Dear KiwiRail,

Under the Official Information Act 1982, I request the following information relating to the "rail max reuse" option chosen for the Cook Strait ferry replacement project, with particular focus on Wellington infrastructure:

Any diagrams, design drawings, or engineering schematics that show how the "rail max reuse" option will be implemented at Wellington, including the proposed new linkspan, wharf extension, and integration with existing yards and terminal areas.

Any descriptions, presentations, or planning documents that outline how existing Wellington facilities will be reused or modified under the rail-max reuse approach.

Briefing notes, reports, or summaries provided to Ministers or senior officials since 1 January 2024 that specifically discuss Wellington infrastructure works under the rail max reuse option.

Yours faithfully,

T.J. Pohl

Link to this

From: Dave Allard
KiwiRail

Good afternoon TJ

This email is to advise we are transferring part of your request to Ferry Holdings Ltd.
Any information post 5 March 2025 on the reuse options will be held by Ferry Holdings and not KiwiRail as it has taken over the ferry replacement project.

Ferry holdings will be in touch directly re your request.

Kind regards

Dave

Dave Allard  | Senior Government Relations Advisor
DDI: 027 201 8182
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO Box 593, Wellington 6140, New Zealand

www.kiwirail.co.nz

-----Original Message-----
From: T.J. Pohl <[FOI #32137 email]>
Sent: Wednesday, 27 August 2025 8:12 pm
To: KiwiRail <[email address]>
Subject: Official Information request - Wellington Ferry Terminal Infrastructure and Linkspan

CAUTION EXTERNAL EMAIL: Do not click links or open attachments unless you know the content is safe.

Dear KiwiRail,

Under the Official Information Act 1982, I request the following information relating to the "rail max reuse" option chosen for the Cook Strait ferry replacement project, with particular focus on Wellington infrastructure:

Any diagrams, design drawings, or engineering schematics that show how the "rail max reuse" option will be implemented at Wellington, including the proposed new linkspan, wharf extension, and integration with existing yards and terminal areas.

Any descriptions, presentations, or planning documents that outline how existing Wellington facilities will be reused or modified under the rail-max reuse approach.

Briefing notes, reports, or summaries provided to Ministers or senior officials since 1 January 2024 that specifically discuss Wellington infrastructure works under the rail max reuse option.

Yours faithfully,

T.J. Pohl

-------------------------------------------------------------------

This is an Official Information request made via the FYI website.

Please use this email address for all replies to this request:
[FOI #32137 email]

Is [KiwiRail request email] the wrong address for Official Information requests to KiwiRail? If so, please contact us using this form:
https://fyi.org.nz/change_request/new?bo...

Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://fyi.org.nz/help/officers

If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.

-------------------------------------------------------------------

hide quoted sections

Link to this

From: Info

Good afternoon, TJ,

We acknowledge receipt of the partial transfer of your request for information after 5 March 2025 under the Official Information Act 1982. We will aim to respond to this request quickly as practically possible and no later than 20 working days from 4 September 2025.

Additionally, we may decide to proactively release our response to your request for information with your personal details removed on our FHL website. We will notify you of this and our timelines for doing so at the time we officially respond to your request.

Kind regards

Nicola

+64 4 886 3440

[email address]

http://www.ferryholdings.co.nz/

PO Box 650, Wellington 6140, New Zealand

Level 8, 117 Lambton Quay, Wellington 6011, New Zealand

CONFIDENTIAL: This email, and any files transmitted with it, are confidential and intended solely for the use of the individual or entity to whom they are addressed. Please notify the sender immediately by e-mail if you have received this e-mail by mistake and delete this e-mail from your system.

-----Original Message-----
From: Dave Allard <[email address]>
Sent: Wednesday, 3 September 2025 5:19 pm
To: [FOI #32137 email]
Subject: Partial Transfer - OIA - Wellington Ferry Terminal Infrastructure and Linkspan

Good afternoon TJ

This email is to advise we are transferring part of your request to Ferry Holdings Ltd.
Any information post 5 March 2025 on the reuse options will be held by Ferry Holdings and not KiwiRail as it has taken over the ferry replacement project.

Ferry holdings will be in touch directly re your request.

Kind regards

Dave

Dave Allard | Senior Government Relations Advisor
DDI: 027 201 8182
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO Box 593, Wellington 6140, New Zealand

http://www.kiwirail.co.nz/

-----Original Message-----
From: T.J. Pohl <[FOI #32137 email]>
Sent: Wednesday, 27 August 2025 8:12 pm
To: KiwiRail <[email address]>
Subject: Official Information request - Wellington Ferry Terminal Infrastructure and Linkspan

CAUTION EXTERNAL EMAIL: Do not click links or open attachments unless you know the content is safe.

Dear KiwiRail,

Under the Official Information Act 1982, I request the following information relating to the "rail max reuse" option chosen for the Cook Strait ferry replacement project, with particular focus on Wellington infrastructure:

Any diagrams, design drawings, or engineering schematics that show how the "rail max reuse" option will be implemented at Wellington, including the proposed new linkspan, wharf extension, and integration with existing yards and terminal areas.

Any descriptions, presentations, or planning documents that outline how existing Wellington facilities will be reused or modified under the rail-max reuse approach.

Briefing notes, reports, or summaries provided to Ministers or senior officials since 1 January 2024 that specifically discuss Wellington infrastructure works under the rail max reuse option.

Yours faithfully,

T.J. Pohl

-------------------------------------------------------------------

This is an Official Information request made via the FYI website.

Please use this email address for all replies to this request:
[FOI #32137 email]

Is [KiwiRail request email] the wrong address for Official Information requests to KiwiRail? If so, please contact us using this form:
https://fyi.org.nz/change_request/new?bo...

Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://fyi.org.nz/help/officers

If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.

-------------------------------------------------------------------

hide quoted sections

Link to this

We don't know whether the most recent response to this request contains information or not – if you are T.J. Pohl please sign in and let everyone know.

Things to do with this request

Anyone:
KiwiRail only: