Download a zip file of all correspondence (note: this contains the same information already available above).