Progress on homes enabled under the Land for Housing programme
Jack Jones made this Official Information request to Ministry of Housing and Urban Development
The request was successful.
From: Jack Jones
Dear Ministry of Housing and Urban Development,
Under the Official Information Act 1982 I request the following information:
As at 31 December 2023:
1. How much of the $722m of recyclable funding allocated to the Land for Housing programme since its conception and to March 2022, as referred to in CBC-22-MIN-0015, has been spent?
2. How many of the estimated 9,491 homes to be delivered through the allocation of funds referred to in 1. above, have been completed and received CCC and title?
3. How many of the estimated 9,491 homes to be delivered through the allocation of funds referred to in 1. above, have received building consent and are in construction?
4. How many of the estimated 9,491 homes to be delivered through the allocation of funds referred to in 1. above, are yet to receive building consent?
5. When does the Ministry expect to recycle the funding referred to in 1. above, back to the Crown?
6. Please supply a table with the following information:
a. Names of the the 34 sites/developments acquired by the Land for Housing Programme, the region they are in and the date of each contract (as referred to in CBC-22-MIN-0015)
b. And for each site listed in a. above, the number of homes contracted to be built, the number of homes completed, the number of homes under construction, the number of homes yet to receive building consent and the forecast completion dates of both the unconsented and under construction homes.
7. How many of the 22 sites referred to as in the 2022 pipeline (as outlined in CBC-22-MIN-0015) are under construction?
8. Of the estimated 4,000 homes referred to in the 2022 pipeline (as outlined in CBC-22-MIN-0015), are complete, how many are under construction and how many are awaiting consent.
9. How much of the additional $311.132 million allocated to the Land for Housing programme as agreed in CBC-22-MIN-0015 has been spent and how many homes will that spend enable?
10. When are the homes enabled by the spend referred to in the answer to 9. above forecast to be completed.
I await your response within 20 working days of the receipt of this request. If any part of my request is unclear, or if the information is held by another department or agency, I would appreciate your assistance in directing this request to the appropriate party.
Yours faithfully,
Jack Jones
From: OIA Requests
Ministry of Housing and Urban Development
Tçnâ koe Jack Jones
Thank you for your email received 30 January 2024 to Te Tûâpapa Kura
Kâinga – Ministry of Housing and Urban Development requesting, under the
Official Information Act 1982 (the Act), the following information:
1. How much of the $722m of recyclable funding allocated to the Land for
Housing programme since its conception and to March 2022, as referred to
in CBC-22-MIN-0015, has been spent?
2. How many of the estimated 9,491 homes to be delivered through the
allocation of funds referred to in 1. above, have been completed and
received CCC and title?
3. How many of the estimated 9,491 homes to be delivered through the
allocation of funds referred to in 1. above, have received building
consent and are in construction?
4. How many of the estimated 9,491 homes to be delivered through the
allocation of funds referred to in 1. above, are yet to receive building
consent?
5. When does the Ministry expect to recycle the funding referred to in 1.
above, back to the Crown?
6. Please supply a table with the following information:
a. Names of the the 34 sites/developments acquired by the Land for Housing
Programme, the region they are in and the date of each contract (as
referred to in CBC-22-MIN-0015)
b. And for each site listed in a. above, the number of homes contracted to
be built, the number of homes completed, the number of homes under
construction, the number of homes yet to receive building consent and the
forecast completion dates of both the unconsented and under construction
homes.
7. How many of the 22 sites referred to as in the 2022 pipeline (as
outlined in CBC-22-MIN-0015) are under construction?
8. Of the estimated 4,000 homes referred to in the 2022 pipeline (as
outlined in CBC-22-MIN-0015), are complete, how many are under
construction and how many are awaiting consent.
9. How much of the additional $311.132 million allocated to the Land for
Housing programme as agreed in CBC-22-MIN-0015 has been spent and how many
homes will that spend enable?
10. When are the homes enabled by the spend referred to in the answer to
9. above forecast to be completed.
Your request has been forwarded to the appropriate officials to respond.
You may expect a decision regarding your request to be sent to you as soon
as possible, but no later than 20 working days from the receipt of your
request. If we're unable to respond to your request by then, we'll notify
you of an extension of that timeframe.
Ngâ mihi
Government Services
Government Services
Organisational Performance
[1][email address]
[2]www.hud.govt.nz
[3]Graphical user interface, website<br><br> Ministry logo
------------------- Original Message -------------------
From: [FOI #25567 email];
Received: Tue Jan 30 2024 16:07:00 GMT+1300 (New Zealand Daylight Time)
To: 2 - [HUD request email] <[email address]>;
Subject: Official Information request - Progress on homes enabled under
the Land for Housing programme
Dear Ministry of Housing and Urban Development,
Under the Official Information Act 1982 I request the following
information:
As at 31 December 2023:
1. How much of the $722m of recyclable funding allocated to the Land for
Housing programme since its conception and to March 2022, as referred to
in CBC-22-MIN-0015, has been spent?
2. How many of the estimated 9,491 homes to be delivered through the
allocation of funds referred to in 1. above, have been completed and
received CCC and title?
3. How many of the estimated 9,491 homes to be delivered through the
allocation of funds referred to in 1. above, have received building
consent and are in construction?
4. How many of the estimated 9,491 homes to be delivered through the
allocation of funds referred to in 1. above, are yet to receive building
consent?
5. When does the Ministry expect to recycle the funding referred to in 1.
above, back to the Crown?
6. Please supply a table with the following information:
a. Names of the the 34 sites/developments acquired by the Land for
Housing Programme, the region they are in and the date of each contract
(as referred to in CBC-22-MIN-0015)
b. And for each site listed in a. above, the number of homes
contracted to be built, the number of homes completed, the number of homes
under construction, the number of homes yet to receive building consent
and the forecast completion dates of both the unconsented and under
construction homes.
7. How many of the 22 sites referred to as in the 2022 pipeline (as
outlined in CBC-22-MIN-0015) are under construction?
8. Of the estimated 4,000 homes referred to in the 2022 pipeline (as
outlined in CBC-22-MIN-0015), are complete, how many are under
construction and how many are awaiting consent.
9. How much of the additional $311.132 million allocated to the Land for
Housing programme as agreed in CBC-22-MIN-0015 has been spent and how many
homes will that spend enable?
10. When are the homes enabled by the spend referred to in the answer to
9. above forecast to be completed.
I await your response within 20 working days of the receipt of this
request. If any part of my request is unclear, or if the information is
held by another department or agency, I would appreciate your assistance
in directing this request to the appropriate party.
Yours faithfully,
Jack Jones
-------------------------------------------------------------------
This is an Official Information request made via the FYI website.
Please use this email address for all replies to this request:
[FOI #25567 email]
Is [HUD request email] the wrong address for Official Information requests to
Ministry of Housing and Urban Development? If so, please contact us using
this form:
[4]https://aus01.safelinks.protection.outlo...
Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
[5]https://aus01.safelinks.protection.outlo...
If you find this service useful as an Official Information officer, please
ask your web manager to link to us from your organisation's OIA or LGOIMA
page.
-------------------------------------------------------------------
Disclaimer
This email is confidential and solely for the use of the intended
recipient. If you have received this email in error, then any use is
strictly prohibited. Please notify us immediately and delete all copies of
this email and any attachments. Any opinions expressed in this message are
not necessarily those of the Ministry of Housing and Urban Development.
References
Visible links
1. mailto:[email address]
2. http://www.hud.govt.nz/
3. https://www.hud.govt.nz/
4. https://fyi.org.nz/change_request/new?bo...
5. https://fyi.org.nz/help/officers
hide quoted sections
From: OIA Requests
Ministry of Housing and Urban Development
Please find attached the response to your OIA to Te Tûâpapa Kura Kâinga –
Ministry of Housing and Urban Development.
Ngâ mihi
Government Services
Government Services
Organisational Performance
[1][HUD request email]
[2]www.hud.govt.nz
[3]Graphical user interface, website<br><br> Ministry logo
;
Received: Tue Jan 30 2024 16:07:00 GMT+1300 (New Zealand Daylight Time)
To: 2 - [HUD request email] <[email address]>;
Subject: Official Information request - Progress on homes enabled under
the Land for Housing programme
Dear Ministry of Housing and Urban Development,
Under the Official Information Act 1982 I request the following
information:
As at 31 December 2023:
1. How much of the $722m of recyclable funding allocated to the Land for
Housing programme since its conception and to March 2022, as referred to
in CBC-22-MIN-0015, has been spent?
2. How many of the estimated 9,491 homes to be delivered through the
allocation of funds referred to in 1. above, have been completed and
received CCC and title?
3. How many of the estimated 9,491 homes to be delivered through the
allocation of funds referred to in 1. above, have received building
consent and are in construction?
4. How many of the estimated 9,491 homes to be delivered through the
allocation of funds referred to in 1. above, are yet to receive building
consent?
5. When does the Ministry expect to recycle the funding referred to in 1.
above, back to the Crown?
6. Please supply a table with the following information:
a. Names of the the 34 sites/developments acquired by the Land for
Housing Programme, the region they are in and the date of each contract
(as referred to in CBC-22-MIN-0015)
b. And for each site listed in a. above, the number of homes
contracted to be built, the number of homes completed, the number of homes
under construction, the number of homes yet to receive building consent
and the forecast completion dates of both the unconsented and under
construction homes.
7. How many of the 22 sites referred to as in the 2022 pipeline (as
outlined in CBC-22-MIN-0015) are under construction?
8. Of the estimated 4,000 homes referred to in the 2022 pipeline (as
outlined in CBC-22-MIN-0015), are complete, how many are under
construction and how many are awaiting consent.
9. How much of the additional $311.132 million allocated to the Land for
Housing programme as agreed in CBC-22-MIN-0015 has been spent and how many
homes will that spend enable?
10. When are the homes enabled by the spend referred to in the answer to
9. above forecast to be completed.
I await your response within 20 working days of the receipt of this
request. If any part of my request is unclear, or if the information is
held by another department or agency, I would appreciate your assistance
in directing this request to the appropriate party.
Yours faithfully,
Jack Jones
-------------------------------------------------------------------
This is an Official Information request made via the FYI website.
Please use this email address for all replies to this request:
[FOI #25567 email]
Is [HUD request email] the wrong address for Official Information requests to
Ministry of Housing and Urban Development? If so, please contact us using
this form:
[4]https://aus01.safelinks.protection.outlo...
Disclaimer: This message and any reply that you make will be published on
the internet. Our privacy and copyright policies:
[5]https://aus01.safelinks.protection.outlo...
If you find this service useful as an Official Information officer, please
ask your web manager to link to us from your organisation's OIA or LGOIMA
page.
-------------------------------------------------------------------
Disclaimer
This email is confidential and solely for the use of the intended
recipient. If you have received this email in error, then any use is
strictly prohibited. Please notify us immediately and delete all copies of
this email and any attachments. Any opinions expressed in this message are
not necessarily those of the Ministry of Housing and Urban Development.
References
Visible links
1. mailto:[email address]
2. http://www.hud.govt.nz/
3. https://www.hud.govt.nz/
4. https://fyi.org.nz/change_request/new?bo...
5. https://fyi.org.nz/help/officers
hide quoted sections
Things to do with this request
- Add an annotation (to help the requester or others)
- Download a zip file of all correspondence