Cost Estimate Southdown - Avondale link
Tim Frank made this Official Information request to KiwiRail
The request was successful.
      From: Tim Frank
      
    
    Dear KiwiRail,
Can you provide the latest cost estimate for the completion of the Southdown - Avondale Link. Can you please clarify whether that estimate refers to a single-track or double-track line and whether it includes electrification or not.
Yours faithfully,
Tim Frank
        From: OCU
        KiwiRail
      
    
    Good afternoon Tim
 
We acknowledge receipt of the below Official Information Act 1982 request.
 
Under the Act, KiwiRail has up to 20 working days from the date of
 receiving your request to respond.  Therefore, you can expect a response
 on or before Thursday 23 March 2017.
 
We will be in touch with you if it is necessary to clarify any aspect of
 your request.
 
Kind regards
Official Correspondence Unit
KiwiRail
 
 
show quoted sections
        From: OCU
        KiwiRail
      
    
    Dear Mr Frank
 
We are writing in response to your request dated 17 January 2017, in which
 you ask for the following information:
“Can you provide the latest cost estimate for the completion of the
 Southdown - Avondale Link?
 
Can you please clarify whether that estimate refers to a single-track or
 double-track line and whether it includes electrification or not? “
 
Your request has been considered under the Official Information Act 1982
 (the Act).
KiwiRail’s provisional cost estimate for the completion of the Southdown -
 Avondale Link is $1 billion. This amount assumes a double track railway
 but does not include the cost of electrification.
 
If implemented the Southdown - Avondale Link will enable north to south
 freight flows to NorthPort at Marsden Point.  However, the link would
 require a major upgrade programme to be undertaken on the North Auckland
 Line, which is in a poor condition, in addition to the construction of a
 rail connection through the Auckland isthmus.
 
No date for the construction of the Avondale -Southdown Link has been set.
 
Under s28(3) of the Act you have the right to complain to an Ombudsman
 about this decision.  Please refer to [1]www.ombudsman.parliament.nz for
 more information.
Regards,
Official Correspondence Unit
KiwiRail
 
From: OCU
 Sent: Thursday, 23 February 2017 1:10 p.m.
 To: '[FOI #5434 email]'
 Subject: RE: Official Information request - Cost Estimate Southdown -
 Avondale link
 
Good afternoon Tim
 
We acknowledge receipt of the below Official Information Act 1982 request.
 
Under the Act, KiwiRail has up to 20 working days from the date of
 receiving your request to respond.  Therefore, you can expect a response
 on or before Thursday 23 March 2017.
 
We will be in touch with you if it is necessary to clarify any aspect of
 your request.
 
Kind regards
Official Correspondence Unit
KiwiRail
 
 
show quoted sections
Things to do with this request
- Add an annotation (to help the requester or others)
 - Download a zip file of all correspondence (note: this contains the same information already available above).
 