Requests similar to 'EF Rebuild'

Replacement for DC Locomotives
Response by KiwiRail to Carl McCormack on .
Successful.
Good afternoon Carl Thank you for your request under the OIA asking for information on the D.C class of locomotives. We will process your request...
Progress on EF locomotive rebuilds
Response by KiwiRail to William Blackmore on .
Successful.
Good afternoon Bill   Thank you for your enquiry on the Electric Locomotives. Please find the response to your OIA request below.   As you may...
DC to AC overhead line conversion
Response by KiwiRail to Carl McCormack on .
Successful.
Good afternoon Carl   Please find our response to your query under the OIA. You asked - I was wondering if work were to be undertaken to convert...
Locomotive mean distance between failure figures
Response by KiwiRail to LJ Holden on .
Successful.
Good afternoon   Please find attached our response to your recent OIA enquiry. I hope this is useful.   Any questions, please get in touch....
Good afternoon Brett   Please find our response as attached.   Kind regards   Dave   Dave Allard  | Government Relations Advisor DDI:...
Length of trains on North Auckland Line
Response by KiwiRail to David Farrar on .
Successful.
Good morning David On behalf of KiwiRail I'd like to acknowledge your OIA request, as detailed in your email below. We received your request on 12 Ja...
Cattle grazing on Kiwirail land
Response by KiwiRail to Harrison on .
Refused.
Thank you for your OIA request, asking for information on KiwiRail and grazing rights.   We received your request on 22/12/2020. We will endeavour...
DL Class locomotive fleet list
Response by KiwiRail to Julien Michel on .
Successful.
Good afternoon Julien, hope you are staying safe in lockdown. Thanks for getting in touch with your request for a list of KiwiRail's DL fleet. I'll ge...
P2P Line speed
Response by KiwiRail to Isaac Morrison on .
Waiting clarification.
And trying again   From: Dave Allard Sent: Monday, November 4, 2024 6:15 PM To: [FOI #28668 email] Subject: RE: Official Information request - P...
Southerner service
Response by KiwiRail to Barry Garrick on .
Successful.
Good afternoon Barry I'd like to acknowledge receipt of your official information request for information on passenger rail studies We received your r...
Driver Support
Response by KiwiRail to Mike Hunua on .
Successful.
Good afternoon Mike   I'd like to acknowledge receipt of your official information request dated 21/01/2022,  for information on what support is p...
Taumarunui train stop communications and correspondence ​ ​ request
Response by KiwiRail to MS on .
Long overdue.
Good afternoon   Following up on the below – is there a email to contact you through?   Cheers Dave   Dave Allard  | Senior Government Re...
Options for ballast replacement in Auckland
Response by KiwiRail to R S Grant on .
Partially successful.
Good afternoon Thank you for your enquiry, our response is as per the below. The Rail Network Rebuild is not light, routine maintenance, which can a...
Wellington Metro Upgrade
Response by KiwiRail to Iain Palmer on .
Successful.
Good afternoon Iain. I'd like to acknowledge receipt of your official information request dated 27 November 2021, for information on KiwiRail's the We...
Good afternoon Brent   I refer to your email dated 4 June 2020, and copied below -   The most recent Picton ferry terminal development consulta...
I-Rex schedual update
Response by KiwiRail to George Bryant on .
Successful.
Good afternoon George Thank you for your enquiry under the OIA. We have received your request and will be processing it. We received your request on 5...
Rail Heritage
Response by KiwiRail to Iain Palmer on .
Partially successful.
Good afternoon Iain. I'd like to acknowledge receipt of your official information request dated 27 November 2021, for information on KiwiRail's work w...
KiwiRail Brand Guidelines
Response by KiwiRail to Tommi Joyce on .
Successful.
Good afternoon Tommi Please find attached the relevant document which refers to put KiwiRail livery. We trust this answers your query, but any further...
Picton Port Gas Leaks
Response by KiwiRail to Brent Yardley on .
Refused.
Good afternoon   Please find attached our response to your OIA request. Any questions, please let me know.   Cheers   Dave   Dave All...
Good afternoon Wade I'd like to acknowledge receipt of your official information request dated 7 March 2022, for information on the electrification of...
Good afternoon I'd like to acknowledge your request - we'll be back to you with a response as soon as possible, in any event no later than 22 November...
Track rebuild Papakura to Pukekohe
Response by KiwiRail to Niall Robertson on .
Partially successful.
Good morning Nial I'd like to acknowledge receipt of your official information request for information on KiwiRail’s track rebuild work on the Papakur...
Good morning Tony   I'd like to acknowledge receipt of your official information request dated 23 March 2021,  for the CRL report authored by Pete...
New Capital Connection Rolling Stock - Provision for bicycles
Response by KiwiRail to Richard Young on .
Long overdue.
Good afternoon Richard I'd like to acknowledge receipt of your official information request dated 14 Feb 2022, for information on the refurbished roll...
Feasibility study for the stratford - Okahukura line
Response by KiwiRail to Matthew Maxwell on .
Long overdue.
Good afternoon Matthew I'd like to acknowledge receipt of your official information request for information on the Stratford - Okahukura line. We rece...