This is an HTML version of an attachment to the Official Information request 'Fluoride Supply Chain Information'.

  
 
 
 
 
 
KAWERAU WTP FLUORIDATION OPERATING AND 
MAINTENANCE MANUAL 
S-0273-G-MAN-001 
 
 
 
KDC 
S-0273 Kawerau Fluoridation Project  
 
 
 
 
Revision history 
Date 
Rev.  Author 
Checked 
Approved 
Description 
30/08/24 
0  K Brooks  
 
 
Issued for Use  
12/11/24 
1  K Brooks  
J Brosnan 
J Brosnan 
Issued for Use  (As Built) 
 
 
 
All copies of this document are uncontrolled. 
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 1 of 39 

link to page 5 link to page 5 link to page 5 link to page 5 link to page 6 link to page 6 link to page 6 link to page 7 link to page 7 link to page 7 link to page 9 link to page 10 link to page 11 link to page 12 link to page 14 link to page 14 link to page 16 link to page 17 link to page 17 link to page 17 link to page 17 link to page 18 link to page 28 link to page 28 link to page 28 link to page 28 link to page 29 link to page 29 link to page 29 link to page 30 link to page 33 link to page 33 link to page 33 link to page 33 link to page 34 link to page 36 link to page 37













 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
TABLE OF CONTENTS 

INTRODUCTION ............................................................................................................. 5 
  Purpose and Scope of the Fluoridation Project ........................................................... 5 
  Legal and Regulatory requirements .......................................................................... 5 
  Overview of the water supply system ....................................................................... 5 


FLUORIDATION PLANT DESCRIPTION ............................................................................... 6 
  Summary ............................................................................................................. 6 
  Plant Design Parameters ......................................................................................... 6 
  Fluoridation Plant Equipment ................................................................................... 7 
2.3.1  IBC Bund .................................................................................................. 7 
2.3.2  IBC Drum Pump and Load In Panel .............................................................. 7 
2.3.3  FSA Storage Tank ...................................................................................... 9 
2.3.4  Transfer Pumps and Transfer line ............................................................... 10 
2.3.5  FSA Day Tank .......................................................................................... 11 
2.3.6  Dosing Pumps and Lines ........................................................................... 12 
2.3.7  Fluoride Analysers .................................................................................... 14 
2.3.8  Ancillary Equipment ................................................................................. 14 

  Reference Drawings ............................................................................................. 16 

FLUORIDATION PLANT PROCESS OPERATION .................................................................. 17 

FLUORIDATION PLANT PROCESS CONTROL ..................................................................... 17 

EQUIPMENT MANUALS .................................................................................................. 17 

OPERATING PROCEDURES ............................................................................................ 17 

PLANT MAINTENANCE REQUIREMENTS: .......................................................................... 18 

MONITORING AND TESTING ......................................................................................... 28 
  Fluoride Levels .................................................................................................... 28 
  Plant Testing and Monitoring ................................................................................. 28 


SAFETY AND EMERGENCY PROCEDURES ......................................................................... 28 
  Emergency Procedures ......................................................................................... 29 
  Contact Information ............................................................................................. 29 

10  QUALITY CONTROL: ..................................................................................................... 29 
11  RECORD KEEPING: ...................................................................................................... 30 
12  STAFF TRAINING ......................................................................................................... 33 
  Staff Qualifications ............................................................................................... 33 
  Staff Training ...................................................................................................... 33 
  Procedure for Documenting Staff Training ............................................................... 33 

13  REVIEW AND UPDATE PROCEDURES FOR THIS MANUAL ................................................... 34 
APPENDIX A—FLUORIDATION PLANT FUNCTIONAL CONTROL DESCRIPTION ............................... 36 
APPENDIX B—IXOM FLUOROSILIC ACID SAFETY DATA SHEET ................................................... 37 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 2 of 39 

link to page 38 link to page 39 link to page 39  
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
APPENDIX C—STANDARD OPERATING PROCEDURES ............................................................... 38 
APPENDIX D—VENDOR EQUIPMENT DATA SHEETS AND OPERATION AND MAINTENANCE 
MANUALS ........................................................................................................................... 39 
 
 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 3 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
ACRONYMS AND DEFINITIONS  
Term 
Definition 
CDR 
Lutra – Kawerau Fluoridation Assessment - Fluoride Assessment and Concept Design 
Report , KDC001-R01-1 Fluoride Assessment and Concept Design Report , KDC001-
R01-1 
FSA 
Fluorosilicic acid, also known as HFA (hydrofluosilicic acid)  
GA 
General Arrangement 
GPG or Good Practice  Water New Zealand, Good Practice Guide: Fluoridation of Drinking-Water Supplies in 
Guide 
New Zealand, February 2023 , Volume 1 & 2.  
HSNO 
Hazardous Substances and New Organisms (HSNO) Act. 
IBC 
Intermediate bulk container 
MAV 
Maximum Allowable Value 
May 
Indicates a possible course of action. 
MoH 
New Zealand Ministry of Health  
PE 
Polyethylene 
Peer Review Report  
Warren Mackenzie Consulting  - Kawerau Water Treatment Plant – Fluoridation System 
Peer Review, dated 28/3/23 
Shall 
Indicates a mandatory requirement. 
Should 
Indicates a preferred course of action. 
Taumata Arowai 
The water services regulator for Aotearoa, New Zealand 
 
 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 4 of 39 

link to page 6


 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 

INTRODUCTION  
 
Purpose and Scope of the Fluoridation Project  
Kawerau DC are required by the MoH to incorporate fluoride dosing into the existing Kawerau WTP, 
hence TRILITY was engaged to design and build a fluoridation system at the plant on behalf of the 
Kawerau District Council. The fluoridation system has been constructed in the existing WTP building 
and it has four main aspects: chemical unloading, storage, dosing and analysis of the treated water 
for fluoride. Fluoride is supplied and dosed as fluorosilicic acid (FSA). The fluoridation system is 
described in Section 2.  
 
Legal and Regulatory requirements 
Concentrated FSA as supplied at 20-23% concentration is both a corrosive and toxic substance. It is 
a Class 8 Dangerous Good and is also classed as a Hazardous substance. Operators should be aware 
of the relevant requirements of NZ Health and Safety at Work (Hazardous Substances) Regulations 
2017 and HSNO. Operators and contractors who are required to work at Kawerau WTP should be 
trained in the precautions, handling, PPE, first aid, emergency management and regulatory 
requirements for FSA.  
Fluoride dosing into drinking water is regulated and monitored by the MoH, refer to the most recent 
copy of the Good Practice Guide (GPG) (Volume 1 and 2)  for the requirements that must be met.  
Fluoridation must be incorporated into KDC’ s Drinking Water Safety Plan.  
This O&M manual refers to the requirements of the GPG from the February 2023 issue, this manual 
should be reviewed and updated when these guidelines are updated.  
 
Overview of the water supply system 
The Kawerau water supply system serves around 2,900 properties, including residential households, 
businesses, and industrial entities. The system caters to a resident population of approximately 
8,000 people. The water is sourced from two springs and three bores. The treated water is stored in 
two concrete reservoirs located on Monika Lanham Reserve, with a combined capacity of 6,700 m3, 
and a third reservoir on Beattie Road Reserve with a capacity of 4,500 m3. The reticulation network 
includes 75 kilometres of pipes, 700 valves, and 880 fire hydrants, efficiently distributing water to all 
connected properties. 
The water treatment process starts with screening to remove large debris, followed by UV 
disinfection to kill harmful microorganisms. Chlorine is added to maintain a safe level of disinfectant, 
and fluoride is added as part of the MoH directive to improve dental health. Finally, caustic soda is 
used to adjust the pH and ensure effective disinfection. 
The Pumphouse Treatment Plant is designed to handle a maximum flow rate of 725 m3/hr, with 
continuous monitoring to maintain water quality. Reservoir levels are kept above 75% to ensure a 
steady supply and prevent pressure fluctuations. Regular checks are conducted to keep the water 
clear and free from sediment, and security measures are in place to prevent contamination. Regular 
water quality sampling at the Pumphouse Treatment Plant and across the District to ensure the 
reliability and water safety of the watery supply.  
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 5 of 39 



 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 

FLUORIDATION PLANT DESCRIPTION  
 
Summary 
Fluoride is delivered to the plant as fluorosilicic acid (FSA), in a 1,000L IBC. The operator will use 
the forklift to load the FSA IBC onto the FSA IBC bund in the fluoride room.  
When FSA Storage Tank filling is required, the operator will don PPE and use the removable drum 
pump to load FSA into the 2, 000L storage tank, he/ she will place the drum pump into the top of 
the IBC and turn the pump on at the local GPO on/ off switch. The operator will stop the pump once 
the unloading is complete. As a safeguard, the control system will cut power to the pump on 
reaching the safe fill level. Once the drum pump has been stopped, the delivery pipework will self-
drain both to the bulk tank and back to the IBC (through the drum pump), prior to the operator 
removing the pump from the IBC and placing it back on its stand.  
Fluoride is not dosed from the bulk storage directly into the water supply, instead, it is metered into 
a day tank, which hold 1 days’ worth of FSA (at maximum plant flowrates), this is required (by NZ 
regulations) in order to reduce the risk of overdosing of the water supply. The FSA is metered into 
the day tank via air driven diaphragm pumps (operating as duty/ standby). 
Once in the day tank, the FSA is dosed into the water supply via dosing pumps (operating as duty/ 
standby). Backpressure valves in the dosing system prevent the risk of siphoning from the day tank 
to the water supply. The pumps are each fitted with a pressure relief valve, which relieves back to 
the day tank, should a blockage occur in the dosing line. The dosed FSA enters the water supply via 
(duty/standby) dosing lines with injection spears into the mains water. 
To confirm that the fluoride dosing is at the correct dosage rate, duty/ standby fluoride analysers 
analyse a sample from the water sample point, located a suitable distance downstream from the 
dosing point to allow for mixing. The fluoride dosing system will automatically stop should the 
analysed concentration be above the maximum allowable value, or if the analyser low flow switch 
activates, indicating that the sample water is not running through the sample.  
Special provisions have been made in the plant design to enable operating and maintenance without 
risk of contact with the FSA, which is toxic and corrosive, and also to ensure fluoride is never dosed 
if the water supply is not running, and to ensure that the fluoride dose does not exceed the guideline 
concentration. 
 
Plant Design Parameters 
Table 1—Plant Design Parameters 
Parameter  
Value 
Average Water Demand 
4,000 m3/day 
 
Peak Daily Demand  
13,500 m3/day 
Max Plant Capacity 
14,000 m3/day 
Background level of fluoride in water supply 
0-0.1 mg/L 
Fluoride Dose Requirement  
0.75 mg/L 
Fluoride Residual Setpoint 
0.85 mg/L 
Maximum Fluoride Dose Rate  
1.00 mg/L 
Supplied FSA concentration 
22% 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 6 of 39 



 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Parameter  
Value 
Supplied FSA SG 
1.22 
FSA bulk storage tank nominal volume  
2,000 L 
FSA Day tank nominal volume  
58 L 
FSA instantaneous transfer rate to Day tank  
10 L/min 
 
 
Fluoridation Plant Equipment 
2.3.1  IBC Bund 
The FSA is supplied in 1,000L IBCs. An HPDE Bund is provided in the fluoride room for the supplied 
Fluoride IBC to be placed on, the purpose of this bund is to contain leaks/ splashes from the IBC or 
the Drum Pump. The bund has a drain valve which will normally be kept closed.  
 
Figure 1 -IBC Bund 
2.3.2  IBC Drum Pump and Load In Panel 
A portable drum pump is provided for the operator to place into the top of the IBC to load FSA into 
the storage tank. The drum pump has a dedicated GPO point. The operator connects the drum 
discharge hose to the load in line, turns on the GPO and then switches on the hand switch on the 
drum pump.  Refer to procedure S-0273-G-WI-001 Filling the FSA Tank from an IBC. 
There is a Load-In panel on the building wall, visible to the operator at the drum pump, which 
displays the following information: 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 7 of 39 


 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
•  2x level indicator readings reading in litres, one from each level transmitter in the FSA Storage 
Tank The load in panel has a label that reads “Safe Fill level = 1,800 L ; Maximum Fill Level = 
2,000L”  
•  An audible/ visual alarm which activates at the Safe Fill Level and at the Maximum fill level from 
EITHER level instrument 
•  A Safe Fill Level Override button which cancels the Safe Fill Level audible/ visual alarm AND the 
Safe Fill level GPO interlock for a period of 2 minutes 
•  A Maximum Fill Level Alarm silence button (Reset Lamp Test), which silences the maximum fill 
level audible alarm.  
•  A lamp indicating FSA tank bund high level. 
•  A System Emergency stop button - activation of this will cut power to the Drum Pump GPO, 
deactivate the transfer pumps’ solenoid valves and stop the dosing pump. 
 
Figure 2 – FSA Load -In Panel 
The operator will run the pump until the IBC is nearly empty, or the FSA tank is full. The drum pump 
should not be run dry. The operator will switch off the pump either at the pump hand switch or the 
GPO.  
If the FSA Storage tank level (level instrument) reaches Maximum fill level, then the PLC will cut 
power to the drum pump GPO, until BOTH instruments read below Maximum Fill Level. The Operator 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 8 of 39 


 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
can press the “Maximum Fill Level Alarm Silence (Reset Lamp Test)” button which will de-activate 
the audible alarm but will have no effect in the GPO interlock.  
If the FSA Storage tank bund high level switch is activated, then the PLC will cut power to the drum 
pump GPO and activate the lamp indicating FSA tank bund high level .  There will be no override for 
this alarm.  
2.3.3  FSA Storage Tank 
FSA is stored in the FSA Storage Tank which is a 2,000 litre self-bunded PE Tank in the fluoride 
room. The volume of the tank is monitored by two radar level transmitters. The level on these two 
transmitters is also be displayed on the Load In Panel beside the IBC bund and on the OIP.  
If FSA leaks/ overflows into the tank bund, this is indicated by a level switch  
The FSA Storage tank overflow pipe terminates in a lute seal , or water trap,  to prevent odours 
from the tank from entering the fluoride room. A low level switch indicates that the level on this 
water trap is low, requiring that the operator manually opens the water fill valve and refills it (until it 
overflows, and then re-closes the water supply.  
The FSA tank is vented outside the WTP building. 
  
 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 9 of 39 

link to page 11
 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
 
2.3.4  Transfer Pumps and Transfer line 
As a protection from overdosing of fluoride into the water,  the dosing system must be supplied via a 
Day Tank (refer to section 2.3.5)  which is limited to filling only once per day. The role of the 
transfer pumps (2 , which operate duty / standby) is to fill this Day Tank. The Transfer pumps are 
air-operated double diaphragm pump which use air power, rather than an electric motor, as the 
motive force for pumping.  
The nominal pump capacity of each pump is 15 L/min, however by manually limiting the air pressure 
to 4 bar and providing back pressure to the delivery line via a manual valve diaphragm valve, this 
will be capped at around 5-10 L /min. The pumps are started by the PLC opening the air solenoid 
valve of the duty pump.  The control system will limit the running time of the pump to 1 minute at a 
time to limit the fill rate of the day tank, prior to a 10 second interval to allow the level instrument 
to stabilise. Hence the duty pump would be expected to run for up to 12 minutes over a period of 36 
minutes each 24 hours. This transfer operation will start at 12:00am each evening, once the transfer 
is complete, it will not run again until the same time the next evening. The day tank fills to the same 
level each time, to the “Transfer Stop Level in FSA Day Tank”, set at 51 litres.  
Two (fail closed) air actuated valves before and after the transfer pumps, are normally closed to 
prevent siphoning when the pump is not operating. Line strainers trap foreign materials before the 
day tank. A flow switch on the transfer pump discharge line indicates a no-flow fault situation. 
Activation of the day tank/ dosing panel bund high level switch or the transfer pump bund high level 
switch will immediately stop the FSA transfer pumps. 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 10 of 39 


 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
 
2.3.5  FSA Day Tank 
The Day Tank stores a maximum of 24 hours (at maximum plant flow) of expected fluoride usage in 
a 58 litre PE tank. The overflow pipe terminates in a water trap to prevent odours from the tank 
from entering the fluoride room. The tank vent joins a common vent line for the fluoride system 
which vents outside of the building.  
The day tank is fitted with a radar level transmitter and separate high and low level switches. The 
level of the tank is monitored continuously and each fill cycle the daily use is recorded by SCADA. 
The day tank overflow lute seal is fitted with a low level switch, once this switch is activated, 
indicating the seal pot level is low, a solenoid valve opens and allows water refilling of the seal pot, 
for 10 seconds, after switching off. 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 11 of 39 


 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
 
 
2.3.6  Dosing Pumps and Lines 
There are two fluoride dosing pumps (operating duty / standby) which dose the neat FSA from the 
Day Tank into the mains water. These are Grundfos DDA 7.5 16 pumps, which are each capable of 
dosing a maximum flow of 7.5 Lph of FSA into the water, during commissioning, this flowrate will be 
limited to 2.4 Lph to prevent overdosing. 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 12 of 39 


 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
 
The dosing sequence is as follows: 
The call to run (for the dosing system) is initiated when the plant water flow is above the PLC coded 
minimum value of 125 m3/hour AND the low water flow switch is not activated.  
To prevent accidental overdosing, neither pump will run in auto if one pump’s selector switch (on the 
panel) is in manual, in this case dosing shall stop and an urgent alarm will be raised “Dosing Pump 
in Manual – Auto dosing stopped”. 
There are two dosing lines, but only one is required to be in operation. The duty dose line is selected 
by the operator and the appropriate manual valves are positioned to isolate the standby dose line by 
the plant operator. Once Dosing is called to run, the dosing pumps suction and discharge lines’ 
actuated valves will open and the duty dosing pump will start.   
The duty dose pumps speed signal is calculated from the water flow. The required dose rate is based 
on the FSA concentration, the calculated total water flow and the required fluoride dose. The duty 
dose pumps speed is trimmed based on the deviation of actual dose and the analysed fluoride 
concentration downstream of the dose point. 
The actual dose rate (i.e., referred to as Dose Verification in the Good Practice Guide) is calculated 
from the measured FSA flow, the plant flow, and the FSA specific gravity.  
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 13 of 39 


 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
2.3.7  Fluoride Analysers 
The potable water is sampled and analysed for fluoride concentration via two analysers located in 
the fluoride room. The two analysers operate in parallel and at least one must be operational for 
dosing to operate.  
 
 
The flow to the analysers is manually controlled and is typically set up during commissioning. Each 
analyser requires a flow of between 30 to 60 L/hr at a maximum pressure of 1 bar. The analysers 
each have a low flow switch to indicate if sample flow has stopped.  The operator will be able to 
select one of the two analysers to be out of service (but never both) , in which case the reading and 
alarm/s from this analyser will be ignored by the control system.  
2.3.8  Ancillary Equipment 
Air Compressor 
The actuated valves and FSA transfer pumps are driven by compressed air. An air compressor and 
pressure vessel are installed behind the FSA room to supply this air. The compressor power is 
permanently on, and its onboard control system will turn the compressor on and off as required to 
maintain plant air pressure.   
A low-pressure switch on the air line to the plant is installed to indicate a problem with the plant air 
supply. Activation of this switch will stop the transfer and dosing systems, if they are in operation. 
Note that although air pressure is required to allow fluoride dosing, loss of air pressure will cause 
the air operated valves to fail in the closed position – effectively stopping dosing or day tank transfer 
without operator action.  
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 14 of 39 



 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Ventilation Fan 
A ventilation fan is permanently on, drawing air through the louvres above the roller door and out 
through the fan cowling to be discharged above the roof.  
Safety Shower and Wash Down Hose  
A safety shower has been installed in front of the Fluoridation room, for use in the event of a 
chemical splash. The shower is fitted with a flow switch to indicate that it has been operated. Correct 
operation of this shower should be checked regularly. 
 
A wash down hose is included inside the building, near the IBC bund, for washing down any 
chemical splashes. 
 
 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 15 of 39 


 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
 
Reference Drawings 
Table 2—Plant Reference Drawings 
Drawing or Document 
Number  
Title 
S-0273-E-503-01-001 
Single Line Diagram 
S-0273-E-503-02-001 
Control Panel Schematic 1 
S-0273-E-503-02-002 
Control Panel Schematic 2 
S-0273-E-503-02-003 
Control Panel Schematic 3 
S-0273-E-503-02-004 
Control Panel Schematic 4 
S-0273-E-503-02-005 
Control Panel Schematic 5 
S-0273-E-503-02-006 
Control Panel Schematic 6 
S-0273-E-503-03-001 
Wiring Diagram 1 
S-0273-E-503-03-002 
Wiring Diagram 2 
S-0273-E-503-03-003 
Wiring Diagram 3 
S-0273-E-503-03-004 
Wiring Diagram 4 
S-0273-E-503-03-005 
Wiring Diagram 5 
S-0273-E-503-03-006 
Wiring Diagram 6 
S-0273-E-503-03-007 
Wiring Diagram 7 
S-0273-E-503-04-001 
Panel GA 
S-0273-E-503-04-002 
Panel Label List 
S-0273-E-503-05-001 
Dual Tank Control Panel – General Arrgt 
S-0273-E-503-05-002 
Dual Tank Unloading Panel – General Arrgt 
S-0273-E-503-05-003 
Dual Tank Control Panel – Electrical Schematic 1 
S-0273-E-503-05-004 
Dual Tank Control Panel – Electrical Schematic 2 
S-0273-E-503-05-005 
Dual Tank Control Panel – Electrical Schematic 3 
S-0273-E-503-05-006 
Dual Tank Control Panel – Electrical Schematic 4 
S-0237-M-503-02-004 
Bulk Storage Tank GA 
S-0237-M-503-03-001 
Day Tank And Dosing Panel GA 
S-0237-M-503-04-001 
Day Tank Transfer Pump Skid 
S-0237-M-605-01-001 
Fluoride Analyser Panel GA 
S-0237-M-700-01-001 
FSA Room GA 
S-0237-P-001 
P&ID Standard Symbols – Sheet 1 of 5 
S-0237-P-002 
P&ID Standard Symbols – Sheet 2 of 5 
S-0237-P-003 
P&ID Standard Symbols – Sheet 3 of 5 
S-0237-P-004 
P&ID Standard Symbols – Sheet 4 of 5 
S-0237-P-005 
P&ID Standard Symbols – Sheet 5 of 5 
S-0237-P-503-001 
P&ID – FSA Storage Tank 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 16 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Drawing or Document 
Number  
Title 
S-0237-P-503-002 
P&ID- Dosing Pump 
S-0237-P-503-003 
P&ID – Fluoride Dosing & Analysers  

FLUORIDATION PLANT PROCESS OPERATION  
In normal operation, fluoride dosing and FSA transfer to the day tank runs automatically via the 
control system, and Operator intervention is not required unless an alarm has been raised or the 
system has faulted. On first start up, or after the plant has been isolated for maintenance, the 
Operator may be required to line up the plant valves in their correct positions prior to automatic 
running of the plant. The correct line up of valves is described in SOPs S-0273-G-WI-002 Transfer 
Pump Set-Up, S-0273-G-WI-003 Fluoride Start Up and S-0273-G-WI-007 Setting back pressure and 
pressure relief valves for the dosing system.  
Loading of FSA from the IBC to the FSA Storage Tank is a manual task, and this described in in SOP 
S-0273-G-WI-001 FSA Unloading from an IBC.  

FLUORIDATION PLANT PROCESS CONTROL  
A detailed description of the fluoridation plant control is provided in S-0273-P-FUD-001, the plant 
functional description. A copy of this document is included in Appendix A. This document should be 
frequently reviewed and updated when changes occur. 

EQUIPMENT MANUALS 
For detailed descriptions of individual items of equipment, refer to the equipment vendors’ O&M 
Manuals, copies of these are included in Appendix D.  

OPERATING PROCEDURES 
Plant operators must familiarise themselves with the plant equipment and operating procedures, a 
list of the standard operating procedures is included below: 
Table 3—Kawerau WTP Fluoridation System Standard Operating Procedures 
Document Number  
Document Title  
S-0273-G-WI-001 
FSA Unloading from an IBC 
S-0273-G-WI-002 
Transfer Pump Set Up 
S-0273-G-WI-003 
Fluoride Start Up  
S-0273-G-WI-004 
Dosing Pump Calibration 
S-0273-G-WI-005 
Fluoride Analyser Calibration & Filter Cartridge Change 
S-0273-G-WI-006 
Manual Sampling for Fluoride   
S-0273-G-WI-007 
Setting back pressure and pressure relief valves for the dosing system 
S-0273-G-WI-008 
Draining the bunds 
 
WTP Emergency Response plan   
Copies of these procedures are included in Appendix C. 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 17 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 

 PLANT MAINTENANCE REQUIREMENTS: 
For detailed descriptions of the maintenance requirements of each item of equipment, refer to the equipment vendors’ O&M Manuals, copies of these 
are included in Appendix D. A brief summary of the recommended plant maintenance schedule is included below, this is not intended as a substitute 
for fully reviewing and understanding the manufacturers’ recommendations.  This information has been provided prior to commissioning and should 
be reviewed periodically and updated as necessary based on plant / equipment performance:  
Table 4— Maintenance Schedule Recommendations 
Tag 
Equipment/Instrument/valve 
Name 
Recommended Maintenance/ Maintenance Interval 
Notes 
EQUIPMENT: 
TNK001 
FSA IBC BUND 
Periodic – visual inspection for damage/ monthly 
 
PMP001 
IBC DRUM PUMP 
At each use – visual inspection for leaks or damage  
 
FSA STORAGE TANK 
Periodic – visual inspection for leaks or damage/ monthly 
 
TNK101 
FSA STORAGE TANK – 
Periodic – visual inspection for leaks or damage/ monthly 
 
OVERFLOW LUTE SEAL 
Vendor recommendations  
 
•  carry out periodic inspections (2-30 days in accordance 
with the fluid pumped) on the filter element of the suction 
strainer (if any) and remove any trapped filtrate when 
PMP101,PMP102 
FSA TRANSFER PUMP #1/#2 
pumping fluids with solids;  
TO FSA DAY TANK 
•  carry out periodic inspections (3-5 months in accordance 
with the fluid pumped and the environment conditions);  
•  ensure correct operation of the system start/stop units;  
 
FAN103 
FSA ROOM BUILDING 
None recommended 
 
VENTILATION FAN 
Periodic – visual inspection for leaks or damage/ monthly 
Contact Ashair  0800 808 486 
CPR104 
PLANT AIR COMPESSOR 
Annual service required 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 18 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Tag 
Equipment/Instrument/valve 
Name 
Recommended Maintenance/ Maintenance Interval 
Notes 
Periodic – visual inspection for leaks or damage/ monthly 
 
 
 
Annual service required 
FSA INLINE STRAINER, FSA  Periodic-  visual inspection for leaks / monthly 
 
STN138, STN309 
DOSING PUMP SUCTION 
If flow restriction occurs flush system with water, then remove 
STRAINER 
strainer basket and clear 
TNK301 
FSA DAY TANK  
Periodic – visual inspection for leaks / damage/ monthly 
 
TNK302 
FSA DAY TANK OVERFLOW 
Periodic – visual inspection for leaks / damage/ monthly 
 
LUTE SEAL 
Periodic – visual inspection for leaks / damage/ monthly 
 
CAL303 
FSA DOSING PUMP 
CALIBRATION COLUMN 
 
Daily: 
Vendor recommendation  
Check, if liquid leaks from the drain opening (see manual) and if 
the drain opening is blocked or soiled. If so, follow the instructions 
given inspection 7.6 Diaphragm breakage ( of manual) 
Check, if liquid leaks from the dosing 
head or valves. If necessary, tighten dosing headscrews with a 
torque wrench at 4 Nm. If necessary, tighten valves and cap nuts, 
or perform service (see 7.4 Perform service, of manual). 
Check, if a service requirement is present at the pump display. If 
PMP301 , PMP302 
FSA DOSING PUMP 1/ 2 
so, follow the instructions given instructions given in 
section 7.3 Service system (of manual)
 
Weekly -Clean all pump surfaces with a dry 
Vendor recommendation 
and clean cloth. 
Monthly – Recalibrate and record results 
Monthly flow calibration is required by GPG 
24 Monthly ( or 8000 service hours)  - Service as per Pump manual  Vendor recommendation 
section 7.4 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 19 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Tag 
Equipment/Instrument/valve 
Name 
Recommended Maintenance/ Maintenance Interval 
Notes 
Test operation on entry to the room – on each occasion  
 
SSR424 
SAFETY SHOWER AND 
Periodic – inspect shower head / eyewash sprays for build-up , 
EYEWASH 
debris or damage  - Weekly 
Periodic – complete flow test / annually 
Periodic – visual inspection for leaks / damage/ 6 monthly 
 
HOS426 
Retractable Washdown Hose 
(Indoor dosing panel area) 
 
STN703, STN710 
ANALYSER  1, 2  SAMPLE 
Visual inspection to confirm that flow is not restricted / no algal 
 
STRAINERS 
growth  in filter 
Periodic – visual inspection for leaks / damage/ monthly 
 
ME440, ME441 
INJECTION QUILLS  
 
Periodic – visual inspection for leaks / damage/ 6 monthly 
 
ME719 
SAMPLE SINK 
 
ME720 
PORTABLE STEP LADDER 
Periodic – visual inspection for damage/ 6 monthly 
 
INSTRUIMENTS: 
AE/AIT7O6, 708 
Carry out regular visual inspections of the fluoride measuring 
Vendor advice 
system, particularly the fluoride probe, the in-line probe housing 
and the flow meter. 
Look for: 
• air bubbles in the sample water 
• air bubbles in front of the LaF3 crystal of the fluoride probe 
• leaks 
• correct flow through the cell 
Check that the limit value sensor is seated firmly on the flow 
meter. 
Check that the float can move freely inside the flow meter. 
FLUORIDE ANALYSERS 1,2 
If you need to alter the flow: the float should move. If necessary, 
clean the flow meter and then test its function again (change flow). 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 20 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Tag 
Equipment/Instrument/valve 
Name 
Recommended Maintenance/ Maintenance Interval 
Notes 
Recalibration  - record results  
At least monthly, or more frequently if 
 
accuracy requirement is not being exceeded 
FI 402,716, 706B, 
None recommended 
 
708B 
ROTAMETERS - VARIOUS 
FIT312 
FSA DOSING FLOW 
None recommended 
 
TRANSMITTER 
FS126,403,425,427 
None recommended 
 
706B,708B 
 
FLOWSWITCHES - VARIOUS 
LIT103 A, B, 301 
LEVEL TRANSMITTERS 
None recommended 
 
LAH 107, 138 
PANEL INDICATOR LAMPS 
Test schedule  - Suggest 6 monthly lamp test 
 
LSH124, 332 
BUND LEVEL SWITCHES 
None recommended 
 
LSH107, 129, 307, 
LEVEL SWITHCES – 
None recommended 
 
308, 330, 411, 429  VARIOUS  
PI123,326, 404, 14, 
None recommended 
 
430  
PRESSURE GAUGES - 
 
VARIOUS 
PSL137 
COMPRESSED AIR 
None recommended 
 
PRESSURE SWITCH 
VALVES: 
BLL110,122,303, 
Actuator: 
 
331 
- Check air quality / pressure periodically.  
- Check for leaks of the device. If necessary, replace the o-rings  
 
Ball Valve: 
ACTUATED BALL VALVES - 
1. Visual and function check (every three months): – Normal 
VARIOUS 
operating conditions unchanged – No leaks – No unusual operating 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 21 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Tag 
Equipment/Instrument/valve 
Name 
Recommended Maintenance/ Maintenance Interval 
Notes 
noises or vibrations  
2. Ensure that fitting functions properly (opening, closing)  
3. Clean fitting with a moist cloth if necessary 
 
SOL124,125 
Low frequency operation: Switch valves at least once every 30 
 
days to prevent malfunction. Also, in order to use it under 
SOLENOID VALVES – AIR  
optimum state, conduct a regular inspection once every 6 months. 
SOL329 
SOLENOID VALVE – WATER  No specific recommendations  
 
MANUAL BALL 
Periodic – visual inspection for leaks / test for operation - 6 
 
VALVES & V-PORT 
MANUAL BALL VALVES & V-
monthly  
BALL VALVES 
PORT BALL VALVES 
 
VARIOUS 
VARIOUS 
CHECK VALVES - 
Periodic – visual inspection for leaks / test for operation - 6 
 
VARIOUS 
monthly  
CHECK VALVES - VARIOUS 
 
Diaphragm valves  -  Diaphragm valves  - 
Periodic – visual inspection for leaks / damage/ monthly 
 
VARIOUS 
VARIOUS 
 
RPZD416 
DOSING SYSTEM WATER 
Annual re-test/ re- certification by licenced plumber  
Required by regulations ( tbc)  
RPZD 
SR320, 321 
1. Visual and function check (every three months): – Normal 
 
operating conditions unchanged – No leaks – No unusual operating 
noises or vibrations  
2. Check tightening torque of screws (12) (Manual → 9.2.3 
DOSING PUMP PRESSURE 
Tightening torques, Page 12).  
RELIEF VALVES 
3. Clean fitting with a moist cloth if necessary. 
PRV123 
AIR SUPPLY REGULATING 
No specific recommendations 
 
VALVE 
PG328, PG414,  
DOSING LINE BACK 
1. Visual and function check (every three months): – Normal 
 
PG431 
PRESSURE VALVE 
operating conditions unchanged – No leaks – No unusual operating 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 22 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Tag 
Equipment/Instrument/valve 
Name 
Recommended Maintenance/ Maintenance Interval 
Notes 
noises or vibrations  
2. Check tightening torque of screws (12) (Manual → 9.2.3 
Tightening torques, Page 12).  
3. Clean fitting with a moist cloth if necessary. 
 
Table 5—Spare Parts Recommendations 
The following table includes TRILITY’s initial recommendations for the installed equipment: 
 
Tag 
Equipment/Instrument/valve 
Name 
Recommended Spare parts 
Notes 
EQUIPMENT: 
TNK001 
FSA IBC BUND 
No recommendations 
 
PMP001 
IBC DRUM PUMP 
No recommendations 
 
TNK101 
FSA STORAGE TANK 
No recommendations 
 
 
FSA STORAGE TANK – 
No recommendations 
 
OVERFLOW LUTE SEAL 
PMP101,PMP102 
FSA TRANSFER PUMP #1/#2  4mm tubing and one-touch fittings 
 
TO FSA DAY TANK 
FAN103 
FSA ROOM BUILDING 
No recommendations 
 
VENTILATION FAN 
CPR104 
PLANT AIR COMPESSOR 
6mm & 10mm tubing and one-touch fittings 
 
VE104 
PLANT AIR COMPESSOR 
10mm tubing and one-touch fittings 
 
VESSEL 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 23 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Tag 
Equipment/Instrument/valve 
Name 
Recommended Spare parts 
Notes 
FSA INLINE STRAINER, FSA  Replacement strainer basket / o-rings for each , or 1 complete 
 
STN138, STN309 
DOSING PUMP SUCTION 
spare for each 
STRAINER 
TNK301 
FSA DAY TANK  
No recommendations  
 
TNK302 
FSA DAY TANK OVERFLOW 
No recommendations 
 
LUTE SEAL 
CAL303 
FSA DOSING PUMP 
No recommendations 
 
CALIBRATION COLUMN 
Grundfos service kit, valve/diaphragm. SD-S-PV/T/C-1 
Vendor recommendation 
PMP301 , PMP302 
FSA DOSING PUMP 1/ 2 
Product Code: 97751539 
SSR424 
SAFETY SHOWER AND 
Spare eyewash covers 
 
EYEWASH 
HOS426 
Retractable Washdown Hose  No recommendations 
 
(Indoor dosing panel area) 
STN703, STN710 
ANALYSER  1, 2  SAMPLE 
Replacement 5micron 5” filter cartridge (usu. 1 spare supplied with  TRILITY recommendation , replacement 
STRAINERS 
unit ) 
frequency will depend on om water quality  
ME440, ME441 
INJECTION QUILLS  
No recommendations ( these are duty /standby) 
 
ME719 
SAMPLE SINK 
No recommendations 
 
ME720 
PORTABLE STEP LADDER 
No recommendations 
 
INSTRUIMENTS: 
AE/AIT7O6, AND FI  FLUROIDE ANALYSERS 1,2 
Item/Part #  
This is the vendor recommended list, 
70806B, 708B 
and ROTAMETERS 
•  Flow cellDGMA300T000 
TRILITY advises that the items in bold are 
the most likely to be needed - suggest 
•  Transmitter FP V11028280 
holding 1 set of spares per 2 analysers 
•  Fluoride probe FELP 010 SE1028279 
•  Reference electrode REFR1083790 
•  Pt 100 sensor305063 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 24 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Tag 
Equipment/Instrument/valve 
Name 
Recommended Spare parts 
Notes 
•  Polishing Paste559810 
•  KCl solution 3M 250 ml791440 
•  Magnetic Stirrer3671000l 
•  Magnetic Stirrer Rod 001.215C 
•  Magnetic Rod Retriever 004.250.C 
•  Connection Set 8x5mm 1 pair 817053 
•  Ball Valve –DGMA1010380 
FI 402,716,  
ROTAMETERS - VAROUS 
None recommended  
 
FIT312 
FSA DOSING FLOW 
None recommended 
 
TRANSMITTER 
FS126,403,425,427  FLOWSWITCHES - VARIOUS  None recommended 
 
706B,708B 
LIT103 A, B, 301 
LEVEL TRANSMITTERS 
No vendor recommendations – consider holding 1 complete spare   
instrument  
LAH 107, 138 
PANEL INDICATOR LAMPS 
Suggest keeping 1 spare of each colour  
 
LSH124, 332 
BUND LEVEL SWITCHES 
Suggest keeping - 1 spare 
 
LSH107, 129, 307, 
LEVEL SWITHCES – 
Suggest keeping - 1 spare  
 
308, 330, 411, 429  VARIOUS  
PI123,326, 404, 14,  PRESSURE GAUGES - 
None recommended 
 
430  
VARIOUS 
PSL137 
COMPRESSED AIR 
None recommended 
 
PRESSURE SWITCH 
VALVES: 
BLL110,122,303, 
ACTUATED BALL VALVES - 
Actuators: 
May be easier to keep 1 spare valve body of 
331 
VARIOUS 
Spare kit available. Every kit includes:  
each size ( DN15, DN20) & 1 spare actuator 
o O-rings set  
for ease of replacement  
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 25 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Tag 
Equipment/Instrument/valve 
Name 
Recommended Spare parts 
Notes 
o Pistons friction bands  
 
o Pinions (models from PP10 to PP20)  
o Shaft washer.  
o Shaft safety ring 
 
Ball Valve: 
No specific recommendations  
SOL124,125 
SOLENOID VALVES – AIR  
No specific recommendations – consider keeping 1 complete spare   
valve or spare coil   
SOL329 
SOLENOID VALVE – WATER    Can get coil set , plunger tube set or wearing parts set, or keep 1   
complete spare valve 
MANUAL BALL 
MANUAL BALL VALVES & V-
Suggest keeping: 
 
VALVES & V-PORT 
PORT BALL VALVES 
•  1  x ½” (Ball Valve, 546 Pro, PVC-U, SCS, 1/2”, EPDM (p/n 
BALL VALVES 
VARIOUS 
161546242)), &  
VARIOUS 
•  1 x 1” (Ball Valve, 546 Pro, PVC-U, SCS, 1”, EPDM (p/n 
161546244)), 
CHECK VALVES - 
Check VALVES - VARIOUS 
Suggest keeping 1 x ½” & 1 x 1” in stock 
 
VARIOUS 
Diaphragm valves  -  Diaphragm valves  - 
Suggest keep 1 x ½” on hand (p/n 161 514 512) 
 
VARIOUS 
VARIOUS 
RPZD416 
DOSING SYSTEM WATER 
Vendor recommend a repair kit consists of: relief valve repair kit, 
 
RPZD 
first check repair kit, second check repair kit, retainer (if plastic) 
(p/n tba)  
SR320, 321 AND 
DOSING PUMP PRESSURE 
Vendor advises the diaphragm & seals can be renewed as required   
PG328, 414, 431 
RELIEF VALVES AND 
, however it may be easier to keep 1 x ½” spare complete valve in 
DOSING LINE BACK 
stock  
PRESSURE VALVE 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 26 of 39 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Tag 
Equipment/Instrument/valve 
Name 
Recommended Spare parts 
Notes 
PRV123 
AIR SUPPLY REGULATING 
No specific recommendations  
 
VALVE 
PIPING: 
General note  
Consider keeping small amount of DN15 pipe, fittings ,primer & 
 
 
glue onsite   
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 27 of 39 

link to page 30 link to page 30

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
 

MONITORING AND TESTING 
 
Fluoride Levels  
Fluoride dosing must be controlled within the following limits ( refer to GPG , Vol1, Sect 4.3):  
Total fluoride ion 
Parameter 
concentration 
Response to process limits 
(mg/L) 
Operating target (to be achieved for  0.85 
 
≥95%of the time that the treatment 
plant is producing water) 
Operating range (≥95% of the time  Within ± 0.15 of 
 
that the fluoridation plant is in 
operating target. 
operation) 
Upper action process limit  
1.3 
Immediate fluoride plant shut down 
(safeguards interlocked with the 
dosing system.) 
Emergency limit ( Maximum 
1.5 
Immediate fluoride plant shut down. 
Allowable Value, MAV)  
(Safeguards interlocked with the 
dosing system.) Notify Taumata Arowai, 
investigate the cause of the exceedance and 
take appropriate action. 
 
 
Plant Testing and Monitoring  
In addition to the automated fluoride dosing control, online monitoring and automated subsequent 
shutdown actions, the GPG requires that the items listed in Table 6— Record keeping requirements 
are also monitored.  
Refer to S-0273-G-WI-006 for a procedure for taking a manual sample for fluoride analysis.  
Refer to Table 6— Record keeping requirements for details of how results are to be recorded. 

SAFETY AND EMERGENCY PROCEDURES 
FSA is a toxic and corrosive liquid, operators should review and understand the SDS and receive 
specific training in the precautions, first aid procedures and safe handling for this product, and 
records of this training should be kept.  
A current SDS for FSA should be available to the operators (refer to Appendix B of this manual). 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 28  



 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
 
Emergency Procedures 
For Emergency Procedures, refer to Kawerau District Council’s document:  WTP – Emergency 
Response Procedure in Appendix  .  
 
Contact Information 
Contact information for emergency services and regulatory authorities is as follows: 
Contact 
Contact details  
Emergency Response – Fire / Police / Ambulance 
Tel 111 
Plant Designer – TRILITY solutions 
TRILITY  
Unit 4, 23 Tukorako Drive  
Spare Parts  - TRILITY Sales/ Service  
Mount Maunganui NZ 3116 
Tel: +64 7577 9988 
 
Chemical supplier  
IXOM 
166 Totara Street 
Mount Maunganui 3116 
Tel: 0800 222 277 
On call WTP Operator 
Glen Penny 
Tel: +64 27 292 0703 
NZ Ministry of Health 
Ministry of Health 
133 Molesworth Street 
Thorndon, Wellington 6011 
Tel: 0800 400 569 
Eg. Taumata Arowai, NZ Drinking Water Regulator 
Taumata Arowai 
Level 2/10 Brandon Street 
Wellington Central, Wellington 6011 
Tel: 04 889 8350 
10 
QUALITY CONTROL: 
To ensure that fluoride dosing / analysis always operates within guidelines and in a safe and 
effective manner,  there are three main aims of plant quality control, these are: 
•  to ensure the accuracy and reliability of fluoride dosing and monitoring. 
•  to verify and validate equipment performance. 
•  To implement corrective actions for addressing deviations from target fluoride levels.  
In the fluoridation plant these aims should be achieved by: 
•  Monitoring, recording and reviewing plant dosing data based on the verification calculations in 
the FUD. 
•  Regular calibration and maintenance of the dosing pumps 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 29  

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
•  Regular calibration of the fluoride analysers  
•  Regular laboratory testing of the fluoride level in the raw and treated water  
•  Logging and recording incidences of deviation of plant control outside of guideline values 
•  Obtaining and recording FSA concentration and analysis certificates from the vendor 
•  Maintaining plant equipment regularly and holding stock of essential plant spares  
•  Regular operator/ maintainer training / re- training.  
 
11 
RECORD KEEPING: 
The Water New Zealand Good Practice Guide - Fluoridation of Drinking Water Supplies outlines 
specific record-keeping requirements for drinking water suppliers. This section summarises those 
requirements:  
Table 6—Record Keeping Requirements 
Records to be kept:  
Suggested means of recording this: 
Fluoride Dosing Records: 
•  Record the amount of fluoride added to the water.  •  Data logging records ( Continuous data (minimum 5 
minute interval records) as/where required by the 
Drinking Water Quality Assurance Rules) of: 
•  Water Flow 
•  Online fluoride concentration 
•  FSA flow 
•  Manual records of FSA IBC receipts  
 
•  Maintain records of the fluoride compound used, 
•  Manual records of FSA IBC receipts  
including batch numbers and suppliers. Supplier to 
 
provide chemical analysis 
•  The drinking-water supplier must, at a minimum,  •  Data logs 
also record the following parameters at the 
frequencies indicated: 
•  The volume of water treated 
•  The quantity of fluoride added to the water (based 
on day tank or hopper and dose flow meter, 
where monitored) 
•  The stock of fluoride on hand 
•  The results of fluoride analysis of the samples of 
water taken from the treated water at the 
intervals required – on site and IANZ accredited 
samples 
•  Average fluoride concentration each day on the 
basis of the online analyser records  
•  Average fluoride concentration each day on the 
basis of the loss of mass or volume in the dosing 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 30  

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Records to be kept:  
Suggested means of recording this: 
tank  
•  A reconciliation of each of the independent checks 
(refer Safeguard D and Section 4.7.6) 
•  Note the date and time of fluoride addition. 
•  Data logging of control system data for fluoride 
pump operation  
Water Quality Monitoring: 
•  Regularly measure and record the fluoride 
•  Data logging on analyser results 
concentration in the treated water. 
•  Regular laboratory analyses  
•  Incorporate the Fluoride dosing into the suppliers’  •   
Drinking Water Safety Plan ( Ref GPG Vol 1 , Sect 
3.3) 
•  Document the frequency of monitoring and the 
•  Continuous monitoring for Fluoride levels at the 
methods used for testing. 
Fluoride Plant 
•  Daily testing for fluoride levels at 3 different sites 
across the district using a fluoride meter. Results 
are recorded in the Daily Monitoring Sheet and 
reported to Taumata Arowai monthly. 
Equipment Maintenance Logs: 
•  Keep detailed records of the maintenance and 
•  Fluoride analyser log sheet (example tba) 
calibration of equipment used for fluoride dosing 
•  Fluoride dosing pump calibration log sheet (example 
and monitoring. Include dates of inspections, 
tba) 
servicing, and any repairs carried out 
•  Fluoride Inspection log sheet (example tba) 
•  Fluoride Maintenance Logs – calibrations to be done 
monthly 
Operational Records: 
•  Record any deviations from standard operating 
 
procedures, including reasons and corrective 
actions taken. 
Refer to Fluoride Operational Logs 
•  Document any incidents or issues related to 
Refer to Fluoride Operational Logs 
fluoride dosing, including equipment malfunctions 
and quality control failures 
•  The operation of shutdown systems must be fully  Refer to Fluoride Operational Logs 
tested at least annually and the outcome of these 
tests recorded ( Ref GPG Vol 1 , Sect 4.7.7) 
•  Routine testing of critical alarms and corrective 
Fluoride Maintenance Logs – routine testing to be done 
actions and outcomes of the system shutdown 
monthly 
tests 
•  Surveillance monitoring and audits records 
Surveillance monitoring to be logged on the Fluoride 
Operational Logs 
Audit records to be kept in the KDC Shared Drive 
•  Log any control overrides ( Ref GPG Vol 1 , Sect 
Fluoride Operational Logs 
4.7.7) 
•  The drinking-water supplier should keep records 
Operational and Maintenance Logs are to be updated 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 31  

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
Records to be kept:  
Suggested means of recording this: 
verifying that the fluoride plant is managed and 
accordingly. 
operation accordance with the GPG ( Ref GPG Vol 
1 , Sect 6.5) 
The printed copy is to be verified and scanned monthly, 
to be kept in the KDC Shared Drive. 
Compliance Documentation: 
•  Maintain records of compliance with regulatory 
Compliance records are kept digitally in the KDC Shared 
requirements and guidelines. 
Drive, readily available for compliance officers and 
regulatory bodies. 
•  Include any communications with regulatory 
All communications with regulatory bodies, inspection 
bodies, inspection reports, and audit findings 
reports, and audit findings are found in the KDC 
Internal Shared Drive. 
Training Records: 
•  Keep records of training provided to staff involved  Records of FSA training  
in fluoride dosing and monitoring. Include dates, 
training content, and names of attendees 
Records of plant familiarisation and specific SOP 
training 
Public Communication: 
Document any public notices or communications  Copy of correspondence records are found in the KDC 
related to fluoride levels in drinking water 
Internal Shared Drive 
Keep a record of public inquiries and responses  Public enquiries can be lodged via email, phone or 
provided 
Antenno. Records of public enquiries and 
responses (as well as status, service request type, 
contact person and contact number, etc.) can be 
found on the KDC Datascape CRM. 
Annual reporting requirements: 
Refer to the GPG (Ref GPG Vol 1, Sect 7) 
Monthly reporting to Taumata Arowai are kept on the 
KDC Internal Shared Drive and submitted on the 
Hinekorako Website within the first ten days of the 
month. 
A copy of the reports is also provided to the water 
compliance auditors as part of the Annual Water Quality 
Audit. 
 
By adhering to these record-keeping practices, drinking water suppliers can ensure the safe and 
effective fluoridation of drinking water, while also maintaining compliance with regulatory standards 
and providing transparency to the public. 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 32  




 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
12 
STAFF TRAINING 
  Staff Qualifications  
The GPG recommends that “National Certificate in Water Treatment (Site Operator) - Level 4 (or 
equivalent), or preferably a National Diploma in Drinking Water - Water Treatment (Site Technician) 
- Level 5 (or equivalent) is recommended as a minimum qualification for operators of fluoridation 
plants” (refer to Vol 1 section 5.4).  
 
  Staff Training 
Staff must be trained in handling, precautions and emergency management for FSA, as well as the 
associated regulatory requirements for chemical handling. 
NZ GPG (Vol 1 section 5.4) requires that: 
“The drinking-water supplier must ensure that operational personnel (employees or contractors) are 
appropriately skilled and trained in the management and operation of the fluoridation plant, and that 
these competencies are maintained (and that this is documented in the Water Safety Plan). 
Operational personnel must have an adequate knowledge of the principles of fluoridation (including 
the risks), the type of plant or equipment and its operation and maintenance.” and  
“Operational personnel must have a sound knowledge base from which to make effective operational 
decisions. This requires training in the methods and skills required to perform tasks efficiently and 
competently. Operational personnel should be aware of the potential consequences of system 
failures, and how decisions made can affect the safety of the scheme.” 
  Procedure for Documenting Staff Training  
Staff training are to be logged on the Staff Training Log Sheet – noting any expiration date of the 
training so the staff can be booked for a refresher training 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 33  


 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
 
Figure 3 – Example KDC Staff Training Log Sheet 
13 
REVIEW AND UPDATE PROCEDURES FOR THIS MANUAL 
 The NZ GPG recommends that this operating and maintenance manual is regularly reviewed, it is 
the responsibility of KDC to see that this is implemented. TRILITY recommend that it is reviewed 
after commissioning, and at regular intervals thereafter (eg. annually), or more frequently if it is 
apparent that it is not suitable for facilitating meeting the objectives of KDC’ obligation to maintain 
consistent and effective operation of the fluoridation systems, maintain compliance with regulatory 
standards, and safeguard public health. 
This manual should also be reviewed if the relevant legislation or guidelines are updated, OR if new 
items of equipment are incorporated into the plant.  
The latest version of the FSA SDS should also be kept with this manual.  
 
 
 
 
 
 
 
 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
Page 34  

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
APPENDIX A—FLUORIDATION PLANT FUNCTIONAL CONTROL DESCRIPTION 
 
 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
APPENDIX B—IXOM FLUOROSILIC ACID SAFETY DATA SHEET 
 
 
 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
APPENDIX C—STANDARD OPERATING PROCEDURES 
 
 
 
 
 
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
 

 
 
 
Kawerau WTP Fluoridation Operating and Maintenance Manual 
S-0273 Kawerau Fluoridation Project 
APPENDIX D—VENDOR EQUIPMENT DATA SHEETS AND OPERATION AND 
MAINTENANCE MANUALS 
 
 
-   
 
All copies of this document are uncontrolled.  
 
Copyright of this document is the property of TRILITY. 
 
S-0273-G-MAN-001_1 
 

Document Outline