Great North Road Roadworks in Waterview
Tom made this Official Information request to New Zealand Transport Agency
This request has an unknown status. We're waiting for Tom to read recent responses and update the status.
From: Tom
Dear New Zealand Transport Agency,
What is the plan for the roadworks being undertaken on Great North Rd in Waterview, and what changes to the road layout will be needed to achieve this.
Yours faithfully,
Tom
From: Official Correspondence
New Zealand Transport Agency
Kia ora Tom
This email acknowledges receipt of your below correspondence.
Your correspondence has been forwarded to the appropriate section of Waka
Kotahi NZ Transport Agency, and a response will be provided to you as soon
as possible.
If you would like to contact us about this, please respond to us by email
at [1][NZTA request email].
Ngâ mihi
Ministerial Services
Te Waka Kôtuia | Engagement & Partnerships
Waka Kotahi NZ Transport Agency
[2]twitter | [3]youtube | [4]facebook
[5][IMG]
show quoted sections
From: Official Correspondence
New Zealand Transport Agency
Kia ora Tom
Thank you for your email below requesting information regarding the
roadwork on Great North Road.
The information you have requested is more closely connected with the
functions of Auckland Transport than with Waka Kotahi NZ Transport
Agency. Therefore, the Project & Business Interface Team at Auckland
Transport will address their response directly to you.
Ngâ mihi
Ministerial Services
Te Waka Kôtuia | Engagement & Partnerships
Waka Kotahi NZ Transport Agency
[1]twitter | [2]youtube | [3]facebook
[4][IMG]
show quoted sections
From: Projects (AT)
Hi Tom
The works being undertaken are stabilisation of an historic and ongoing
slip affecting a section of Great North Rd at Waterview.
The slip has caused considerable damage to the shared pathway at the
location, making them unusable and poses a high risk for damaging a
section of the road. Failure of a section of the road would cause major
traffic congestion and add considerable cost to fix. The scope of work for
the project is:
1. To create room for site establishment, access for heavy
vehicles and safety zones by shifting all four traffic lanes to the west,
followed by installing fences and barriers around the works site.
2. Demolish path and retaining wall then level the site.
3. Construct in-ground slip stabilisation concrete panels.
4. Reinstate the retaining wall and path, repair road lane and
kerb etc.
Note, all stabilisation works are off road to minimise disruption. All
four vehicle lanes will be kept open throughout.
The impacts wile undertaking the works include:
• Re-alignment of the traffic lanes.
• Temporary relocation of two bus stops.
• Closure of the Herdman St intersection.
• Closure of the right turn into Oakley Rd
• Closure of a section of pathway requiring users to cross the
road at Alford St and back again at Herdman St.
The impact on travel times and bus services should be minimal.
Project duration is six to nine months with completion targeted for
February 2024.
Kind regards
Sandy Webb | Project and Business Interface Lead
Infrastructure Project Delivery|Integrated Networks
Auckland Transport
20 Viaduct Harbour Avenue, Auckland 1010
Direct Dial: 09 930 5091
Project Group: 09 930 5090
[1][email address] | [2]www.at.govt.nz
show quoted sections