This is an HTML version of an attachment to the Official Information request 'Exotic Caulerpa Science'.
link to page 2 link to page 2 link to page 2 link to page 5 link to page 8 link to page 10 link to page 10 link to page 11 link to page 11 link to page 12 link to page 12 link to page 13 link to page 13 link to page 14 link to page 15 link to page 16 link to page 16 link to page 17 OMAKIWI SUCTION DREDGING TRIAL 
 
Interim progress report for Phase II 
Northland Regional Council & Cawthron Institute, 2024 
 
Table of Contents 
 
 
1. Introduction ....................................................................................................................... 2 
2. Mechanical suction dredging .............................................................................................. 2 

2.1. Modifications made for, and during, Phase II ............................................................. 2 
2.2. Phase II dredging activity .......................................................................................... 5 
3. Diver-operated suction dredging ......................................................................................... 8 
4. Monitoring ........................................................................................................................ 10 
4.1. Turbidity ................................................................................................................. 10 
4.2. Dredged material.................................................................................................... 11 
4.3. Percent cover of exotic Caulerpa ............................................................................ 11 
4.4. Ecological monitoring ............................................................................................. 12 
4.5. Delimitation surveys ............................................................................................... 12 

5. Phase II observations ....................................................................................................... 13 
5.1. Operational capacity .............................................................................................. 13 
5.2. Mechanical dredge efficiency ................................................................................. 14 
5.3. Diver-operated dredge efficiency ............................................................................ 15 
5.4. Ongoing challenges ................................................................................................ 16 
Acknowledgements ............................................................................................................. 16 
References .......................................................................................................................... 17 
 
 
 
 
 

1. Introduction 
Exotic Caulerpa (Caulerpa brachypus and Caulerpa parvifolia) was identified in Te Rāwhiti Inlet, 
Bay of Islands, in May 2023. An incursion response for Northland was initiated, the focus of 
which was development of methods and technologies to remove exotic Caulerpa biomass. 
Omakiwi Cove was selected as the study site for this trial as dense meadows of exotic Caulerpa 
are present there. A mechanical suction dredge was developed by Johnson Bros Ltd. (JBL) and 
deployed in Omakiwi Cove in February 2024, where it remained until April 2024. During this time 
(‘Phase I’) the dredging equipment was tested, and repairs and improvements were made. 
Concurrently, scientific research was undertaken to document and evaluate the efficacy and 
suitability of suction dredging as a removal technology. All dredging and monitoring activities 
undertaken for Phase I are reported fully in Davidson et al. (2024). 
By the end of Phase I (9 April) almost 2,000 m2 had been dredged and high levels of removal from 
treated areas had been achieved. However, hurdles to suction dredging as an effective removal 
technology remained; long stand down periods were required to de-water and securely dispose 
of all dredged material and, despite significant rates of removal in dredged areas, some exotic 
Caulerpa remained. Intentions for the next phase of the trial (‘Phase II’) include installation and 
assessment of a system to separate dredged material, and identification of an effective and 
efficient method for removing remnant exotic Caulerpa. Scientific monitoring will also continue, 
to support and monitor dredge activity. 
The intention of this document is to provide a brief interim report of work undertaken to date as 
part of Phase II of the suction dredge trial (29 April to 16 June), and to note some initial 
observations and considerations that have arisen during this time. It is not the intention of this 
document to discuss results or findings of Phase II; these will be detailed in a full report written 
upon completion of Phase II.  
 
2. Mechanical suction dredging  
2.1. Modifications made for, and during, Phase II 
Installation of trommels 
The barge underwent a full biosecurity inspection following completion of Phase I (9 April), then 
returned to Ōpua Marina where a trommel system was installed onto the deck of the barge (Fig. 
1A). This system separates dredged material, enabling sediment to be returned to the seafloor 
(Fig. 1B) and exotic Caulerpa to be retained onboard (Fig. 1C). This modification negates the 
time-consuming requirement to collect and dispose of all dredged material which, during Phase 

 




I, necessitated long stand-down periods while the collection bags de-watered and the barge 
was grounded to offload dredged material. This work was completed by 26 April and the barge 
relocated back to Omakiwi Cove on 29 April. Upon relocation the new system was tested and 
refined (e.g., altering water pressure and angle of spray bars) and was found to successfully 
separate fine sediment (silt, mud, sand) from larger material (exotic Caulerpa, shell fragments). 
A secondary vessel was employed to transport one-tonne bags of dredged material ashore, 
while the primary barge was able to continue dredging. 
 
 
(A) 
(B) 
(C) 
 
Figure 1. A new trommel system was installed prior to commencing Phase II of the suction dredging trial. (A) The 
trommels separate fine sediment from exotic Caulerpa. (B) Sediment is returned to the seafloor. (C) Exotic Caulerpa is 
retained onboard in dewatering bags. Photos: NRC.  
 

 




Deposition of dredge spoil 
The separation of dredged material requires sediment to be returned to the seafloor via ‘stinger 
pipes’. At shallow depths these pipes fold, preventing sediment deposition. A mechanical 
method of adjusting the pipe length was suggested by JBL, in addition to integrating a 
positioning system to enable precise deposition of dredge spoil into previously dredged areas. 
Modifications of this system are ongoing. 
 
Installation of moorings 
Dredge activity in Phase II was impacted by adverse weather conditions. On several occasions 
the barge was unable to remain in Omakiwi Cove, which necessitated moving it to a secure 
mooring in Waipiro Bay (south of Omakiwi, within the Controlled Area Notice zone). Moving the 
barge out of Omakiwi required a biosecurity inspection of the hull by NRC divers (Fig. 2A, B) and 
full decontamination of all dredging equipment (Fig. 2C) to ensure adherence with biosecurity 
conditions and procedures (see Davidson et al. (2024) Appendix 1). Hull inspections revealed 
exotic Caulerpa fragments entangled in biofouling, which were removed by hand before the 
vessel was given clearance to move. This time-consuming process will be circumvented by 
application for, and subsequent installation of, two temporary moorings in Omakiwi. The barge 
will then be able to remain safely in Omakiwi during periods of adverse weather. 
 
(A) 
(B) 
(C) 
 
Figure 2. Inspection and decontamination procedures required to enable the barge to move from Omakiwi Cove in the 
event of bad weather. (A) A diver inspects the hull of the barge. (B) Exotic Caulerpa fragments were found entangled in 
biofouling on the hull. (C) All dredge equipment was decontaminated prior to moving the barge. Photos: NRC. 
 
 
Equipment repairs 
Toward the end of Phase I, a 700mm length of reinforcing bar was dredged up and caused 
damage to the dredge head and pump (9 April). The dredging equipment was still operational, 
albeit at a reduced capacity. Divers from NRC undertook several search dives, using a metal 
detector, to locate and remove any remaining rebar. Replacement brushes and shafts were later 
fitted onto the dredge head and subsequent testing of the new equipment was undertaken (22 - 
26 May).  

 

Data reporting 
During Phase I, GPS data was not readily available to reliably map or measure the area targeted 
by the suction dredge. Instead, dredged areas were mapped by divers using surface markers to 
signal the location of dredged patches. During Phase II, JBL were able to provide daily GeoTIFF 
files taken from the dredge. The GeoTIFF format embeds geospatial metadata into image files so 
that they can be used in GIS applications such as the Caulerpa Infestation Dashboard. The 
GeoTIFF files are processed in ArcGis so the area dredged can be calculated and displayed. 
 
2.2. Phase II dredging activity 
Dredging 
During the initial part of Phase II (29 April to 16 June), 21 days of dredging were undertaken, 
resulting in a total area dredged of 11,856 m2 and 226 one-tonne bags offloaded (Fig. 3; Table 1). 
Dredging activity during this time can be divided into three distinct phases. From 29 April to 2 
May, the new trommel system was tested. From 3 May to 20 May the dredge operated in Zone 
DRG with a primary focus of connecting and expanding the test patches conducted during 
Phase I (Fig. 3). This style of dredging somewhat constrained dredge operations as frequent 
lifting and repositioning of the dredge head was required to work around the areas already 
dredged. From 27 May onwards, the dredge was fully operational in Zone B. During this time, 
using the days for which data is available (11 days; Table 1), the average rate of removal was 
1,013 m2 per day, or 154.85 m2 per hour.  
 
Offloading 
The offloading procedure in Phase II was made significantly more efficient via the use of a 
supplementary barge to ferry one-tonne bags ashore, meaning the primary dredging barge was 
able to continue working. The supplementary barge was grounded at high water and, once the 
tide receded, the one-tonne bags were craned off and transported to the on-land disposal site 
on small tipper trucks. This process took approximately two hours each time and was carried 
out on 10 May (50 bags), 1 June (68 bags), and 11 June (58 bags). The disposal site was 
inspected by NRC compliance officers (6 May) and was found to be in good condition. 
 
Stand-downs 
The barge is unable to operate in wind above 30-35 knots from the west, southwest, or 
northwest. Consequently, several stand-down days / periods of days have been required during 
Phase II as a result of adverse weather conditions (Table 1). In some instances, the barge had to 
be re-located offsite to shelter and wait for the weather to pass, resulting in multiple days of no 
dredging. 

 


 
 
Figure 3. Area dredged by the mechanical suction dredge (indicated in grey) during the initial part of Phase II (29 April to 13 June). Dredging activity in Zone B is coloured according to each 
days’ dredging, with the darkest shade of grey indicating the earliest dredging activity during that day and the lightest shade indicating later dredging. The different shades in Zone DRG 
represent different days of dredging.  

 

Table 1. Mechanical suction dredging undertaken during the initial part of Phase II (29 April to 16 June). Dredging activity 
is divided between two distinct phases; connecting test patches in Zone DGR, and full operational dredging in Zone B. 
Days on which no dredging occurred are omitted. Note – days that NRC did not receive an update from JBL have been 
left blank. 
 
Date 
Area dredged (m2) 
Quantity dredged (bags) [1] 
Time dredged (h:m) 
Dredge rate (m2/hour) 
Zone DGR 
3 May 
 
4 May 
 
16 
2:00 
 
5 May 
No dredging - Sunday 
6 May 
 
 
 
 
7 May 
 
8 May 
705 
30 
6:30 
108 
9 May 
 

6:10 
 
10 May 
 
15 
5:50 
 
11 May 
 
 
7:00 
 
12 May 
No dredging - Sunday 
13 May 
 
18 
7:15 
 
14 May 
 
21 
7:15 
 
15 May 
No dredging - weather 
16 May 
No dredging - weather 
17 May 
No dredging - weather 
18 May 
No dredging - weekend 
19 May 
No dredging - weekend 
20 May 
 
21 May 
No dredging - hull inspection prior to relocating for weather 
22 May 
No dredging - weather, maintenance 
23 May 
No dredging - maintenance 
24 May 
No dredging - maintenance 
25 May 
No dredging - maintenance 
26 May 
Not fully operational - testing new shafts and brushes 
Zone B 
27 May 
600 
 
7:00 
86 
28 May 
1,110 
14 
8:50 
126 
29 May 
No dredging - weather 
30 May 
 
 
 
 
31 May 
 
 
 
 
1 June 
775 

4:40 
166 
2 June 
No dredging - Sunday 
3 June 
 
 
 
 
4 June 
1,360 

6:40 
204 
5 June 
1,350 

5:25 
249 
6 June 
1,046 

6:30 
161 
7 June 
1,240 
11 
9:30 
131 
8 June 
No dredging 
9 June 
No dredging 
10 June 
1,300 
21 
6:00 
217 
11 June 
1,302 
18 
4:24 
296 
12 June 
792 
11 
7:50 
101 
13 June 
276 
11 
4:40 
57 
14 June 
No dredging 
 
 
 
15 June 
No dredging 
 
 
 
16 June 
No dredging 
 
 
 
 
 [1] The weight of one full bag was found to be 1.4 tonne, however this does not necessarily equate to 1.4 tonnes of exotic 
Caulerpa. Other dredged material is present within the bags (e.g. large shell fragments), in addition to water weight.  

 


 
(A) 
(B) 
(C) 
(D) 
 
Figure 4. Area dredged by the mechanical suction dredge over three days during the initial part of Phase II. (A) 27 May. (B) 
28 May. (C) 31 May. (D) Three days combined; 27 to 31 May. 
 
 
 

3. Diver-operated suction dredging 
During Phase I, remnant exotic Caulerpa was observed in dredged areas. This resulted from the 
bulldozing effect of the dredge head creating mounds of exotic Caulerpa on the edges of 
dredged areas, and patches of unattached exotic Caulerpa moving into dredged areas. This was 
identified as a significant challenge to be addressed during Phase II (Davidson et al. 2024).  
During Phase II, Commercial Dive Specialists (CDS) were contracted to undertake diver-
operated suction dredging to support the mechanical suction dredge operations by targeting 
patches of exotic Caulerpa that had either been missed by the mechanical dredge or had moved 
into the dredged area afterwards (Fig. 5A). The diver-operated suction dredge feeds exotic 
Caulerpa into a filter cage on the surface (Fig. 5B). Large material (exotic Caulerpa, shell 
fragments) is retained in the cage, while smaller material (sand, silt) filters out and returns to the 
seabed. When the cage is filled to a quarter of its capacity it is taken ashore and the material is 
disposed on land. 
 

 



(A) 
(B) 
 
Figure 5. Diver-operated suction dredging was trialled during Phase II to address patches of remnant exotic Caulerpa. (A) 
A drone photo illustrates patches of exotic Caulerpa left within a dredged area. (B) The filter cage used by Commercial 
Dive Specialists Ltd. Photos: MES and CDS. 
 
 
As of June 16, approximately 775.1 m2 had been dredged via diver-operated suction dredging, 
with approximately 420 kg of dredged material removed (values exclude unknown metrics from 
11 June; Table 2). Diver operations were able to cover, on average, 155.02 m2 per day, or 33.05 
m2 per hour, however this was highly variable. The operation rate was influenced by the density 
of exotic Caulerpa; in areas where it is sparse, a larger area was able to be covered, however 
divers frequently encountered dense patches which slowed the dredging operations. On one 
occasion the pump mechanism was blocked entirely by a large patch. Subsequently, any 
patches encountered that were considered too large for the diver-operated dredge were marked 
for removal at a later date, either by the mechanical dredge or benthic matting. 
 
 
Table 2. Diver-operated suction dredging activity undertaken during the initial part of Phase I . 
 
Date 
Area dredged (m2) 
Approx. quantity 
Time dredged 
Dredge rate 
Dredge rate 
dredged (kg)  
(h:m) 
(kg/hour) 
(m2/hour) 
10 June 
Testing pump, not fully operational 
11 June 
Unknown 
Unknown 
4:40 
Unknown 
Unknown 
12 June 
50.6 
120 
4:49 
24.92 
10.51 
13 June 
110 
30 
5:09 
5.83 
21.36 
14 June 
51.5 
120 
3:09 
38.1 
16.35 
15 June 
196 
75 
5:00 
15 
39.2 
16 June 
367 
75 
4:43 
15.89 
77.82 
 
 

 


 
Figure 6. Area dredged by the diver-operated suction dredge (indicated in blue) during the initial part of Phase I  (29 April 
to 16 June). In Zone DRG, the black and dark grey shaded areas indicate dredging activity undertaken during Phase I, and 
the white shaded areas indicate dredging undertaken in Phase II. In Zone B, dredging activity is coloured according to 
each days’ dredging, with the darkest shade of grey indicating the earliest dredging activity and the lightest shade 
indicating later dredging activity. 
 
 
 
4. Monitoring 
4.1. Turbidity 
 
Following the modification of the dredging process there was potential for increased turbidity 
resulting from the return of sediment to the seafloor instead of collecting and disposing it on 
land. Compliance Officers from NRC conducted a site visit on 6 May to assess adherence of the 
new dredging system to conditions of the permit issued to discharge dredge spoil to the seabed. 
The evaluation revealed full compliance; a sediment plume was discernible only <20 m from the 
dredge operation, and monitoring by Secchi disk at 150 m from the dredge operation was also 
compliant. A later turbidity survey undertaken by Maxwell Ecological Services Ltd. on 6 June 
indicated a more significant sediment plume than had been observed previously (Fig. 7), 
however this was still within the 300 m compliance radius (Fig. 7 insert). It is thought the 
increased turbidity resulted from problems with the stinger pipes that deliver sediment back to 
the seabed. Modifications are ongoing. See Davidson et al. (2024) for details of resource 
consent conditions and compliance monitoring methods.   
10 
 



 
Figure 7. Sediment plume observed on 6 June. Insert: Turbidity monitoring results. Photo: MES. 
 
 

4.2. Dredged material 
 
During initial testing of the new trommel system, dredged material was sampled by Cawthron (3 
May). The larger material collected by the trommel was found to consist of exotic Caulerpa and 
broken shell fragments. The material destined to be returned to the seafloor was also sampled 
to determine presence of viable exotic Caulerpa. A 500 L sample of this material was sieved to 
1 mm and found to consist mostly of fine sediments (silt, sand). Eight small (<5 mm) exotic 
Caulerpa fragments were found within this sieved material.  
 
 
4.3. Percent cover of exotic Caulerpa 
 
Divers from Cawthron conducted pre- and post-dredge monitoring within defined zones where 
dredging operations were scheduled to be undertaken. This work commenced on 30 April with a 
karakia, with the first phase of diving completed on 17 May 2024. Surveys were conducted in 
10 x 2 m plots randomly distributed across six zones. In total, 56 pre-dredge plots and 17 post-
dredge plots were completed during the first phase of dive assessments. Within plots, census-
style (whole-plot) surveys measuring exotic Caulerpa cover were completed. Divers swum the 
full length of the 10 m transect recording data for each 1 m2 grid cell either side of the transect 
(i.e. 20 grid cells per plot). Quadrats (0.5 m x 0.5 m) were also used as a finer-scale assessment 
of exotic Caulerpa cover within treatment plots. Five quadrats were haphazardly placed within 
each 10 x 2 m plot (n = 365) and were assessed for percentage cover of surface (attached) and 
free-floating exotic Caulerpa. Perspex cores (6 cm) were also used to gauge the depth of exotic 
Caulerpa stolons and make substrate observations. See Davidson et al. (2024) for full 
methodology.  
11 
 

4.4. Ecological monitoring 
 
Divers collected epibiota and infauna data from within the 10 x 2 m transect plots discussed 
above. For each quadrat, the presence of native seaweeds and epifauna abundance and 
diversity were recorded. These data were recorded at a broad taxonomic level of functional 
groups (crabs, other crustaceans, anemones, echinoderms, bivalves, other molluscs, sponges, 
and polychaetes). Divers also collected five replicate 10 cm diameter cores (to a depth of 10 
cm) from within each plot (n = 352). Core samples were sieved to 1 mm and infauna abundance 
and diversity at a broad taxonomic level recorded. These methods provided an insight into 
ecological communities present prior to dredging and were repeated after dredging had 
occurred to quantify any ecological impacts on non-target species. See Davidson et al. (2024) 
for full methodology. 
 
 

4.5. Delimitation surveys 
 
A wider surveillance project was undertaken between 15 April and 16 May 2024 to monitor the 
spatial extent of exotic Caulerpa beyond Omakiwi Cove. Twenty-five harbours and bays and 19 
islands/island groups within the Northland region were surveyed by CDS, following a 
standardised search method. An infestation was found in one location; the south side of 
Poroporo Island (Fig. 8A, B). Benthic matting and chlorine tablets were applied to treat this 
infestation (Fig. 8C, D). See Northland Regional Council (2024a, b) for methodology and results.  
 
 
 
 
 
 
 
 
12 
 






 
(A) 
 
  (B) 
(C) 
(D) 
 
 
 
 
 
 
 
 
Figure 8. (A) Wider surveillance outside of Omākiwi Cove identified an infestation on the southern side of Poroporo 
Island. Insert: Poroporo Island is situated in Te Rāwhiti Inlet, within the Controlled Area Notice zone. (B) Exotic Caulerpa 
at Poroporo Island. (C) Infestations were treated with benthic mats and chlorine. (D) Mortality of exotic Caulerpa 
following treatment. Photos: NRC. 
 
 
 

5. Phase II observations 
 
The following are interim observations only. 
 
5.1. Operational capacity 
There has been a notable increase in the operational capacity of the mechanical suction dredge 
during Phase II, as evidenced by the area and quantity dredged per day. During Phase I, each 
one to two minutes of dredging necessitated a stand-down period of approximately 45 minutes 
13 
 

to allow for the collection bag to dewater. Additionally, the disposal of this material required the 
barge to be grounded for extended periods. 
In Phase II, modifications such as the installation of trommels and the use of a support barge to 
transport dredge material ashore have eliminated these requirements. Although operations 
during the initial days of Phase II were somewhat constrained due to the style of dredging 
(focused on connecting Phase I test patches), the later part of Phase II (from 27 May onward) 
saw more uniform dredge sweeps, leading to increased operational capacity. 
During this period, for the days where data is available (11 days; see Table 1), the average rate of 
removal was 1,013 m² per day. To date, the total area dredged in Phase II is 11,856 m², a 
significant improvement from Phase I, where the total area dredged was 1,998.8 m². 
The desired aim of the trial was to achieve clearance of spatial scales of over a hectare per day, 
and we acknowledge that we are still a long way off from achieving this outcome. To meet the 
expectations of our communities and hapu partners, further advancements need to be applied 
to improve speed and efficacy. 
 
 
5.2. Mechanical dredge efficiency  
 
While the operational capacity increased markedly in Phase II, a question remains regarding 
optimal dredge efficiency (i.e. the percent of exotic Caulerpa removed from dredged areas); this 
requires an appropriate balance between spatial coverage and quality of dredging. The results 
of percent cover monitoring from Phase I indicated that areas of remnant exotic Caulerpa 
persisted within dredges, and observations made by divers during Phase II indicate that this 
issue persists. This is evidenced by the quantity of material removed by the diver-operated 
suction dredge within an area that the mechanical suction dredge had already been through 
(Table 2; Fig. 5). Following discussion with JBL it was decided that operations for the remainder 
of the Phase II would be adjusted to focus on more thorough dredging (i.e. more Caulerpa 
removed, but less area covered).  
 
Additional to the speed of the dredge head over the seafloor, there are a number of other factors 
that affect the efficiency of the mechanical dredge in removing exotic Caulerpa. For example, 
the number of passes the dredge head makes over one area, the weather (wind and swell 
conditions can make dredge operations challenging), and the operator of the dredge. In order for 
the dredge to work successfully, the operator needs to consider and maintain control of 
numerous factors. For example, depth of the cut, speed that the brushes turn, angle of the 
leading edge of the dredge, etc. All these factors are constantly adjusted without the operator 
being able to see the dredge. 
 
 
14 
 

5.3. Diver-operated dredge efficiency 
 
It is evident that the operational capacity of diver-operated dredging is significantly less than the 
mechanical suction dredge (c.f. Tables 1 and 2). However, because the diver-operated suction 
dredging was conducted toward the end of the date range for this report, no observations have 
yet been made regarding the comparative efficacy of diver-operated dredging for removing 
remnant exotic Caulerpa. However, one key observation is that on several occasions the divers 
encountered mats that were simply too large and / or thick to be removed with hand-held 
dredges. For these situations the power of the mechanical dredge is required, and subsequently 
the discussion around diver vs mechanical operations must consider exotic Caulerpa density as 
well as spatial extent. 
 
 
5.4. Costing information 
 
The set-up fees for the Omakiwi Suction Dredging Trial, including the design and build of sand 
extractors/trommels, piping manifolds, and amendments and repair costs incurred during the 
Phase I trials, are estimated to be up to $600,000. Final costing of this build will be included in 
the final report upon all contractors submitting final invoices. It must be acknowledged that the 
time constraints placed on the accelerated trial did increase costs. Understandably, this is 
expected in a response scenario; however, future builds would not be expected to incur the 
same costs. The estimated daily dredge rate, which includes the barge, dredging equipment, 
pump hire, hoses, fuel, Morooka hire, operator labor, shoreside excavator, and project manager, 
is approximately $20,000 per day. Stand-down rates, which cover non-suitable conditions or 
mechanical downtime and include costs for barge, dredging equipment, Morooka hire, and 
other associated hire rates, are estimated to range between $10,000 and $12,000 per day. Given 
the time of year and the weather conditions, unfortunately, this project has incurred 
considerable stand-down days. 
The Suction Dredging Trial experienced a mix of operational and non-operational days. Dredging 
operations during this interim period are estimated to have occurred on 18 days. The trial faced 
weather-related stand-downs on an estimated seven days, while mechanical or preparation-
related activities accounted for approximately 13 days of non-dredging operations, such as 
equipment preparation, unloading, and decontamination. The trial also involved a significant 
mobilization phase from April 13 to April 30, with continuous efforts to prepare for Stage 2 of the 
operations. This phase included various setup activities, testing of screening plants, and the 
mobilization of equipment from Opua to Omakiwi. Please note, accurate total stand-down days, 
operational days, and stand-down days will be presented in the final report upon receiving final 
logs from our dredging contractor. 
 
 
 
15 
 

5.5. Ongoing challenges 
 
Stinger pipes 
 
Deposition of dredge spoil remains challenging. If the pipes are too long, they fold up upon 
themselves and sediment deposition is prevented. If they are too short, water pressure pushes 
the pipes away from the seafloor, resulting in a sediment plume and widespread deposition of 
sediment. Several factors (tide, swell, barge repositioning) mean that the optimal depth for the 
pipes changes throughout the day. JBL are continuing to work on a solution. 
 
Buried exotic Caulerpa 
 
Divers reported finding extensive areas of exotic Caulerpa buried under sediment. This 
presumably occurs as a result of the issues with the stinger pipes, discussed above. 
 
Visibility
 
 
The sediment discharged by the barge is very fine, and subsequently causes poor visibility for 
dive operations within approximately 100 meters of the barge (depending on how the stinger 
pipes are operating). This can prevent divers from conducting ecological monitoring in areas 
recently dredged during the same day unless dredging ceases. 
 
Data management
 
 
The provision of daily GeoTIFF files has been a significant improvement to reporting capabilities 
during Phase II, however access to this information remains variable. The data is not necessarily 
transferred by the dredge operator at the end of each day or, depending on personnel, may not 
be transferred at all. No automated data transfer system is available / possible. 
 
Weather 
 
Phase II activities have been impacted by adverse weather conditions on a number of 
occasions, which has resulted in several full stand-down days, and days when dredging was 
only able to occur for part of the day or at a reduced capacity. This has implications for the utility 
of the dredge, particularly at times of year when adverse weather is a more common 
occurrence. 
 
 
 
Acknowledgements 
 
16 
 

Northland Regional Council and Cawthron Institute would like to acknowledge the ongoing 
support, leadership, and involvement of Ngāti Kuta and Patukeha hapū throughout the Caulerpa 
response in Te Rāwhiti, Bay of Islands, in addition to the following partners: Bay of Plenty 
Regional Council, Commercial Dive Specialists, the Department of Conservation, Discovery 
Marine Limited, Ethos Environmental, Johnson Bros Ltd., Marine and Environmental Field 
Services, Maxwell Ecological Services, the Ministry of Primary Industries, the National Institute 
of Water and Atmospheric Research, and Wai Knot. 
 
 
References 
 
Davidson I, Fletcher L, Richards D, Bennett-Jones L, Nevill-Jackson M, Smith A, Floerl L, 
Gammon M, Leonard K. 2024. Omakiwi Cove exotic Caulerpa removal. Phase I: method 
development for mechanical suction dredging. Nelson: Cawthron Institute. Cawthron Report 
4040. Prepared for Northland Regional Council and Biosecurity New Zealand. 
 
Northland Regional Council (2024a) Wider surveillance for exotic Caulerpa in Northland. 
Prepared for Biosecurity New Zealand. 
 
Northland Regional Council (2024b) Perimeter management and treatment report. Prepared for 
Biosecurity New Zealand. 
 
17