Main North Line corridor between Christchurch and Rangiora
Patrick Dunford made this Official Information request to KiwiRail
The request was successful.
From: Patrick Dunford
Dear KiwiRail,
What is the width of the rail corridor between Addington and Rangiora on the Main North Line? Is it sufficient for double tracking throughout this section and the placement of passenger stations on a double track line?
(Irrespective of any leases of land in the corridor to other parties)
How much freight traffic is currently carried each year through this section and how many train services daily are needed to transport this freight?
What are the upgrades that are said to be needed in this section for commuter train proposals (presuming a report was done for the Greater Christchurch Partnership)?
Yours faithfully,
Patrick Dunford
From: Dave Allard
KiwiRail
Good afternoon Patrick
I'd like to acknowledge receipt of your official information request for information on the infrastructure around the Main North Line corridor between Christchurch and Rangiora
We received your request on 5 January 2024, and will endeavour to respond to your request as soon as possible and in any event no later than 13 February 2024, i.e. the 20 working days after the day your request was received.
If we are unable to respond to your request by then, we will notify you of an extension of that timeframe.
I'll be looking after your request, so any questions please get in touch with me at this email address.
Cheers
Dave
-----Original Message-----
From: Patrick Dunford <[FOI #25334 email]>
Sent: Friday, 5 January 2024 8:02 am
To: KiwiRail <[email address]>
Subject: Official Information request - Main North Line corridor between Christchurch and Rangiora
CAUTION EXTERNAL EMAIL: Do not click links or open attachments unless you know the content is safe.
Dear KiwiRail,
What is the width of the rail corridor between Addington and Rangiora on the Main North Line? Is it sufficient for double tracking throughout this section and the placement of passenger stations on a double track line?
(Irrespective of any leases of land in the corridor to other parties)
How much freight traffic is currently carried each year through this section and how many train services daily are needed to transport this freight?
What are the upgrades that are said to be needed in this section for commuter train proposals (presuming a report was done for the Greater Christchurch Partnership)?
Yours faithfully,
Patrick Dunford
-------------------------------------------------------------------
This is an Official Information request made via the FYI website.
Please use this email address for all replies to this request:
[FOI #25334 email]
Is [KiwiRail request email] the wrong address for Official Information requests to KiwiRail? If so, please contact us using this form:
https://fyi.org.nz/change_request/new?bo...
Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://fyi.org.nz/help/officers
If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.
-------------------------------------------------------------------
hide quoted sections
From: Dave Allard
KiwiRail
Good afternoon
Please find the attached.
Kind regards
Dave
Dave Allard | Senior Government Relations Advisor
DDI: 027 201 8182
Level 4, Wellington Railway Station, Bunny Street, Wellington 6011 | PO Box 593, Wellington 6140, New Zealand
www.kiwirail.co.nz
-----Original Message-----
From: Patrick Dunford <[FOI #25334 email]>
Sent: Friday, 5 January 2024 8:02 am
To: KiwiRail <[email address]>
Subject: Official Information request - Main North Line corridor between Christchurch and Rangiora
CAUTION EXTERNAL EMAIL: Do not click links or open attachments unless you know the content is safe.
Dear KiwiRail,
What is the width of the rail corridor between Addington and Rangiora on the Main North Line? Is it sufficient for double tracking throughout this section and the placement of passenger stations on a double track line?
(Irrespective of any leases of land in the corridor to other parties)
How much freight traffic is currently carried each year through this section and how many train services daily are needed to transport this freight?
What are the upgrades that are said to be needed in this section for commuter train proposals (presuming a report was done for the Greater Christchurch Partnership)?
Yours faithfully,
Patrick Dunford
-------------------------------------------------------------------
This is an Official Information request made via the FYI website.
Please use this email address for all replies to this request:
[FOI #25334 email]
Is [KiwiRail request email] the wrong address for Official Information requests to KiwiRail? If so, please contact us using this form:
https://fyi.org.nz/change_request/new?bo...
Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://fyi.org.nz/help/officers
If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.
-------------------------------------------------------------------
hide quoted sections
Things to do with this request
- Add an annotation (to help the requester or others)
- Download a zip file of all correspondence