This is an HTML version of an attachment to the Official Information request 'Removal of prohibition against switching protective earth neutral (PEN) conductors from Wiring Rules'.



 
20 March 2026  
File Ref: 251174 
 
Aidan Thornton 
Via FYI 
 
Dear Aidan 
 
Thank you for your Official Information Act (Act) request received on 6 November 2025. 
You requested: 
 
•  Background 
The Electricity (Safety) Amendment Regulations 2025 (ESAR25) were published 13 
October 2025 and the amendments come into effect 13 November 2025. 
Note: being an imminent public safety issue an accelerated processing time is 
requested. 
 
Issue: PEN Conductor Protections Removed 

ESAR25 r12 amends Schedule 2 of the Electricity (Safety) Regulations 2010 (ESR). 
 
ESR Schedule 2 is amended to cite AS/NZS 3000:2018 (…Wiring Rules) subject 

multiple modifications. The issue raised here is the deletion of clauses 2.3.2.1.2 (b) & 
(c) from the Wiring Rules. 
 
AS/NZS 3000:2018 clauses 2.3.2.1.2 (b) & (c) provide the only prohibitions 

preventing the extremely unsafe action that is the installation of switches, fuses or 
circuit breakers within an installation’s Protective Earth Neutral (PEN) conductor. 
In the Multiple-Earthed Neutral system used by New Zealand, the neutral conductor 
of consumer mains is a PEN conductor. 
Important note: the presence of fuses or independent switches/breakers in a PEN 
conductor can render the installation lethal under normal operating conditions (even 
with no faults present). 
 
•  Question 1: 
Please provide details of the management of change (or equivalent) procedure 
associated with this regulatory change (allowing a fuse, independent circuit 
breaker or switch within the PEN conductor), including requirements for: 
   • initiation of the process 
   • requirements analysis (ie justification for the proposed change) 
   • consultation with industry, the public, and other government entities 
   • due diligence 
   • review (internal, peer, and expert) 
   • detailed technical analysis 
   • risk/reward and benefit-to-cost-ratio analysis 
   • required signoffs or gating 
   • other necessary steps 
 
 
•  Question 2: 
Please provide all documentation associated with this regulatory change, 
including but not limited to the above items. 
 
 

PO Box 165, Wellington 6140 
 

 
 
 
 
Question 3: 
During due diligence prior to the release of ESAR25, what overseas jurisdictions were 
identified that allow the installation of fuses, switches, disconnects, and/or circuit 
breakers within Consumer Mains Neutral, Protective Earth Neutral, or Protective 
Earth conductors of equivalent or similar systems of supply? 
 
On 11 December 2025, we extended the time limit for deciding on your request to 6 
February 2025 and on 29 January we communicated that we had decided to grant your 
request in part.  Again, we apologise for the delay in communicating this decision. 
 
 
WorkSafe response to Question 1: 
 
In 2019, Government agreed to update references to standards cited in the Electricity 
(Safety) Regulations (ESR). These standards are principally safety standards for 
electrical equipment and installation practices. Primary drivers for this update were to 
maintain currency with the evolving international standards and joint Australian/New 
Zealand standards in line with our international commitments including trans-Tasman 
recognition and, where possible, to address emerging safety issues. Public consultation 
on updating those references took place in 2020.   
One issue on which consultation sought feedback was which edition or editions of 
AS/NZS 3000 should be cited in updated regulations. Feedback on this point favoured 
citation of the 2018 edition and removal of citation of the 2007 edition.  
Policy analysis on updating the references to standards took both the feedback from the 
public consultation and how to ensure the safety of emerging technologies and practices 
into consideration in order to provide detailed recommendations on the updated citation 
of standards. As part of this analysis, it is normal practice for advisors, including 
WorkSafe’s technical experts, to consider and advise on the way a standard is cited. This 
is to ensure each standard meets the purpose for which it is cited in regulations and to 
reflect any changes within a standard, the way the standard is used, or to accommodate 
changes in technology or practices.  
The recommendations came about during this process subsequent to the public 
consultation. They arose from consideration of feedback and how best to update the 
citation of AS/NZS 3000, and ongoing discussions amongst technical experts about 
better providing for electrical safety to address outstanding issues. Specifically, neither 
AS/NZS 3000:2007 nor AS/NZS 3000:2018 deal effectively or comprehensively with 
providing for electrical safety in circumstances where there are acknowledged 
weaknesses with the New Zealand MEN system, including those associated with:   
•  supply faults occurring during the charging and discharging of electric vehicles; and  
•  the resilience of the electricity supply of an installation in the face of a natural 
disaster.     
In the “EV” scenario, interruption of the protective earthing or the neutral (PEN) 
conductor of an electrical installation is a foreseeable failure mode for MEN systems. It 
has the potential to cause the metal bodywork of a connected EV to become enlivened. 
Removal of the restriction stated clause 2.3.2.1.2 (b) and (c) allows for the introduction 


 
 
 
 
of techniques which better provide for the safety of EV charging under foreseeable fault 
conditions.    
In a “resilience” scenario, where an installation has the ability to generate electricity 
independently from the grid, removal of this restriction enables solutions in which the 
installation can be configured to operate safely if supply from the grid is lost without 
putting the grid, including conductors of the grid, and other users, at risk from the grid 
being re-enlivened inadvertently. The need to better provide for resilience of electrical 
installations received added emphasis following cyclone Gabrielle in 2023, after which 
WorkSafe issued guidance on how an electrical installation could be reconfigured for 
independent operation on a temporary basis.  
Noting that there are more general provisions for safety, removing the application of the 
prescriptive clauses 2.3.2.1.2 (b) and (c) was proposed as an achievable preparatory 
step to better provide for safety in these scenarios. The recommendation anticipated 
that rules or guidance, setting out when and how ‘switching’ of these conductors would 
be permitted to better provide for safety in specific scenarios, will be promulgated.  
It has never been intended to permit ‘switching’ of these conductors without introducing 
substitute controls to provide for safety.    
In any case, removing the application of clauses 2.3.2.1.2 (b) and (c) did not remove all 
controls which restrict switching those conductors, nor did it require that switching be 
installed in any or all circumstances.  
In developing the recommendations, WorkSafe technical experts carefully considered the 
relevant scenarios and both the likelihood and consequence of the proposed changes, 
given the characteristics of New Zealand’s electricity supply system which relies on 
multiple earthing of the neutral conductor (MEN earthing). The scenario and risk analysis 
considered and compared realistic failure modes and their likelihood and consequences. 
This took the history of events which led to significant consequences into account.  
Given the recommendation was proposed as a preparatory step, with the intention that 
the restriction would be replaced by specific guidance relevant to each scenario, a formal 
documented risk analysis or cost-benefit analysis was not necessary for this specific 
change which merely removed a partial control. The anticipated guidance included 
identification of scenarios in which ‘switching’ of either the main earth or PEN conductor 
would be allowed and where it would not be allowed.  
Each item was also considered for consistency with the policy mandate for the project 
which was based around updating references to cited standards to be satisfied that it 
was:  
•  consistent with overall goal of improving safety, and specifically safety of EV 
charging and Government goals of improving EV charging infrastructure;  
•  not inconsistent with the policy mandate;  
•  necessary to address or prepare to address an identified risk that was not 
adequately addressed; and   
•  did not create additional risk.  
 


 
 
 
 
WorkSafe response to question 2: 
 
WorkSafe interprets this as relating to documents which make substantive reference to 
or directly discuss making the recommendation related to clause 2.3.2.1.2, which was 
accepted by Cabinet in October 2024.  
Given the nature of the recommended change, there is little detailed documentation of 
the recommendation and how it was formulated.  
This was appropriate given the recommendation was made as a preparatory step, with 
the intention that the restriction would be replaced by specific guidance relevant to each 
scenario, and it was not intended to permit ‘switching’ of these conductors without 
introducing substitute controls to provide for safety.    
In any case, documents related to drafting the amendments are subject to legal 
privilege. In any case, most of these documents do not make a substantive reference to 
clause 2.3.2.1.2 or why the recommendation was made.  
There are also documents in scope which are publicly available on the MBIE website 
which need not be released. 
There are also documents for release that are in scope for your request.  Please refer to 
the following table:  
 
Requested Information 
  
The following documents are publicly available: 
  electricity-safety-amendment-regulations-2025-and-gas-safety- Publicly available 
and-measurement-amendment-regulations-2025-
on MBIE website  
proactiverelease – dated 25 November 2025 
updating-energy-safety-standards-citations-in-regulations-
Publicly available 
minute-of-decision-proactiverelease – dated 26 March 2025 
on MBIE website 
 
The following documents are in scope of your request.  
Item 
Document Title 
Decision 
1.    Email dated 23 June 2023  -  RE_ Updates to citation of 
standards in ESR and GSMR 
Release in part 
Extract from attachment  -  Copy of Copy of Copy of  Release in part 
2.    Streamlined standards table for Cabinet paper CB 
Comments to update to Dec 2022 new 
Release in full 
3.    Email dated 27 February - Amendments to the regs 2024-
02-27 
4.    Extract from attachment - REgs review 
Release in part 
Release in part 
5.    Email dated 13 March 2024 -  Scotts, Chris and my 
comments combined - only harmonics to do 


 
 
 
 
Extract from attachment  -  Copy of Copy of Copy of  Release in part 
6.    Standards tables from Energy Safety as at 7 March with LA 
markup 
Release in part 
7.    Email dated 14 March 2024 - FW_ Hopefully the last lot of 
questions on the ESR schedules __ 
Release in part 
8.    Extract from attachment  -  Standards tables from Energy 
Safety as at 7 March with LA markup 
Further information about changes to standards included in  Release in part 
     9.  Energy Safety Standards Update - linked to email 2024-05-
25 
  
I have decided to release the relevant parts of the documents listed above subject 
to certain information being withheld under the following section of the Act, with 
any information not relevant to your request removed and noted as “out of scope”:   
 
9(2)(a) – to protect the privacy of natural persons 
 
 
Information being withheld 
   
The information below is covered by your request.   
  
Item 
Document Title 
Decision 
9.    Email dated 25 September 2025 and attachments 
9(2)(h) 
10.    Email dated – dated 13 August 2025 and attachments 
9(2)(h) 
11.    Email dated – dated 16 September 2025 and attachments 
9(2)(h) 
12.    Email dated 7 August 2025 
9(2)(h) 
13.    Email dated 22 August 2025 and attachments 
9(2)(h) 
14.    Email dated 22 September 2025 
9(2)(h) 
15.    Email dated 4 September 2025 
9(2)(h) 
16.    Email dated 20 May 2025  
9(2)(h) 
 
I have decided to withhold the documents listed above in full under one or more of the 
following sections of the Act:   
   
9(2)(h) – to maintain legal professional privilege  
 
In making the decision to withhold information under section 9 of the   Act it has been 
considered that the public interest in release does not outweigh the reasons to withhold 
it.  
 
WorkSafe response to question 3: 
 
The MEN or TN-C-S system is relatively uncommon globally, and different variants which 
are not completely consistent with other variants are implemented. In each case, there 
are variations in the balance in how aspects of those systems are assigned between the 
network and consumer installations. The characteristics of networks and the range of 



 
 
 
 
installation types also influence how safety is achieved. Therefore, while it is useful to 
consider other jurisdictions, each system should be considered unique.   
WorkSafe experts routinely engage in informal technical discussions in standards 
development fora as well as with local and international contacts. Discussions of this 
nature are typically informal and involve shared concerns and insights regarding the 
challenges of, and approaches to, achieving electrical safety as new applications arise 
and technology evolves to address global challenges.  
Guidance on providing for safety which relies on ‘switching’ the PEN or protective earth 
conductor at consumer mains in a system which corresponds with the New Zealand 
MEN system is therefore only relevant to similar systems which also seek to address 
electrical safety in circumstances where there are acknowledged weaknesses with the 
implementation of an MEN system.  
In this case, at the time the United Kingdom was specifically identified as providing or 
developing relevant guidance which includes ‘switching’ the PEN or protective earth 
conductor to provide for safety.  
 
This reply addresses the information you requested. You may ask the Ombudsman to 
investigate and review this decision, and further information is available at 
www.ombudsman.parliament.nz.   
 
If you require further assistance, please contact [email address]. 
 
Yours sincerely 
 
 
 
 
Rob Pope 
Head of Inspectorate