This is an HTML version of an attachment to the Official Information request 'Development Plans for Bayswater Marina'.

Bayswater PT Ferry facility
Nicholas Seymour PT Improvements Project Director – February 2016



2
Introductions
Nick Seymour – Project Director AT
Marilyn Nicholls - AT Elected Member Liaison
Elaine Irvine –Panuku Development Auckland
Chris Hume – TGSRC 





3
Bayswater Marina 
Existing facilities and overview
Existing location of the 
TGSRC Blue shed
Existing concrete Wharf 
owned by AC
Proposed location for new 
Existing ferry facility
ferry facility




4
Budget overview

Project not currently funded in the current LTP

AT Metro Operations have requested re-prioritisation of the Bayswater 
Ferry project to commence construction late 2016 – circa $4M TBC.

AT Board have delegation to refine projects with LTP, subject to no 
budget increase in overall LTP

$120K approved by AT management in Dec 2015 to progress ferry 
design to completion by June 2016.

Budget for landside scope construction not likely before early 2018

Project to be staged delivery as funding becomes available.




5
Overall PT Objective at Bayswater
Deliver a new public transport interchange between ferries and buses 
including

Upgraded concrete wharf 

New pontoon and gangway, including associated piling, fendering
systems 

Lighting, Power, CCTV, Signage, Passenger Information Displays, 
Integrated ticketing enabled.

Covered waiting area for PT Users

Operational Staff accommodation

Reconfigured and formalised park n ride, drop off, Cycle facilities. 

Reconfigured bus stops/shelters. 

Future proofed for growth of PT Users




6
PT Facility overall Delivery Strategy
Subject to funding approval;
Stage 1 scope;

Design and construction of the Ferry facility and connection to landside including
concrete repairs to the existing AC owned wharf.

Detailed design only of the landside scope of works for Bus, Park n ride, Staff
facilities, Enhanced waiting areas, Cycle facilities.  
Programme for stage 1;

Complete detailed design for ferry facility – July 2016

Complete detailed design for landside scope – Oct 2016

Construction of the new ferry facility by mid 2017
Stage 2 – Construction of all landside works.
Programme likely to be construct between Dec 2017 and August 2018




7
Progress to date

AT Metro  - in progress with tendering the Ferry services contract (PTOM)

Confirmed option 2 for the future landside parking/bus layout.

Ongoing engagement with TGSRC, AC, Panuku Dev Auckland 

Development of memorandum of understanding towards achieving 
AT/PDA/TGSRC objectives.

Discussion around proposed Licence to Occupy (TGSRC) in progress.

Development of delivery programmes AT/TGSRC

AT Project timing vs funding for PT scope re; TGSRC future 
location/tenure

Alternative locations considered for TGSRC Community rowing facility  - 2 
Sir Peter Blake Parade preferred location.

AT/PDA have no objection to the preferred alternative.




8
Programme overview/key dates

Concept design for seaward pontoon/gangway completed 2014.

Concept design for Landside parking layout completed 2014

Agreed MOU AT/PDA/TGSRC by early Feb2016

Licence to Occupy (TGSRC) agreed and in place – target completion   
April 2016

Developed design Feb to July 2016

Detailed design July to Sep 2016

Stage 1 Construction commence Oct 2016 to Sep 2017

Consenting, land designations commence May 2016

resource, building, coastal marine area resources 

Ongoing discussions with BMH Ltd re ‘spitestrip’

Overall project completion all stages – 2nd half of 2018





9
Proposed park and ride layout, post removal of blue sheds 2017/18
Proposed parking layout 2nd half of 2018





10
Land overview plan
Proposed location for the TGSRC Community Rowing Facility – 2 Sir PB Drive
Proposed location for the 
TGSRC Community Facility
Future location for Park 
and Ride and bus 
accessibility/integration




11
Questions