Dear Christchurch City Council,
On 15 Nov 2021, CCC published an article stating "The next revision of our water safety plan will be ready to submit to Taumata Arowai by the end of this year" [2021].
1) Please supply the drinking water safety plan.
Later in the same article it also states "water suppliers can apply for an exemption from chlorination from 1 March 2022 to the new national water regulator, Taumata Arowai".
Given close to two months have passed from this date:
2) Has a "Residual disinfection exemption" been applied for?
3) If not, what caused the delay? Further, what is the current expected timeframe for applying?
Yours faithfully,
Cody C
From: Cody C
Dear Christchurch City Council,
Please acknowledge this request.
Yours faithfully,
Cody C
From: Cody C
Dear Christchurch City Council,
Please confirm receipt.
Yours faithfully,
Cody C
From: Official Information
Christchurch City Council
Dear Cody,
I refer to your request for information below. Responses to your questions
are attached:
Please supply the drinking water safety plan.
We have decided to withhold this information under the following sections
of the LGOIMA -
6(b) - to endanger the safety of any person
7(2)(c) protect information which is subject to an obligation of
confidence or which any person has been or could be compelled to provide
under the authority of any enactment, where the making available of the
information—
(ii) would be likely otherwise to damage the public interest
While we note the district’s water supply has a high public interest, our
water safety plan contains considerable technical detail about the water
supply network. We are currently working on a summary version that would
be available for public release.
Has a "Residual disinfection exemption" been applied for?
No, however we are working with Taumata Arowai to understand the format of
an application. At this stage we will be looking at water supply zone by
zone application as we make the necessary improvements to our
infrastructure, particularly our suction tanks and reservoirs. We are also
considering an exemption application on a zone by zone basis rather than
for the city supply as a whole. Considerable information needs to be
prepared to accompany the application. TA website outlines this:
[1]https://www.taumataarowai.govt.nz/for-wa...
If not, what caused the delay? Further, what is the current expected
timeframe for applying?
Staff have been working with Taumata Arowai on the application process and
format and to date have made good progress. We don’t have an exact date
however would expect the first application to be made within the next few
months.
In the Council's view the reasons for withholding these details are not
outweighed by public interest considerations in section 7(1) favouring
their release.
You have the right to request the Ombudsman to review this decision.
Complaints can be sent by email to [2][email address], by fax
to (04) 471 2254, or by post to The Ombudsman, PO Box 10152, Wellington
6143.
Kind regards,
Sean
Sean Rainey
Manager Official Information and Privacy Officer
Official Information Team
**********************************************************************
This electronic email and any files transmitted with it are intended
solely for the use of the individual or entity to whom they are addressed.
The views expressed in this message are those of the individual sender
and may not necessarily reflect the views of the Christchurch City
Council.
If you are not the correct recipient of this email please advise the
sender and delete.
Christchurch City Council
http://www.ccc.govt.nz
**********************************************************************
References
Visible links
1. https://aus01.safelinks.protection.outlo...
2. mailto:[email address]
Cody C left an annotation ()
Received this response on escalation to CEO and Mayor:
Unfortunately our WSP contains a great deal of technical data and could pose a risk to our network. We acknowledge the public interest and that is the primary reason a high level version will be developed for public consumption. At this stage there is no timeline as the Three Waters Team are extremely busy dealing with other major events in this area. Once a timeline is established I will let you know.
Escalated to Ombudsman
Things to do with this request
- Add an annotation (to help the requester or others)
- Download a zip file of all correspondence
Cody C left an annotation ()
Escalated to CEO. Complaint was not acknowledged within 2 business days as required by CCC policy. Referred again and advised “was missed”.