Fluoridation Capital Works 
Project Completion Report 
 
Overview 
This report provides Manatū Hauora with information about the delivery of the project to time, the 
construction of the fluoridation plant, delivery to budget, and includes details of the claim being made. 
Its overall purpose is to confirm compliance with the direction to fluoridate. 
Instructions 
The nominated and approved Certifying Engineer must complete all sections of this report then email 
the report to Allen + Clarke at [email address] by the 10th day of the next 
month 
following completion of the project. 
Details of supply/supplies fluoridated 
Local Authority name: 
New Plymouth District Council 
Water treatment plant(s): 
New Plymouth WTP 
Compliance date(s): 
30 July 2023 
Contract number: 
222308313 
Contracted budget: 
$225,960.00 excluding GST 
Was the project completed within the planned timeframe and compliance date(s)? 
 Yes 
 No 
If the project was not completed within the planned timeframe or compliance date(s), explain why this 
happened. Note that “completed” means the fluoridation plant has been commissioned and is safely 
dosing fluoride into the supply. 
 
Project completion date:  
31/07/2023 
To the best of your knowledge has the fluoridation plant (or plants) been 
 Yes 
constructed in accordance with the approved design (which has been peer reviewed 
 No 
against the Code of Practice for fluoridation of drinking-water supplies or the Good 
Practice Guide for Fluoridation of Drinking Water Supplies)
? 
 
If not, please provide details and the reasons why: 
 
Does the fluoridation plant (or plants) target a fluoride ion concentration of 0.80 or 
 Yes 
0.85 m/L (allowing for any fluoride present in the raw water), and consistently 
 No 
achieve a level of fluoride ion in the water supply within the range of 0.7 to 
1.0 mg/L?
 
This is the optimal amount recommended by the World Health Organisation to provide 
 
protection against tooth decay. If not, please provide details and the reasons why: 
 
Are there any remaining technical issues that need to be followed up and closed 
 Yes 
out? 
 No 
Tell us about any outstanding issues or future risks. Will the completed project be sustainable for the 
foreseeable future? 
Project Completion Report Template – July 2023 


Sensitivity: General 
 
There’s been some minor variability to the dose (remaining with the 0.7-1.0 mg/L range), this is being 
monitored and adjustments being made to improve the control. This includes manual checks and lab 
results.  
Was the project completed within the project budget? 
 Yes 
 No 
If the project was not completed within the budget, explain why this happened. 
 
Were there any variations to the supply and/or install contract(s)? 
 Yes 
 No 
Include details of all contract variations: 
Second fluoride analyser was purchased from an alternate supplier, due to issues with the first 
analyser that could not be suitably resolved with the first supplier.  
Have you been through all the payment certificates and/or invoices for the project 
 Yes 
and confirmed that only eligible cost items are being claimed from Manatū Hauora, 
 No 
and/or that where fluoridation has been installed as part of a larger package of 
works that the portion being claimed is reasonable?  

Include any details of relevance: 
 
Amount of claim 
Amount claimed from Manatū Hauora (excl. GST): 
$212,672.06 
Attach copies of all payment certificates and/or invoices to the claim form (Appendix 1). Payment 
certificates and/or invoices must be clearly marked up as necessary to reconcile these with the amount 
claimed from Manatū Hauora.  
Does this claim represent the final amount? 
 Yes 
 No 
If there are further payment certificates and/or invoices, when will they be processed into a claim and 
how much is that claim expected to be? 
 
Final comments 
Are there any final comments that you would like to make about the project to Manatū Hauora? 
 
Certifying Engineer completing this report 
Full name and job title 
Signature 
Date 
Ben Plummer CPEng 
25/08/2023 
Principal Engineer – Water 
Treatment 
 
 
 
 
Project Completion Report Template – July 2023 

Sensitivity: General 
 
 
Appendix 1: Claim Form 
Attach copies of all payment certificates and/or invoices clearly marked up as necessary to reconcile these 
with the amount claimed from Manatū Hauora. 
Cert or 
Date 
Work covered 
Amount of 
Amount of 
Summary of 
invoice 
certificate/ 
claim (excl. 
reason for 
refer-
invoice (excl. 
GST) 
difference 
ence  
GST) 
 
 
 


 
 
 
 


 
 
 
 


 
 
 
 


 
 
 
 


 
 
 
 


 
 
 
 


 
 
 
 


 
 
 
 


 
 
 
 


 
 
 
 


 
Total claimed  $ 
 
 
 
 
 