Lake Onslow Power Scheme

Andrew made this Official Information request to Ministry of Business, Innovation & Employment

The request was successful.

From: Andrew

Dear Ministry of Business, Innovation & Employment,

I request under the Official Information Act what process has been made on the Lake Onslow Power Scheme.
-Specifically what are the next steps, when and who will make a final decision on whether the project will proceed and when construction will begin.
-Additionally will a decision be made before the next election and next budget.
-Will all of the funds be appropriated and set aside along with construction contracts entered and farm/land owners reimbursed before the next election.
-Has the Ministry taken into account NZ's wider climate emissions targets in its consultation. Has the Ministry consultated with the Ministry for the Environment and the Climate Change Commission.
-Has funding for the project also been sought from the Reserve Bank of New Zealand's green bond facility. Or from the proceeds from the emissions trading scheme.

Yours faithfully,

Andrew

Link to this

From: Ministerial Services
Ministry of Business, Innovation & Employment


Attachment image001.jpg
33K Download


Ref: 2223-1034

 

Dear Andrew

 

On behalf of the Ministry of Business, Innovation and Employment I
acknowledge your email of 16^th November 2022 requesting under the
Official Information Act 1982 (the Act), the following:

 

‘I request under the Official Information Act what process has been made
on the Lake Onslow Power Scheme.

-Specifically what are the next steps, when and who will make a final
decision on whether the project will proceed and when construction will
begin.

-Additionally will a decision be made before the next election and next
budget.

-Will all of the funds be appropriated and set aside along with
construction contracts entered and farm/land owners reimbursed before the
next election.

-Has the Ministry taken into account NZ's wider climate emissions targets
in its consultation. Has the Ministry consultated with the Ministry for
the Environment and the Climate Change Commission.

-Has funding for the project also been sought from the Reserve Bank of New
Zealand's green bond facility. Or from the proceeds from the emissions
trading scheme.’

 

Your request is being processed in accordance with the Act and a response
will be sent to you in due course.

 

If you have any enquiries regarding your request, or its urgency, feel
free to contact us via email at [1][MBIE request email].

 

Nâku noa, nâ

 

Ministerial Services

Corporate, Governance and Information  |   Ngâ Pou o te Taumaru

Ministry of Business, Innovation & Employment

15 Stout Street, Wellington 6011 |  P O Box 1473 Wellington 6140

 

 

References

Visible links
1. mailto:[MBIE request email]
mailto:[MBIE request email]

Link to this

From: *OIA
Ministry of Business, Innovation & Employment


Attachment DOIA 2223 1034 Andrew Response.pdf
374K Download View as HTML


Kia ora Andrew

Please find attached our response to your OIA request of 16 November 2022.

Ngā mihi

Ministerial Services
Ministry of Business, Innovation and Employment
[MBIE request email]

-----Original Message-----
From: Andrew <[FOI #21131 email]>
Sent: Wednesday, 16 November 2022 12:41 am
To: *OIA <[email address]>
Subject: Official Information request - Lake Onslow Power Scheme

Dear Ministry of Business, Innovation & Employment,

I request under the Official Information Act what process has been made on the Lake Onslow Power Scheme.
-Specifically what are the next steps, when and who will make a final decision on whether the project will proceed and when construction will begin.
-Additionally will a decision be made before the next election and next budget.
-Will all of the funds be appropriated and set aside along with construction contracts entered and farm/land owners reimbursed before the next election.
-Has the Ministry taken into account NZ's wider climate emissions targets in its consultation. Has the Ministry consultated with the Ministry for the Environment and the Climate Change Commission.
-Has funding for the project also been sought from the Reserve Bank of New Zealand's green bond facility. Or from the proceeds from the emissions trading scheme.

Yours faithfully,

Andrew

-------------------------------------------------------------------

This is an Official Information request made via the FYI website.

Please use this email address for all replies to this request:
[FOI #21131 email]

Is [MBIE request email] the wrong address for Official Information requests to Ministry of Business, Innovation &amp; Employment? If so, please contact us using this form:
https://aus01.safelinks.protection.outlo...

Disclaimer: This message and any reply that you make will be published on the internet. Our privacy and copyright policies:
https://aus01.safelinks.protection.outlo...

If you find this service useful as an Official Information officer, please ask your web manager to link to us from your organisation's OIA or LGOIMA page.

-------------------------------------------------------------------