7 May 2026  
 
 
 
 
 
 
 
 
             Ref: 21043 
 
 
Harwood Wilson 
[FYI request #32594 email]  
 
 
Tēnā koe Harwood 
 
Thank you for your request of 4 March 2026 to Fire and Emergency New Zealand requesting 
information in relation to the MAN Angloco Type 3 build trucks.  
 
In line with our obligations to make and communicate our decision to you within the statutory 
timeframe, we wrote to you on 17 April 2026 providing our decision and outlining that we decided 
to grant your request and would release the remaining information requested without undue 
delay. Thank you for your patience and please see our response to your request below. 
 
1.  How many of these trucks have undergone fleet specification testings so far? 
 
We have interpreted this question to be referring to acceptance testing. We can confirm that 21 of 
the 28 production MAN Angloco Type 3 appliances have undergone some acceptance testing. 
 
Undergone acceptance testing 
Awaiting acceptance testing 
21 

Please note: this does not include the prototype MAN Angloco Type 3 
 
2.  What issues have been identified that are causing delays in these being released to 
brigades? and what is being done to fix them? if no issues then please explain reasons for 
the delay. 

 
The activities required before the appliances go into operational service had not been scheduled 
at the time of our initial response. These have now been scheduled for 17 of the 29 MAN Angloco 
appliances (this includes the one prototype and the 28 production trucks) which has taken longer 
than previously anticipated in early October. The remaining 12 appliances have been delayed due 
to commercial issues. 
 
Scheduled for operational release 
Delayed due to commercial issues 
17 
12 
Please note: this does not include the prototype MAN Angloco Type 3 
 
 
 



 
 
Before these appliances are introduced into operational service, any items found during 
acceptance testing need to be rectified. A number of other works need to be completed including 
service provider and brigade training, applying signage, servicing, ICT fit out, locker equipment 
adaptations and fit out. Once all of these are completed, the appliances will go into service. 
 
3.  Have FENZ delayed delivering these trucks to stations due to Industrial Action for any 
reason? if so please give detail. 
 
There have been no delays in delivering these trucks to stations due to industrial action. 
 
4.  What is the current expected completion date (i.e. responding to calls) for all these trucks? 
 
The first 16 of these trucks are expected to be completed by the end of June 2026. The timeframe 
for the rest is to be determined. 
 
5.  Please provide any communications between the Chief Executive TEAM and Fleet Team for 
January and February 2026 regarding the these trucks. 
 
Please find attached, as the Appendix to this response, the correspondence between the Chief 
Executive team and Fleet team for January and February 2026 regarding the 28 new Type 3 MAN 
Angloco appliances. As outlined in our decision letter, some information has been withheld under 
the following: 
 
•  section 9(2)(a) of the OIA, to protect the privacy of natural persons 
 
•  9(2)(ba)(i), to protect information which is subject to an obligation of confidence or which 
any person has been or could be compelled to provide under the authority of any 
enactment, where the making available of the information would be likely to prejudice the 
supply of similar information, or information from the same source, and it is in the public 
interest that such information should continue to be supplied 
 
•  section 9(2)(b)(ii) of the OIA, to protect information where the making available of the 
information would be likely unreasonably to prejudice the commercial position of the 
person who supplied or who is the subject of the information 
 
•  section 9(2)(h) of the OIA, to maintain legal professional privilege; and 
 
•  section 9(2)(j) of the OIA, to enable a Minister of the Crown or any public service agency or 
organisation holding the information to carry on, without prejudice or disadvantage, 
negotiations (including commercial and industrial negotiations). 
 
We trust that the information being provided is of assistance. If you require further information, 
please email [FENZ request email]  
 