Dear Tasman District Council,

How many code compliance certificates are still outstanding for consented building activities, grouped by year of consent granted?

I understand that a code compliance certificate is required within 2 years of consent.

www.building.govt.nz states "Building consent authorities need to be proactive in the way they manage issuing code compliance"

Does TDC comply with this requirement

Yours faithfully,

Tony Bach

Link to this

From: LGOIMA
Tasman District Council


Attachment image85e5e5.JPG.jpg
5K Download

Attachment image35664f.PNG.png
1K Download

Attachment image0032d9.PNG.png
1K Download

Attachment imagedcdb91.JPG.jpg
34K Download


Thank you for your request for information received on 22 February 2019.

 

Under LGOIMA, your request must be dealt with as soon as is reasonably
practicable and in no case later than 20 working days after the day on
which the request is received.  20 working days excludes Saturdays and
Sundays, Public Holidays and the period between 25 December and 15 January
inclusive.  On this basis, we calculate a response to your request
received is due by 22 March 2019, at the latest.  We shall of course
endeavour to process your request as quickly as staff resources allow.

 

For requests that are likely to involve substantial collation and/or
research, there may be a charge for staff time.  Under our charging
policy, staff time for the first hour is free of charge.  Thereafter this
will be charged at the prescribed rate of $38 (GST inclusive) per half
hour.  In addition, there will be photocopying charges at 20c per sheet,
with the first 20 pages being copied free of charge.  Under clause 13(4)
of LGOIMA we do have the ability to request the amounts due are paid in
advance of the release of information.   Please be assured that if a
charge is likely to apply you will be notified ahead of the request being
processed so that you can decide if you wish to proceed.  At that time you
will also be given the option to refine your request.

 

Kind regards,

 

Kate Redgrove, Executive Advisor

 

 

LGOIMA 
LGOIMA Requests
DDI 03 543 8400 | [1][Tasman District Council request email]
Private Bag 4, Richmond 7050, NZ
[2]Logo [3]Facebook [4]Twitter
[5]Find water saving tips on our website
[6][IMG]
This e-mail message and any attached files may contain confidential
information, and may be subject to legal professional privilege. If you
are not the intended recipient, please delete.

show quoted sections

Link to this

From: LGOIMA
Tasman District Council


Attachment image002.png
82K Download

Attachment image10f425.JPG.jpg
5K Download

Attachment image4dcc5a.PNG.png
1K Download

Attachment image4810b7.PNG.png
1K Download

Attachment image5b4e43.JPG.jpg
34K Download


Good afternoon,

 

In relation to your request for information, below is a table of Consents
as requested (please note some of the consents may include PIM’s,
Amendments and COA’s which wouldn’t require a CCC)

If you would like this report without PIM’s, Amendments and COA’s this is
possible but may take several hours to collate which would be chargeable.

 

*please note that some 2017/2018 consents have not currently meet their
two year anniversary

 

Building Assurance as an accredited Building Consent Authority have the
obligation to meet the Building Act 2004, we are audited in a two yearly
cycle by IANZ to ensure we meet our obligations.

 

We have procedures in place to cover sect 92 to 95 of the Building Act
2004 (came into effect 31 March 2005) which relates to the Issuing of Code
Compliance Certificate and making a decision to Issue or Refuse the Code
Compliance Certificate within 2 years of the Building Consent being
granted. This includes sending a reminder to the Owner of the property on
the 22 month anniversary of the consent being granted to advise their Code
Compliance Certificate is outstanding. On the 2 year anniversary a
technical staff member reviews the consents and chooses to Issue or refuse
the Code Compliance Certificate.

 

I must advise you of your right to complain to an Ombudsman if you do not
believe you have been given a reasonable response to your request.  This
right to complain is dealt with in section 27 of the Local Government
Official Information and Meetings Act.

 

Please note that we now have a dedicated e-mail address
[1][Tasman District Council request email] to receive requests for official information. 
Direction of future requests to this e-mail address will assist in
processing time.

 

Kind regards,

 

Kate Redgrove, Executive Advisor

 

 

 

 

LGOIMA 
LGOIMA Requests
DDI 03 543 8400 | [2][Tasman District Council request email]
Private Bag 4, Richmond 7050, NZ
[3]Logo [4]Facebook [5]Twitter
[6]Find water saving tips on our website
[7][IMG]
This e-mail message and any attached files may contain confidential
information, and may be subject to legal professional privilege. If you
are not the intended recipient, please delete.

show quoted sections

Link to this

We don't know whether the most recent response to this request contains information or not – if you are Tony Bach please sign in and let everyone know.

Things to do with this request

Anyone:
Tasman District Council only: