This is an HTML version of an attachment to the Official Information request 'Early termination of a significant public contract'.


CONFIDENTIAL - For Internal Use Only 
Chief Executive's Leadership Group
Paper no: 
X.X Advisor to insert
Meeting date: 
27 November 2024 
Paper author: 
s 9(2)(a)
@kaingaora.govt.nz 
Director Infrastructure and Civil Construction (Acting) 
ACT 1982
s 9(2)(a)
Business Group: 
Urban Development and Delivery 
Title: 
CONFIDENTIAL - Auckland LSPs Infrastructure Update 
INFORMATION
RELEASED UNDER THE 
OFFICIAL 
1 



CONFIDENTIAL - For Internal Use Only 
 
Purpose 
1.  This paper outlines the decision to transition away from using the LEAD Al iance in the Auckland Large-Scale Projects. It is being brought to the Chief 
Executive’s Leadership Group for noting before being presented to Kāinga Ora Investment and Delivery Committee (IDC) for endorsement. 
1982
Recommendations 
THE 
2.  It is recommended that The Chief Executive’s Leadership Group (CELG): 
a)  note that LEAD Alliance was initially procured and set up in 2018 to deliver a programme of works in the Auckland Large-Scale Projects (LSPs) that 
ACT 
was planned, but not fully funded; 
b)  note that the brief for the alliance in 2018 was ‘scale and pace’ and this worked well for a fast start and a very high volume of work to follow, 
delivering more than $600m of works and enabling 4,000 homes between 2018 – 2022; 
UNDER 
c)  note that the alliance model has provided flexibility as the scope and definition of the multi-year LSP programme evolved, including managing the 
Covid-19 disruption very well and ensuring resourcing availability during a constrained market; 
d)  note that as the alliance matured, the programme cost and performance was not in alignment with Kāinga Ora expectations, and in 2023 Kāinga 
Ora managed a significant reset process to increase the alliance’s productivity and value proposition, with a focus on programme, cost 
performance and quality. Following this reset the alliance contract was extended for a period of five years; 
e)  note that, while the reset was successful and the alliance is stable and performing well with consistent and predictable costs to complete, Kāinga 
Ora Urban Development and Delivery (UDD) has determined that LEAD Alliance does not deliver the value we require given the high programme 
INFORMATION 
nature, and therefore the alliance model no longer suits our current needs; 
RELEASED 
f)  note that the Alliance Agreement and contract extension does not commit Kāinga Ora to using the alliance for work in our Auckland and Porirua 
LSPs as sole Owner-Participant of the alliance, Kāinga Ora UDD has the authority to wind down the alliance at any time; 
g)  note that the process of transitioning away from using LEAD Al iance is expected to take up to 6 months with committed projects completed for 
design and construction;    OFFICIAL 
 
2 



CONFIDENTIAL - For Internal Use Only 
 
h)  note that UDD is currently assessing options for civils delivery and may engage with the civil construction industry in order to inform a 
procurement plan; and 
i)  note that the next steps are for UDD management to inform the Programme Alliance Board (PAB), whose members represent the participant 
companies of the alliance. Following this, a paper will be prepared for the Kāinga Ora Investment and Delivery Committee for noting, and the 
1982
office of the Minister of Housing wil  also be informed of the decision. UDD wil  report back to CELG on the transition and procurement plan by 
March 2025. 
THE 
Background 
ACT 
3.  The LEAD Alliance (formerly Piritahi Alliance) was established in 2018 to help with the coordination of the consent, design and delivery of the civil 
infrastructure required to enable additional housing for the Auckland LSPs, at the time known as the Auckland Housing Programme. 
4.  LEAD Al iance consists of one owner-participant, Kāinga Ora, and five non-owner participants: civil designers Tonkin + Taylor, Harrison Grierson and 
Woods, and civil constructors Hick Bros and Dempsey Wood. 
UNDER 
5.  It was contracted by HLC (the urban development subsidiary of Housing New Zealand) through an Auckland Civils Alliance Programme Agreement 
(ACAPA) for an initial term of five years, from December 2018-2023. 
6.  The use of alliancing in programme delivery (rather than project-specific delivery) was an innovation for land development. Furthermore, none of the 
companies had been involved in an al iance programme of the scale that was on the table. By focusing on construction and design companies that 
occupy the industry’s ‘second-tier’, HLC sought to grow the overall sector capability and capacity. 
7.  The alliance also worked well for a fast start and a very high volume of work, which total ed more than $600m and enabled 4,000 homes between 
INFORMATION 
2018 – 2022. It was instrumental in retaining community support throughout the long development timelines, despite the very high work volumes and 
disruption. 
RELEASED 
8.  The alliance had delivered a significant amount of infrastructure, but had not been focused enough on the basics of project delivery, including efficient 
processes and systems. As the contract term was closing, Kāinga Ora was to consider whether or not to extend the contract for a further five years. 
OFFICIAL 
 
3 



CONFIDENTIAL - For Internal Use Only 
 
9.  At the time, the projection for LEAD Alliance’s deliverables over the five years of the contract extension period (December 2023 – December 2028), 
being land for 6,000 homes and up to $1b of works, was based on the Cabinet-approved Programme Business Cases for Mangere, Roskill and Tāmaki 
Large-Scale Projects (LSPs), and the remaining work in Northcote and Oranga. 
10. Kāinga Ora UDD entered into contract renewal negotiations with LEAD Al iance in November 2022, with Kāinga Ora managing a rigorous review and 
1982
reset process of the Alliance. This approach was supported by the Kāinga Ora Board and the Construction Programme Assurance Panel (CPAP). The 
reset focused on cost management and programme performance, as well as alliance systems and processes. It included a complete overhaul of senior 
THE 
leadership and directors, new KRA and KPI frameworks, a strategic review and significant training and upskilling, both for alliance personnel and Kāinga 
Ora staff. This work resulted in a five-year extension to the al iance contract, signed in December 2023.   
ACT 
11. It is worth noting that UDD has previously undertaken to wind down the Te Aranga Al iance in the Porirua LSP because the remaining works 
programme for Eastern Porirua no longer justified an alliance delivery model, due to the low complexity and reduced programme scale. UDD has 
successful y managed a transition process for this in 2023. 
UNDER 
Discussion 
12. During a period of a very constrained labour market (particularly during Covid-19), one of the efficiencies of LEAD Alliance was in keeping the labour of 
both civil designers and constructors together. As these constraints have softened and industry growth builds, this efficiency within the al iance model 
is no longer demonstrable. 
13. The Al iance was set up on the basis of a volume of work expected to be more than $200m per year. This programme of work has been reduced and 
neighbourhoods / stages have been pushed out due to funding decisions made to the original approved funding envelope.  
INFORMATION 
14. The remaining design and construction work within the funded LSP programme yet to be delivered is approximately $950m. We are currently on 
budget and broadly on programme, although this is starting to fal  behind as our approvals for future neighbourhoods are delayed. 
RELEASED 
15. Due to the programme of work reducing, and project delivery moving out, this has resulted in a higher overhead cost to project delivery. UDD 
management has identified that it wil  be more cost-effective to deliver the remaining programme under other delivery models. 
16. We anticipate savings of $18m per year for the alliance, with expected savings over the remaining funded programme of $90m - $100m. 
OFFICIAL 
 
4 



CONFIDENTIAL - For Internal Use Only 
 
17. The ACAPA reserves the right for Kāinga Ora to not put all work in the LSP programme through the alliance, and reserves the right to terminate the 
contract at any stage. 
18. UDD estimates that the process of transitioning away from an al iance model wil  take up to 6 months, with a further two years to close out Project 
Quality assurance. This can be managed by the UDD team with limited support from the current partners in the LEAD Al iance. We also have internal 
1982
resource and expertise to manage procurement and delivery within UDD. 
19. Alongside the agreed projects allocated to LEAD Alliance, Kāinga Ora UDD has continued exploring and implementing alternative best-for-project 
THE 
decisions in its Auckland LSPs and greenfield projects, and in some instances has used a conventional 3910 construction contract (the most commonly 
used contract for building and civil engineering construction) where appropriate. 
ACT 
20.  As new design and construction projects emerge during this transition period, UDD wil  take a tailored approach to the delivery of these civils. Kāinga 
Ora already has panels for civil partners, and UDD wil  use these panels (and add to the panels) as needed. UDD will also engage with the civil 
construction industry to inform a procurement plan.   
UNDER 
21. Kāinga Ora, as the client and owner-participant, owns the project-specific intel ectual property and wil  continue to use lessons learned from the 
alliance to inform future decisions around the design and delivery of civil infrastructure.   
22. A transition team will be put in place to manage the transition of work away from the alliance. s 9(2)(a)
Director Infrastructure and Civil 
Construction, wil  lead this team and focus on the most cost-effective and efficient plan to close out the remaining work in the Alliance. We will report 
back to IDC with an update by March 2025. 
Risks and their Treatments 
INFORMATION 
 
RELEASED 
Type 
Risk/Issue 
Causes (s) 
Consequence (s) 
Control ed 
Risk Treatment 
Risk Owner 
Risk Rating 
Risk 
Costs incurred 
Breaking lease term 
Up to $1m 
Medium (6-
The transition team wil  work with the  s 9(2)(a)
for lease of 
payable per year  15) 
landlord on an exit option, and look 
alliance office 
for lease 
for other government projects that 
after it ceases 
may require a project office 
OFFICIAL 
 
5 



CONFIDENTIAL - For Internal Use Only 
 
Issue  Issue of alliance  Poor messaging and 
Aggrieved 
Low (1-5) 
Comms plan with key messages that  s 9(2)(a)
closure closely 
communications 
alliance partners, 
note that the contract extension was 
following 
media coverage 
based on funded programmes that 
publicised 
have since been reduced. 
contract 
1982
extension and 
reset process 
THE 
Risk 
Delivery 
Assumption that investment in 
OIA requests, 
Low (1-5) 
Comms plan which notes that the 
Transformation  LEAD participating in pilot 
media coverage 
pilot work wil  be used by UDD to 
ACT 
investment 
programme is wasteful spending 
inform how to improve management 
and deliver civils work outside of the 
alliance. We note that UDD has 
undertaken a similar plan for the 
UNDER  closure of the Te Aranga Alliance in 
Porirua. 
Next Steps 
23. The next steps are to inform the LEAD Alliance Programme Alliance Board (PAB) members of the decision, and then a noting paper wil  be prepared for 
the Kāinga Ora Investment and Delivery Committee. The office of the Minister of Housing will also be informed of the decision.  
24. Kāinga Ora UDD will develop and implement a plan to communicate the announcement. The expectation is that al  stakeholders are informed by 
INFORMATION 
Monday 9 December 2024. 
RELEASED 
25. UDD wil  report back to IDC with a transition plan by March 2025. 
OFFICIAL 
 
6 

Document Outline