I-Rex schedual update

George Bryant made this Official Information request to KiwiRail

The request was successful.

From: George Bryant

Dear KiwiRail,

With recent talks about the new Interislander ferries arriving in 2025, and work starting on the Inter-island Resilient Connection (IRex) in picton recently.
Could you please provide a current scheduled completion date of IRex, and key milestone dates, in particularly when this facility will be complete enough to allow use of the new ferries.

Yours faithfully,
George Bryant

Link to this

From: Dave Allard
KiwiRail

Good afternoon George

Thank you for your enquiry under the OIA.
We have received your request and will be processing it.
We received your request on 5 August 2022, and will endeavour to respond to your request as soon as possible and in any event no later than 2 September 2022, i.e. the 20 working days after the day your request was received.
If we are unable to respond to your request by then, we will notify you of an extension of that timeframe.

I’ll be looking after your request, so any questions please get in touch with me at this email address, or on the number below.

Cheers
Dave

Dave Allard  | Senior Government Relations Advisor
DDI: +64 4 498 3218
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO Box 593, Wellington 6140, New Zealand

www.kiwirail.co.nz
-----Original Message-----
From: George Bryant <[FOI #20146 email]>
Sent: Friday, 5 August 2022 12:01 pm
To: KiwiRail <[email address]>
Subject: Official Information request - I-Rex schedual update

CAUTION EXTERNAL EMAIL: Do not click links or open attachments unless you know the content is safe.

Dear KiwiRail,

With recent talks about the new Interislander ferries arriving in 2025, and work starting on the Inter-island Resilient Connection (IRex) in picton recently.
Could you please provide a current scheduled completion date of IRex, and key milestone dates, in particularly when this facility will be complete enough to allow use of the new ferries.

Yours faithfully,
George Bryant

-------------------------------------------------------------------

This is an Official Information request made via the FYI website.

Please use this email address for all replies to this request:
[FOI #20146 email]

Is [KiwiRail request email] the wrong address for Official Information requests to KiwiRail? If so, please contact us using this form:
https://fyi.org.nz/change_request/new?bo...

Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://fyi.org.nz/help/officers

If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.

-------------------------------------------------------------------

hide quoted sections

Link to this

From: Dave Allard
KiwiRail


Attachment image001.png
3K Download

Attachment Timeline.pdf
36K Download View as HTML


Good afternoon George.

 

Thank you for your OIA request asking for - a current scheduled completion
date of IRex, and key milestone dates, in particularly when this facility
will be complete enough to allow use of the new ferries.

On review of your request, we have determined the bulk of the information
you are asking for is hosted on the dedicated iReX website – found here
[1]www.irex.co.nz

 

However, we were unsure if there was a suitable timeline hosted on the
site, so we include it here.

 

Any further questions, please get in touch.

 

Kind regards

Dave

 

Dave Allard  | Senior Government Relations Advisor

DDI: +64 4 498 3218
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO
Box 593, Wellington 6140, New Zealand

[2]Description: Description: cid:image001.png@01D46098.E77643D0

[3]www.kiwirail.co.nz

 

References

Visible links
1. http://www.irex.co.nz/
3. http://www.kiwirail.co.nz/

Link to this

Things to do with this request

Anyone:
KiwiRail only: