Test Results Submission Sheet
File No (CWBS): GW\1A-05-06-15\D0007\R01
RM Ref. No.: RM\1A-05-06-15\D0005\R02
Submission Title: Type Test Report for Mainline Test of Propulsion System in AW3 Load Condition
Responsible Manager: Barry Fryer - Engineering Manager
Part 1
Actual Date
Outcome
Responsible Manager
Project Director or
Out
Description
R/NR/SC
Signature
Delegates Signature
The document “Type Test Report for Mainline Test of Propulsion System in AW3 Load
18.03.11
Condition” is Not Rejected Subjected to Changes based on the following:
SC
Barry Fryer
Rigby Wason
•
The timetable performance for the Johnsonville line is still to proven once the
line speed permits.
Legend
R
Rejected
NR
Not Rejected
SC
Not Rejected Subject to Changes
CWBS
Contract Work Breakdown Structure
WGN_DOCS-#897364-v1
Test Results Submission Sheet
Item
GW Response details to be filled out by RM
Section/Page/Drg:
GW Comments:
By:
No.:
Timetable testing carried out on the Johnsonville Line to date fails to
We have carried out the time table test for Johnsonville line
1
GW
demonstrate compliance with Schedule 4 Clause 7.1.
again but test result did not meet the criteria because of
the restriction speed difference between simulation
Simulation results indicate that the train shall be able to meet the
condition and real condition.
contractual requirements, despite the lower maximum speed provided
So RM proposes to adjust the time table for Johnsonville
to Rotem during design.
line.
Please refer to appndix7 in test report package.
RM to conduct further testing to demonstrate (or better understand)
timetable performance on the Johnsonville Line. Agreed that this is to
be carried out in AW0 condition at the first suitable opportunity when
the line speed permits.
GW note informal discussions regarding modelled thermal capacity
RM will propose the additional test for thermal capacity test
2
GW
indicate almost no redundancy for recovery of trains in the event of
in rescue condition.
propulsion system failures.
So RM will submit the test procedure for it and we will
carry out the main line test and review the test result.
Further discussion will be undertaken in the Rescue Test Report.
Part 3
Outcome
Rejected
Not Rejected
X Not Rejected Subject to Changes
WGN_DOCS-#897364-v1