This is an HTML version of an attachment to the Official Information request 'BDC Port Consultants and Reports.'.
Kawatiri Business Review 
DETERMINING THE FUTURE OF BULLER DREDGING
MARCH 2021
RMC2 Limited t/a RMC²
Prepared by Ray Mudgway

K
AWA

TIRI BU
SINES
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
/ RMC
2
Author: Ray Mudgway 
All work is done, and services rendered at the request of, and for the purposes of the client only. Neither RMC2 
Limited T/A RMC² nor any of its employees accepts any responsibility on any grounds whatsoever, including 
negligence, to any other person.
While every effort is made by RMC2 Limited T/A RMC² to ensure that the information, opinions and forecasts 
provided to the client are accurate and reliable, RMC2 Limited T/A RMC² shall not be liable for any adverse 
consequences of the client’s decisions made in reliance of any report provided by RMC2 Limited T/A RMC², nor 
shall RMC2 Limited T/A RMC² be held to have given or implied any warranty as to whether any report provided by 
RMC2 Limited T/A RMC² will assist in the performance of the client’s functions.
2   O F   4 6

K
AWA

Contents
TIRI BU
SINES
Section 1: Introduction – giving context ..................................................................................................................................................................................4
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
  1.  Executive Summary ..........................................................................................................................................................................................................................................5
  2.  Business review .....................................................................................................................................................................................................................................................6
Section 2: Value Proposition – defining our opportunities ........................................................................................................................7
  1.  Immediate focus - government funded works in Buller ............................................................................................................................................8
   
a.  Gravel extraction .........................................................................................................................................................................................................................................9
  2.  Growing the Buller and West Coast ...............................................................................................................................................................................................10
   
a.  Economic Impact Assessment ..................................................................................................................................................................................................11
   
b.  Resilience & Lifelines strategy ...................................................................................................................................................................................................14
  3.  Dredging growth opportunities ........................................................................................................................................................................................................15
Section 3: Business plan – leveraging our opportunities .........................................................................................................................16
  1.  Capital plan .............................................................................................................................................................................................................................................................17
  2.  Financial model ..................................................................................................................................................................................................................................................18
  3.  Contractual positions ...................................................................................................................................................................................................................................19
  4.  Business structure ...........................................................................................................................................................................................................................................21
/ RMC
  5. Risks ................................................................................................................................................................................................................................................................................22
2
Section 4: Outcomes – taking action .........................................................................................................................................................................................24
  1. Summary ...................................................................................................................................................................................................................................................................25
  2. Recommendations ..........................................................................................................................................................................................................................................26 
Appendices ..........................................................................................................................................................................................................................................................................27
A.  Financial model ................................................................................................................................................................................................................................................28
 
a.  Cashflow for Buller works only .................................................................................................................................................................................................29
   
b.  Cashflow including outer region work .............................................................................................................................................................................30
  B.  Surveyor summary ......................................................................................................................................................................................................................................31
  C.  Anthony Harper legal advice............................................................................................................................................................................................................40
3   O F   4 6

K
AWA

TIRI BU
SINES
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING /
 RMC
2
S E CT I O N   O N E
INTRODUCTION  
Giving context

K
AWA

Executive Summary
TIRI BU
SINES
Background
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
Since Holcim ceased Westport operations approximately seven years ago, the 
institutional knowledge of the dredging business has understandably diminished. Long 
serving local experts left the business due to lack of sustainable and reliable work and 
dredging has occurred on a largely adhoc basis for several years.
The Kawatiri was essentially laid up to reduce costs 
in the face of significantly lower revenues which was 
sensible. Being laid up also had the effect of creating 
some deferred maintenance on the ship due to the 
The key to creating a sustainable 
absence of a full-time crew.
business is to rebuild the 
An older specialist vessel such as the Kawatiri 
institutional knowledge across the 
requires an ongoing program of repairs and 
operation. This is achieved and 
maintenance which is carried out by a dedicated 
underpinned by strong revenues in 
crew. A large proportion of these works are unskilled 
Buller and elsewhere.
in nature but important to the sustainability and 
reliability of the vessel.
The good news is that Buller’s port is undergoing 
Port of Nelson and Eastland Port (Gisborne) are  
a transformation with approximately $1.8m of 
also interested in long term partnership type 
/
dredging work booked for the Kawatiri through 
 RMC
agreements which could bring approximately  
government funded projects. This provides a stable 
2
$1m revenue per year. 
income in the short term to not only reset the 
Buller river for shipping and create flood resilience 
Noting the opportunities and the recent maintenance 
for Westport, but to also fund some immediate 
issues on the Kawatiri, this paper was commissioned 
maintenance needs on the vessel.
to conduct a full review of the dredging business. 
The aim as to understand how to make the dredging 
Additionally, the reality of a large scale export 
business safe, sustainable and profitable. There is 
business (Heavy Mineral Sands) is gaining 
a pathway to achieving these objectives which are 
momentum and may start on the Buller in 2021.  
outlined in sections throughout the paper.
This would effectively replace the Holcim operation 
of the past and makes the Kawatiri a vital component 
The key to creating a sustainable business is to 
of the port system (without her there is no large port).
rebuild the institutional knowledge across the 
operation. This is achieved and underpinned by 
strong revenues in Buller and elsewhere.
Ray Mudgway
Managing Director, RMC2
5   O F   4 6

K
AWA

Business review
TIRI BU
SINES
To complete a thorough review of the current 
business, and to understand the potential pathways 
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
forward, the following building blocks formed  
the review:
The business review:
  1.  Define the value proposition for the Kawatiri  
Builds on the steps already taken by BDC 
in terms of:
following the strategic review in 2020.
  a. Buller.
Explores the governance, ownership 
  b.  The West Coast Region.
and management recommendations in 
  c.  New Zealand.
more detail to make a final decision on 
business structures.
 2.   Define the capital plan required to sustain 
operations.
Looks to leverage the business 
  a.   Define the list and cost of works required 
opportunities that have gathered 
to bring the vessel (and business) up to 
momentum since the strategy  
sustainable operational standard.
was written.
  b.   Define working capital requirements  
under all scenarios.
 3.   Create a comprehensive financial model  
 5.   Complete a review of insurances required  
that clearly shows the financial pathway  
for sustained operations.
/
to sustained operations.
 6.   Recommend an operating model to sustain  
 RMC
 4.   Define the contractual positions the business 
safe and reliable operations.
2
requires to sustain operations. This includes 
 7. 
 Clearly outline the risk mitigations for the 
crew contracts under casual and full time 
operation, council, and rate payers of Buller.
arrangements, Buller related contracts, Outer 
This paper steps through each of these building 
Region Contracts (e.g. Port Nelson).
blocks outlining the various options and approached 
in each section before making recommendations  
in section 4 of the paper.
6   O F   4 6

K
AWA

TIRI BU
SINES
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING /
 RMC
2
S E CT I O N   T W O
VALUE  
PROPOSITION 
Defining our opportunities

K
AWA

Immediate focus
TIRI BU
SINES
Central Government funded works – 
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
approximately $2m
There are three dredging jobs requiring completion  
The lagoon works need to be completed by April. 
in Buller and paid for by the government:
Jetty removals are scheduled for July. The river 
  1.   Lagoon dredging to 4m for the new pontoons  
gravel extraction can start following an RFI process 
as funded by the PDU up to $330,000.
scheduled for late February. These works may take 
several months pending work methodology of the 
 2.   Jetty removals from the lagoon following the 
RFI process.
construction of new pontoons as funded by the 
PDU up to $200,000.
Additionally, the accretion of gravel in the Buller 
has increased the flood risk to Westport township. 
  3.   Gravel removal on the river side of half tide wall 
Therefore, a dredging capability is required long  
for river operability and flood protection for 
term for the township and river.
Westport as funded by IRG up to $1.5m.
Without an operational dredge, these services will 
need to be acquired through third parties at great 
expense (and potentially delay). Conversely, the 
work is paid in full by central government funds thus 
providing a guaranteed revenue stream in 2021 for 
the Kawatiri.
/ RMC
2
8   O F   4 6


K
AWA

Gravel extraction (from The IRG Ports Package 2020)
TIRI BU
SINES
$1,500,000
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
As part of the West Coast Ports strategic review in late 
  2.   Degradation of the wall is accelerated by  
2019 (funded by the PGF), a hydrology report was 
the gravel build up. 
commissioned in consultation with the Buller 2100 
  3.   The wall is critical to narrowing the river  
working group. Buller 2100 sought to understand  
to encourage self-flushing of the river.
the flood risk of increased gravel deposits in the  
river system. A full copy of the report is included  
  4.   Degradation of the wall leads to a higher  
in the attached RMC² strategy ‘Securing the Future  
flood risk.
of the West Coast Ports’.
  5.   Gravel extraction or dredging methods  
The hydrology report, in terms of the port strategy 
should be investigated in the port and lower 
work, was scoped to:
river areas.
  1.  Understand the commercial implications on 
  6.   A targeted dredging regime around the wall is 
current and future port operations.
required to reduce this risk (dredging elsewhere 
on the Buller will not materially improve the 
  2.   Understand the sustainability of new port 
situation with respect to the wall).
investment to ensure new assets were not 
undermined by river currents, particularly  
 7.   That gravel removal at Organ’s Island is: 
around the ex Holcim and Bathurst Coal 
  a.   Unlikely to minimise or reduce dredging 
wharves and seawalls.
requirements downstream around the port 
  3.   Test the hypothesis that removing gravel at 
and at the river mouth. 
/
Organ’s Island (upstream of the port operation), 
 
   b.   Likely to increase flood risk downstream if 
RMC
would reduce the dredging requirement around 
too much gravel is removed, thus reducing 
2
the port and at the river mouth.
the overflow into the Orowaiti area.
The key findings of the report, identified that the 
The following recommendations were made to local 
impacts of the port strategy are:
government officials as a result of this study:
  1.   The half tide wall (wall) opposite the Holcim 
Recommend that BDC investigates gravel extraction 
and Bathurst wharves, has increased gravel 
methods for the half tide wall.
build up with is redirecting the river flows 
towards the wharves, associated seawalls, and 
Recommend that the commercial negotiations for 
ultimately the township of Westport.
the fishing sector and HMS sector gives consideration 
to the gravel removal and ongoing dredging 
requirements for a safe and sustainable river system.
Recommend that WCRC, BDC and Buller 2100 
work collaboratively to solve the flooding and 
sustainability risks including the consideration  
of funding models.
9   O F   4 6

K
AWA

Growing the Buller and West Coast
TIRI BU
SINES
Enabling growth and creating 
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
resilience for Buller and the  
West Coast
The prize that a sustainable 
The Port Strategy outlines the need for protecting 
Kawatiri operation unlocks for the 
the existing fishing fleet and attempting to grow 
Buller, and the wider region, is 
shipping through Buller by exporting heavy mineral 
game changing.
sands (refer to the Protect : Optimise : Grow diagram 
below). There has been significant progress made 
in past 12 months to implement the strategy with 
multiple key components currently being executed  
The lease of Holcim wharf to West Coast Bulk 
as planned.
Logistics Ltd enables bulk exports to be exported 
This strategy continues to gather momentum with 
in 2021 and the initiative continues to make strong 
funding provided by IRG and the PDU, as well as 
progress towards operationalisation. 
significant private investment, to establish a fishing 
The following four pages outline the economic 
precinct and a bulk precinct that any region would  
benefits of growing our fishing and bulk sectors  
be proud of.
in the region. The opportunities for the region on  
Fishing is established and is growing with expansion 
the back of executing the ports strategy is significant.  
of Talley’s processing in Westport.
The ports strategy also outlined a plan to create 
greater natural and commercial resilience for the 
region and states the important of the Buller and 
/ RMC
associated assets in this regard.
2
1 0   O F   4 6

K
AWA

Economic Impact Assessment (from The Port Strategy)
TIRI BU
SINES
A full economic assessment was completed by Kel Sanderson in two parts:
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
  1.  Current  state.
  2.  Future  state based on establishing a coast wide FMS sector.
This provides an important lens into the potential value created through a cohesive 
West Coast Transport & Logistics Strategy and is summarised below. A full report is 
attached at Appendix A.
CURRENT STATE SUMMARY
FUTURE STATE SUMMARY
The overall picture shows a considerable level of 
At the Minerals Forum in May 2018, Minister for 
change in the economy of the West Coast Region 
Energy and Resources Hon Dr Megan Woods said 
between 2000 and 2018. It is generally unusual to 
“There is sky-rocketing demand around the world  
see two main resource-based industries like forest 
for minerals which are used in clean-tech and which 
& wood, and mining to reduce in economy share to 
can aid our transition to a low carbon economy.  
such an extent. 
That demand represents a real opportunity for  
In the year 2000, these industries had 12% of the 
New Zealand.” These ‘green’ minerals are needed  
Region’s employment and produced 30% of the 
for batteries, wind turbines, solar panels, LEDs  
/
and hybrid cars.
 RMC
Region’s value added. By 2018, the two industries 
employed just 7% of the Region’s employment and 
Minerals which fall into these groups and are present 
2
generated 13% of the Region’s value added.
on the West Coast include Garnet, Rare Earth 
These are certainly a weak part of the Region’s 
Elements (REEs) and Ilmenite. Work which has been 
current economy, and presumably there are some 
done to determine the size of the deposits, and 
initiatives possible to recover or replace them. 
potential annual production indicates that there  
is a potential to sustainably produce 600,000 tonnes 
Protect and Grow Fishing
per year.
There is also the potential, presumably for a greater 
Establish a 600,000 tonne  
proportion of the fish and seafood offshore of the 
HMS industry
West Coast, to be caught and processed by the 
people on the West Coast.
This industry would mine, process and export 
200,000 tonnes of industrial garnet, and 400,000 
In a 2017 report on “The economic contribution of 
tonnes of ilmenite, mined and extracted as a  
commercial fishing to the New Zealand economy”, 
product complementary with the garnet from  
prepared for the New Zealand commercial fishing 
the West Coast deposits.
industry by BERL, the employment in harvesting in 
FMA7 was shown to be 966 FTEs in 2015. 
This section estimates the impacts of the full 
industry, including the initial Stage One 100,000 
This contrasts with the level shown as 19 to 34 FTEs 
tonnes garnet operation, joined by a further  
in the StatisticsNZ data we have in the table above. 
100,000 tonnes of garnet and 400,000 tonnes  
The 966 FTEs involved in commercial fishing in FMA 
of high-grade ilmenite. 
7 presumably mostly are domiciled in other Regions, 
such as Nelson-Marlborough. Talleys of Motueka 
utilise port facilities at Westport, and it may be 
possible to increase the employment based there  
in certain conditions.
1 1   O F   4 6

K
AWA

TIRI BU
SINES
Operations on the West Coast
Export earnings
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
On a similar basis to the estimates for Stage One 
The expected export return from the mineral sand 
above we now estimate the economic impacts of the 
exports, being of high grade is that an average return 
established industry operating at a level of 600,000 
of US$150 to US$200 per tonne will be achieved.  
tonnes per year.
This is currently equivalent to NZ$240 to NZ$320  
per tonne.
Garnet and ilmenite mining, processing  
and export operations:

This implies that the value of exports from the 
600,000 tonnes exported by this industry would be 
  Employment 
100 FTEs, permanent
worth NZ$144 million to $192 million per year.
  Indirect employment  80+ FTEs, permanent
This implies that the operation of the production 
and processing industry will increase permanent 
Recommend that the PGF approve the funding 
employment on the West Coast by at least 180 
application to renew the fishing jetties to protect  
fulltime employed.
and enable growth in the fishing sector.
Taking account of the different levels of production 
Recommend that the ‘Establishment Board’ to create 
cost per tonne of the initial garnet plant, the 
a West Coast Transport & Logistics strategy be stood 
later garnet plant(s) and the ilmenite plant, the 
up and funded to attempt to maximise the economic 
expectation is that the total direct production cost 
benefit of the HMS sector.
will be of the order of $30 million per year. Taking 
account of the value chain impact the total addition 
/ RMC
to annual expenditure on the West Coast is expected 
to be $60 to $70 million.
2
1 2   O F   4 6

K
AWA

TIRI BU
SINES
These volumes are thought to be conservative in terms of both the resource available and the market 
opportunities.

S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
Capital expenditure on the West Coast:
Garnet processing plant (200,000 tonnes)
 
Capital cost: 
$100 million
 
Construction employment 
30 FTE jobs over three years
 
Indirect employment 
4 FTE jobs over three years
Ilmenite processing (400,000 tonnes)
 
Capital cost: 
$35 million
 
Construction employment 
20 FTE jobs over one year
 
Indirect employment 
16 FTE jobs over one year
Storage / portside 
 
Capital cost 
$20 million
 
Construction employment 
10 FTE jobs over one year
 
Indirect employment 
8 FTE jobs over one year
/ RMC
The indications are that the total capital expenditure to develop the mineral sands industry on the West Coast 
2
would be about $155 million. This would employ directly 30 FTE jobs over three years another 30 FTE jobs over 
one year, which is a total of the equivalent of 30 FTE jobs over four years. This direct employment would generate 
indirect or value chain employment of about 24 FTE jobs over four years, giving a total increase of the equivalent 
of 54 FTE jobs over four years.
1 3   O F   4 6

K
AWA

Resilience & Lifelines strategy (from The Port Strategy)
TIRI BU
SINES
Natural disaster resilience
Essential assets
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
The resilience and lifeline team at WCRC do not 
The ports need to be viewed as a system, rather than 
currently factor in the ports of Westport and 
just a wharf or lagoon. The critical elements of the 
Greymouth as key lifeline assets due to their 
port system in relation to resilience and lifelines are:
perceived poor condition and uncertain futures.
  1.  Seawalls.
This presents a serious risk in the resilience plan 
  2.  River access (dredging).
for the West Coast, particularly in terms of natural 
disaster, given the precarious nature of the roads  
 3.   Wharves that are capable of berthing large ships 
and rail connecting the West Coast to the rest of  
and offloading/loading cargoes and Pax.
New Zealand. In the author’s opinion, the West Coast 
 4.   Road and rail access to berths is ideal including 
ports must play a key role in providing much need 
marshalling land.
resilience for the wider region.
  5.   Safe passage from the sea to the wharves 
For an isolated region at risk from the Alpine Fault, 
including navigation and marine services.
sea transport is essential.
There are limited credible options available at 
Commercial resilience
present with the following seen as priorities:
 1.   Holcim wharf is by far the most resilient and 
The closure of main roads such as Arthur’s Pass,  
valuable wharf to achieve sizeable shipping 
and the semi-regular disruption to rail services  
on the West Coast presently. The issue with 
(the latest being October 2019), presents significant 
the wharf is the Buller River bar access which 
business disruption and economic impact on that 
/ 
requires ongoing dredging. This is a critical 
RMC
largest West Coast exporters; Westland Dairy and 
element which must be maintained in order 
2
Bathurst Resources.
to achieve resilience.
Both Westland Dairy, and Bathurst Resources, have 
  2.   The Greymouth bar is self-flushing, but the 
sought contingency plans to utilise ports as an 
general-purpose wharf is in very poor condition 
alternative, but again, due to the perceived condition 
and not in itself a resilient structure. 
of assets and their future, have struggled to achieve  
a robust alternative to road and rail.
Recommend that the recommended strategies to 
maintain the Buller River are executed to not only 
Opportunity
present commercial opportunities, but to underpin  
a resilience strategy that involves a credible sea 
Through the renewal of fishing jetties, and the 
option for the West Coast.
adoption of the strategies recommended in this 
study, the ports will provide the confidence to WCRC 
Recommend that the general-purpose wharf in 
and the commercial exporters, to have a credible and 
Greymouth is maintained to its current state as  
reliable plan to utilise ports when it is required.
a secondary option to Holcim wharf.
Accordingly, the strategies encourage increased 
Recommend that WCRC, Westland Dairy, Bathurst 
involvement from WCRC to achieve natural disaster 
Resources and other West Coast entities establish a 
resilience, and it is recommended that Westland 
clear resilience plan to utilise the assets at Westport 
Dairy and Bathurst contribute to the ‘Establishment 
and Greymouth if a natural disaster occurs and road 
Board’ costs to enable their alternative sea  
and rail is not an option.
logistics options.
1 4   O F   4 6

K
AWA

Dredging growth opportunities
TIRI BU
SINES
Outer region contracts
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
The Kawatiri’s small size compared to its competitors 
presents a unique value proposition for dredging at 
There is a lot of work to do before 
smaller NZ ports.
BDC could achieve the required 
Port of Nelson, Eastland Port, CentrePort, Port of 
levels of service to enter into 
Oamaru and potentially others all have a need for 
long term contracts. However, by 
boutique and small scale dredging.
following the path outlined in this 
Some of this work consists of capital dredging 
paper outer port work is a real 
(one off assignments that are required to ‘reset’ 
potential option from later this year.
a port) where others require annual or biannual 
maintenance dredging thus providing a longer term 
revenue stream.
Partnership approach 
Key enablers for outer  
region contracts
Previous contracts have been adhoc and a one-sided 
‘contractor agreement’ arrangement. This did not 
Port of Nelson and BDC had a robust debrief 
serve BDC or Nelson well on the last contract. 
following the recent work. For Nelson, the dredge is 
If outer port work is to be pursued, a longer term 
important to them and they are keen to engage for a 
‘partnership’ type contract is required that provides 
long term contract. However, they must be reassured 
the certainty and revenue for BDC, and the reliability 
/
of its reliability and professionalism before doing so 
 RMC
and professionalism for the client. 
citing recent reliability issues and crewing issues.
2
Both Port of Nelson and Eastland port are keen  
There is a lot of work to do before BDC could achieve 
to enter into such negotiations. There is potential 
the required levels of service to enter into long term 
that the two annual maintenance contracts at those 
contracts. However, by following the path outlined in 
ports are tied together in one ‘ports agreement’ 
this paper outer port work is a real potential option 
which provides increased surety for all parties.  
from later this year.
This is the model that is applied by Dutch Dredging  
at larger ports.
The contract must also enable BDC to look after its 
own port interests at all times. This may require a 
negotiation around timings at outer ports, as well  
as contractual provisions to enable the vessel to 
return to Buller for works if required at short notice. 
These are standard approaches in the industry.
1 5   O F   4 6

K
AWA

TIRI BU
SINES
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING /
 RMC
2
S E CT I O N   T H R E E
BUSINESS PLAN  
Leveraging our  
opportunities

K
AWA

Capital plan
TIRI BU
SINES
Vessel works
Working capital
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
 1.   Immediate works $200,000. These can be 
Based on all scenarios, there will not be a working 
funded by revenues from the government 
capital requirement for dredging (noting that  
contracts throughout the work.
there wouldn’t be any dredging if sand exports  
  2.   2022 slipping estimated $2.2m Some of these 
didn’t occur).
works can be funded from operating surpluses 
If it was decided to continue outer port work (without 
but may require an investment from BDC.  
the need for large scale work in Westport), there may 
These works would only be completed if the 
be a requirement to top the operation up from time 
growth opportunities outlined happen.  
to time depending on the success of each individual 
By doing so, the works would be repaid  
job (similar to that experienced to date).
quickly through operating revenues.
The fishing fleet will not sustain dredging operations.
A full list of works has been created by the Port 
Manager, in consultation with the dredging crew  
and SGS. An independent SGS report is appendix B.
The costs are estimates only. Thorough assessments 
and quotes from industry professionals are required 
and recommended before any major works are 
carried out.
/ RMC
2
1 7   O F   4 6

K
AWA

Financial model
TIRI BU
SINES
Cashflow model
Key points to note for the model:
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
To fully understand the cash implications of the 
  •   The model has been prepared on a  
dredging operation, a cashflow model has been 
pre-tax basis. 
created based on the BDC budget. Maintenance 
  •   All calculations and assumptions are detailed 
provisions as outlined in this paper have also been 
on the “Assumptions” worksheet.
added. This approach was taken (rather than a Profit 
and Loss) so cash requirements from council are 
  •   With the exception of items relating to 
clearly understood.
additional out of port dredging work, revenues 
and expenses are as per the draft Budget 
To help understand the different phases, the model 
provided to us on 10 March.
enables the user to select outer port work or remove 
it to understand how sustainable the operation is. In 
  •  
A complete reliance has been put on the budget 
summary, the model shows:
data provided by BDC. General comments:
 1.   The annual operating budget of the dredge  
  •   No dredging income has been budgeted 
with a full time crew is approximately $1.7m  
in 2021/22 (with the exception of the Govt 
if it remains in the Buller. This scenario would 
work). However, all costs appear to have 
only occur if sands exports were to occur. 
been allowed for - fuel, crew etc so the 
Revenues from these activities would be 
model is showing a pessimistic outcome.
approximately $2.6m per year. Therefore,  
  •  
Additional operating costs are added for 
the Buller dredging business under a sands 
outer port work. In time, some of these may 
export model is profitable and sustainable.
prove to be double ups.
/ RMC
 2.   Outer Port work (based on BDC budget ratios) 
With respect to the additional out of port the 
2
costs approximately $360,000. If revenues are 
following additional costs on the ratio of budgeted 
contracted at $1m per year (which is the request 
costs to budgeted revenue:
from Nelson and Gisborne), this work is also 
 • Fuel: 11.6% of the additional revenue
profitable and sustainable.
 •  R&M: 7% of the additional revenue (note this 
  3.   BDC does not have chase outer port work to 
excl. slip charges)
create a sustainable business model.
  •  
Other Operating Costs: 2.7% of additional 
  4.   Outer Port work on its own is marginal and 
revenue
should be carefully considered. It will not 
sustain a full time crew.
The 2019 Nelson campaign was reviewed and noted 
there are other out of port specific costs for the likes 
Extracts from the model as summarised above  
of mobilisation, surveys, crew transfers, port charges 
are in the Appendices.
etc. These specific costs accounted for 14.7% of 
the revenue for that campaign so these have been 
applied to this model. 
Crew costs are assumed to be fixed - so no further 
costs are added for the out of port work.
1 8   O F   4 6


K
AWA

Contractual positions
TIRI BU
SINES
Legal advice
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
Several dredging contracts were reviewed  
Examples of work
as part of this strategy including the existing  
  •  
Advising Lyttelton Port Company on a range of 
Nelson/BDC version.
development, transport, logistics, relationship 
To gain a deep understanding of the pitfalls of 
and procurement arrangements (including 
dredging contracts, the services of Chris Dann, 
dredging works; and vessel, crane and 
Partner Anthony Harper, were used to discuss the 
container handling equipment procurement 
operation and potential contracts (particularly  
(construction, purchase, hire and charter)).
outer port work). 
  •  
Acting for a number of Ports in preparing and 
Chris’ in-house experience in the UK as Corporate 
negotiating container terminal, depot services 
Legal Manager at Exel Plc, then the world’s largest 
and stevedoring/marshalling agreements with 
logistics company, provided him with a commercially 
shipping lines and other parties.
pragmatic approach and an in-depth understanding 
  •  
Advising CentrePort in relation to the 
of the shipping and logistics industry. 
establishment of its inland container terminal 
He has continued to develop this expertise and 
in Wanganui and on a range of services and 
is now regarded as one of the country’s leading 
relationship arrangements (including with 
transport and logistics lawyers. Chris is ranked as a 
KiwiRail for CentrePort’s “CentreRail” freight 
“Leading Individual” in the 2018-2021 Legal 500 Asia 
transportation service).
Pacific Guides. In 2020 he was awarded the Chartered 
  •  
Advising Southland District Council on both 
Institute of Logistics and Transport’s Communication 
/ 
template and bespoke procurement contracts 
RMC
Award for his contributions to the sector.
for services and minor works.
2
Chris heads Anthony Harper’s corporate advisory 
  •  
Advising Southland District Council on the 
team and has over 20 years’ of experience in 
procurement process and approach and 
commercial contracts, procurement, manufacturing, 
regulatory issues and implications in relation 
supply and distribution, corporate structuring  
to contracts for community services, including 
and governance, joint ventures and mergers  
under the Local Government Act and Local 
and acquisitions.
Authorities (Members’ Interests) Act 1968, 
following a service delivery review under s17A 
of the LGA.
  •  
Lead advisor to the Ministry of Business, 
Innovation and Employment in relation to 
the domestic and international procurement 
of petroleum reserves for the New Zealand 
Government, including tendering, procurement 
and probity advice and documentation,  
tender evaluation, and contract drafting  
and negotiation.
Chris Dann
Partner | Head of the Corporate Advisory team
+64 3 964 5835
+64 27 672 8721
[email address]
1 9   O F   4 6

K
AWA

TIRI BU
SINES
Legal approach
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
Chris’ advice has been provided to management  
One advantage of the FIDC form of contract is 
in full, however the following is important for  
that has the same ‘look and feel’ as a standard 
the strategy:
construction contract (an “Appendix” of specific 
 1.   First, we think that there are two general 
details, bespoke “Particular Conditions” if required 
‘approach’ considerations:
and a set of “General Conditions”), so we expect that 
Council staff will find it relatively user friendly, yet it 
   1.1.   We recommend a relational/”partnering” 
is specifically designed for dredging (both capital and 
approach with the client in order to 
maintenance dredging, as well as reclamation work 
minimise the risk of surprises which can 
and ancillary construction) and somewhat simpler 
lead to risk and dispute. Two aspects are 
than a standard form construction contract.
particularly important:
   (a)  proper definition of the full scope of 
works (explained further below); and
   (b)  identifying and properly allocating  
risks to the party best placed to address 
those risks (including, where that  
party is the Council, ensuring that the 
Council is properly remunerated for 
those risks).
/ RMC
   1.2.   The form of contract should be appropriate 
for dredging services. In our view, an 
2
industry standard construction contract 
(e.g. NZS 3910 – 3916 suite) is not 
appropriate for dredging services.  
There are considerations which are unique 
to dredging operations that are not 
addressed in a construction contract (and 
vice versa). We suggest that the Council 
considers either: 
   (a)  preparing a template dredging contract 
which is specifically designed for 
dredging services by the Council using 
Kawatiri; or 
    (b) 
 uses the standard form “FIDIC® Form  
of Contract for Dredging and 
Reclamation Works”. 
2 0   O F   4 6

K
AWA

Business structure
TIRI BU
SINES
Ownership
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
The review considered these four scenarios:
When considering the streams of potential work,  
 1. 
Status Quo
the recommended structure is quite simple:
 2.  Transfer to CCO (Buller Holdings?)
 1.  BDC retains 100% ownership.
  3.  Partnership (other Ports/Government)
  2.   The crew is hired full time (pending work)  
and is locally based.
  4. Opco/AssetCo
 3.   Outer port contracts are long term and 
Once the staged approach was fully understood,  
partnerships, not service agreements.
it became apparent that the Kawatiri:
 4.   Third party experts are engaged formally  
  1.  Is a strategic asset for the Buller.
for engineering assessments and works.
  2.  Can be sustainable.
This model is simple, gives the region full control 
  3.   Is a long term option (doesn’t need replacing  
over its strategic assets, generates local high paid 
for many years).
jobs, and creates win win scenarios for partner ports.
  4.  Has value for other ports.
 5.   Requires local institutional knowledge  
to operate effectively and safely.
/ RMC
2
2 1   O F   4 6

K
AWA

Risks
TIRI BU
SINES
The following outlines some key risks and how  
Operational
this strategy is seeking to mitigate/minimise or avoid 
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
the risks.
Currently, the part time contracted crew is expensive 
and hard to keep current and motivated. There is low 
Financial
institutional knowledge of the operation as a whole 
and this puts reliance on third parties who may not 
Currently, the operation loses money, capital 
have our best interests at heart.
requirements are high (slipping), it is rate payer 
Additionally, the current operation lacks continuity 
funded, and external contracts are not reliably 
and is not capable of maintaining full operability  
profitable.
at Buller for bulk shipping.
The staged approach as recommended ensures:
The staged approach:
  1.  Short term maintenance is paid by contracted 
  1.   Creates an operating model that will sustain full 
works from government.
time Westport based crews.
 2.   2022 major works is defined but not committed 
  2.   The funds to manage the business 
to until there is confirmed work in Buller  
professionally.
(sands exports)
  3.   Will rebuild institutional knowledge. 
  3.   If sands exports happens, the operating model 
is profitable and sustainable and creates 
Reputational
enormous value for Buller and the region.
  4.   Outer port contracts are not entered into unless 
External contracts have been a mix of successes  
/
and the value proposition of the Kawatiri diminishes 
 RMC
they are strategic/partnership in nature, long 
term (guaranteed revenue) and the council can 
with bad experiences (like the last Nelson contract). 
2
commit to major works on the vessel.
Outer port work may reduce if the operation is not 
reset into a professional format.
 5.   The self funding staged approach removes  
the need for rate payer subsidies for  
The staged approach:
dredging operations.
  1.   Commits the dredge to work only if it is fit for 
purpose. This includes the vessel, equipment, 
operation, crew and management.
2 2   O F   4 6

K
AWA

TIRI BU
SINES
Health and Safety
Capital
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
Dredging operations are specialised activities  
There has been concern that the capital required 
that require professionals. Casual crewing increases 
to sustain operations is unachievable due to low 
the H&S risk profile through inconsistent work  
revenues and high risks.
at multiple ports and a lack of currency.
There is limited or no appetite from council to 
Direct oversight on outer region contracts is  
commit further capital under the existing model.
limited and largely outsourced to the master  
This staged approach:
(who is a contractor).
 1.   Generates the income required to sustain 
Deferred maintenance of the vessel increases  
operations.
the H&S risk profile.
 2.  Does not require rate payer funds.
This staged approach:
  3.   Is largely self funding, and if not entirely,  
 1.   Ensures all systems are safe and sustainable  
any committed funds can be repaid quickly.
for each stage of work.
  2.   Focusing on work creates the need for a full 
time, dedicated and local crew.
  3.   Oversight becomes less important with a full 
time employed crew with a vested interest in 
the operation.
/ 
 4.   The plan does not defer maintenance, it ensures 
RMC
it is on time and fully funded.
2
2 3   O F   4 6

K
AWA

TIRI BU
SINES
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING /
 RMC
2
S E CT I O N   FO U R
OUTCOMES  
Taking action

K
AWA

Summary
TIRI BU
SINES
There is now a clear plan on how to create a 
sustainable dredging operation for Buller:
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
 1.   Complete all government works as outlined.
 2.   In parallel, start long term negotiations  
with outer ports to understand the position. 
Engage professional engineers to give a full 
assessment of major works needed in 2022.
  3.   Understand the export sands opportunity.  
If that is confirmed as a start:
  a.   Hire a full time crew and start  
building institutional knowledge  
across the operation.
  b.   Book the vessel in for major works  
as defined by experts.
 4.  If export sands does not happen:
   a.   Reassess the sustainability of operations  
and major works requirements before 
signing any outer port contract.
/ RMC
2
2 5   O F   4 6

K
AWA

Recommendations
TIRI BU
SINES
Immediate focus of government 
Outer port contracts
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING 
funded works
Recommend that the FIDC contract form is adopted.
Following a thorough survey of the vessel by SGS 
Recommend that outer port contracts are long term 
(qualified company providing professional services), 
and partnerships, not service agreements.
and discussions with the current contract crew, 
Recommend that Chris Dann is engaged to form a 
these works can safely be completed by the Kawatiri 
robust contract for works if this option is pursued.
without major works or capital being spend on  
the vessel.
Recommend that no outer port contracts are  
Recommend
signed until the export sands business is understood 
 that a casual crew is contracted 
(to underpin major works in 2022).
immediately for works.
Recommend that BDC commits up to $200,000  
Structure
for immediate maintenance works as recommended 
by SGS as follows:
Recommend that BDC retains 100% ownership  
of the Kawatiri.
 1.   Commission a qualified marine electrical 
engineer to understand the sychronisation of 
Recommend that a full time crew that is based 
the gensets. From this, a program of works will 
locally is hired (pending the export sands outcome).
be created for next year’s slipping to confirm the 
Recommend that third party experts are engaged 
capital requirements and would potentially fix 
formally for engineering assessments and works.
the intermittent bow thruster issue.
/ RMC
 2.   Fix all hand rails which are currently rusted  
(non skilled labour)
2
 3.   Review the ventilation and alarm arrangements 
in the engine room (through SGS)
  4.   Lift the floor plates in the engine room, clean 
and make good any maintenance under the 
floor. This also provides clear access to assess 
the sea water pipes and hull ahead of next 
year’s slip.
2 6   O F   4 6

K
AWA

TIRI BU
SINES
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING /
 RMC
2
APPENDICES

K
AWA

TIRI BU
SINES
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING /
 RMC
2
A P P E N D I X   A
FINANCIAL 
MODEL

KAWATIRI DREDGE
CASH FLOW MODEL
Notes:
1 Unless stated otherwise, values shown within this file are exclusive of GST and presented in NZD.
2 Cash flows are presented in nominal terms (i.e. values include assumed general price / cost inflation over time). 
3 Cel s highlighted in orange represent inputs / assumptions that may be manual y altered.
No other values should be altered without careful consideration, as they general y rely on supporting calculations / formula.
4 Cash flows are presented on a before tax basis.  The impact of income tax (if any) should be separately considered.
5 For supporting calculations and assumptions refer to the worksheet 'Assumptions'.
Select Scenario
Budgeted Dredging
Included
Budgeted Government Related Work
Included
Additional Out of Port Dredging
Excluded
Cash Flows
1
2
3
4
5
6
7
8
9
10
Assumption Ref.
Source
2021/22
2022/23
2023/24
2024/25
2025/26
2026/27
2027/28
2028/29
2029/30
2030/31
1) Cash flows to repair / extend life of dredge
Dredge Slipping
A1
Draft Budget
  ( 2,200,000)
Contribution from interested third party
A2
Draft Budget
                - 
Total cash flows to repair/extend life of dredge
               - 
  ( 2,200,000)                - 
               - 
               - 
               - 
                - 
                - 
                - 
                - 
2) Cash flows from operating activities
Revenue
Per Draft Budget
Dredging Income
A3
Draft Budget
       3 00,000     2
  ,601,000     2
  ,653,020     2
  ,703,427     2
  ,752,089     2
  ,801,627     2 ,849,254     2 ,897,692     2 ,946,952     2 ,994,104
Government Related Work
A4
Draft Budget
    1
  ,800,000        2 04,000                 - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
Additional Out of Port Work
Additional Out of Port Dredging Work
A5
Refer A5
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
Total Revenue
    2
  ,100,000     2
  ,805,000     2
  ,653,020     2
  ,703,427     2
  ,752,089     2
  ,801,627     2 ,849,254     2 ,897,692     2 ,946,952     2 ,994,104
Operating Expenses
Per Draft Budget
Crew Costs
A6
Draft Budget
  ( 1,111,489)   ( 1,068,415)   ( 1,088,781)   ( 1,109,028)   ( 1,129,438)   ( 1,150,680)    ( 1,171,640)    ( 1,193,228)    ( 1,215,710)    ( 1,237,917)
Fuel
A11a
Draft Budget
      ( 307,122)       ( 302,554)       ( 308,605)       ( 314,469)       ( 320,129)       ( 325,892)       ( 331,432)       ( 337,066)       ( 342,796)       ( 348,281)
Repairs and Maintenance
A10a
Draft Budget
      ( 197,835)       ( 181,392)       ( 185,019)       ( 588,535)       ( 191,928)       ( 195,383)       ( 598,705)       ( 202,083)       ( 205,518)       ( 608,806)
Contractor Depth Sounding
A7
Draft Budget
          ( 9,000)           ( 9,180)           ( 9,364)           ( 9,542)           ( 9,713)           ( 9,888)         ( 10,056)         ( 10,227)         ( 10,401)         ( 10,567)
Insurance
A8
Draft Budget
        ( 25,000)         ( 25,500)         ( 26,010)         ( 26,504)         ( 26,981)         ( 27,467)         ( 27,934)         ( 28,409)         ( 28,892)         ( 29,354)
Other Operating Costs
A9a
Draft Budget
        ( 68,268)         ( 69,633)         ( 71,026)         ( 72,376)         ( 73,678)         ( 75,005)         ( 76,280)         ( 77,576)         ( 78,895)         ( 80,158)
  ( 1,718,714)   ( 1,656,674)   ( 1,688,806)   ( 2,120,453)   ( 1,751,869)   ( 1,784,315)    ( 2,216,047)    ( 1,848,589)    ( 1,882,212)    ( 2,315,084)
Additional Out of Port Work
Fuel for Additional Out of Port Work
A11b
% of Revenue
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
Repairs and Maintenance - Additional Out of Port Work
A10b
% of Revenue
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
Mobilisation, maps, surveys, crew transfers etc - Out of Port
A12
% of Revenue
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
Other Operating Costs - Additional Out of Port Work
A9b
% of Revenue
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
Total Operating Expenses
  ( 1,718,714)   ( 1,656,674)   ( 1,688,806)   ( 2,120,453)   ( 1,751,869)   ( 1,784,315)    ( 2,216,047)    ( 1,848,589)    ( 1,882,212)    ( 2,315,084)
Total cash flows from operating activities
      3
  81,286     1
  ,148,326       9
  64,214       5
  82,974     1
  ,000,220     1
  ,017,312         6
  33,208     1 ,049,103     1 ,064,740         6
  79,020
Total Cash Flow in Year (Before Tax)
      3
  81,286   ( 1,051,674)       9
  64,214       5
  82,974     1
  ,000,220     1
  ,017,312         6
  33,208     1 ,049,103     1 ,064,740         6
  79,020
Cumulative Cash Flow (Before Tax)
      3
  81,286      ( 670,388)       2
  93,826       8
  76,800     1
  ,877,021     2
  ,894,333     3 ,527,540     4 ,576,643     5 ,641,384     6 ,320,404

KAWATIRI DREDGE
CASH FLOW MODEL
Notes:
1 Unless stated otherwise, values shown within this file are exclusive of GST and presented in NZD.
2 Cash flows are presented in nominal terms (i.e. values include assumed general price / cost inflation over time). 
3 Cel s highlighted in orange represent inputs / assumptions that may be manual y altered.
No other values should be altered without careful consideration, as they general y rely on supporting calculations / formula.
4 Cash flows are presented on a before tax basis.  The impact of income tax (if any) should be separately considered.
5 For supporting calculations and assumptions refer to the worksheet 'Assumptions'.
Select Scenario
Budgeted Dredging
Included
Budgeted Government Related Work
Included
Additional Out of Port Dredging
Included
Cash Flows
1
2
3
4
5
6
7
8
9
10
Assumption Ref.
Source
2021/22
2022/23
2023/24
2024/25
2025/26
2026/27
2027/28
2028/29
2029/30
2030/31
1) Cash flows to repair / extend life of dredge
Dredge Slipping
A1
Draft Budget
  ( 2,200,000)
Contribution from interested third party
A2
Draft Budget
                - 
Total cash flows to repair/extend life of dredge
               - 
  ( 2,200,000)                - 
               - 
               - 
               - 
                - 
                - 
                - 
                - 
2) Cash flows from operating activities
Revenue
Per Draft Budget
Dredging Income
A3
Draft Budget
       3 00,000     2
  ,601,000     2
  ,653,020     2
  ,703,427     2
  ,752,089     2
  ,801,627     2 ,849,254     2 ,897,692     2 ,946,952     2 ,994,104
Government Related Work
A4
Draft Budget
    1
  ,800,000        2 04,000                 - 
                - 
                - 
                - 
                - 
                - 
                - 
                - 
Additional Out of Port Work
Additional Out of Port Dredging Work
A5
Refer A5
    1
  ,000,000     1
  ,020,000     1
  ,040,400     1
  ,061,208     1
  ,082,432     1
  ,104,081     1 ,126,162     1 ,148,686     1 ,171,659     1 ,195,093
Total Revenue
    3
  ,100,000     3
  ,825,000     3
  ,693,420     3
  ,764,635     3
  ,834,521     3
  ,905,707     3 ,975,417     4 ,046,377     4 ,118,612     4 ,189,196
Operating Expenses
Per Draft Budget
Crew Costs
A6
Draft Budget
  ( 1,111,489)   ( 1,068,415)   ( 1,088,781)   ( 1,109,028)   ( 1,129,438)   ( 1,150,680)    ( 1,171,640)    ( 1,193,228)    ( 1,215,710)    ( 1,237,917)
Fuel
A11a
Draft Budget
      ( 307,122)       ( 302,554)       ( 308,605)       ( 314,469)       ( 320,129)       ( 325,892)       ( 331,432)       ( 337,066)       ( 342,796)       ( 348,281)
Repairs and Maintenance
A10a
Draft Budget
      ( 197,835)       ( 181,392)       ( 185,019)       ( 588,535)       ( 191,928)       ( 195,383)       ( 598,705)       ( 202,083)       ( 205,518)       ( 608,806)
Contractor Depth Sounding
A7
Draft Budget
          ( 9,000)           ( 9,180)           ( 9,364)           ( 9,542)           ( 9,713)           ( 9,888)         ( 10,056)         ( 10,227)         ( 10,401)         ( 10,567)
Insurance
A8
Draft Budget
        ( 25,000)         ( 25,500)         ( 26,010)         ( 26,504)         ( 26,981)         ( 27,467)         ( 27,934)         ( 28,409)         ( 28,892)         ( 29,354)
Other Operating Costs
A9a
Draft Budget
        ( 68,268)         ( 69,633)         ( 71,026)         ( 72,376)         ( 73,678)         ( 75,005)         ( 76,280)         ( 77,576)         ( 78,895)         ( 80,158)
  ( 1,718,714)   ( 1,656,674)   ( 1,688,806)   ( 2,120,453)   ( 1,751,869)   ( 1,784,315)    ( 2,216,047)    ( 1,848,589)    ( 1,882,212)    ( 2,315,084)
Additional Out of Port Work
Fuel for Additional Out of Port Work
A11b
% of Revenue
      ( 116,322)       ( 118,649)       ( 121,022)       ( 123,442)       ( 125,911)       ( 128,429)       ( 130,998)       ( 133,618)       ( 136,290)       ( 139,016)
Repairs and Maintenance - Additional Out of Port Work
A10b
% of Revenue
        ( 69,739)         ( 71,134)         ( 72,557)         ( 74,008)         ( 75,488)         ( 76,998)         ( 78,538)         ( 80,108)         ( 81,711)         ( 83,345)
Mobilisation, maps, surveys, crew transfers etc - Out of Port
A12
% of Revenue
      ( 147,233)       ( 150,178)       ( 153,181)       ( 156,245)       ( 159,370)       ( 162,557)       ( 165,808)       ( 169,124)       ( 172,507)       ( 175,957)
Other Operating Costs - Additional Out of Port Work
A9b
% of Revenue
        ( 26,772)         ( 27,307)         ( 27,853)         ( 28,410)         ( 28,979)         ( 29,558)         ( 30,149)         ( 30,752)         ( 31,367)         ( 31,995)
      ( 360,066)       ( 367,268)       ( 374,613)       ( 382,105)       ( 389,747)       ( 397,542)       ( 405,493)       ( 413,603)       ( 421,875)       ( 430,313)
Total Operating Expenses
  ( 2,078,780)   ( 2,023,942)   ( 2,063,419)   ( 2,502,559)   ( 2,141,616)   ( 2,181,857)    ( 2,621,540)    ( 2,262,192)    ( 2,304,087)    ( 2,745,396)
Total cash flows from operating activities
    1
  ,021,220     1
  ,801,058     1
  ,630,001     1
  ,262,077     1
  ,692,905     1
  ,723,851     1 ,353,877     1 ,784,186     1 ,814,524     1 ,443,800
Total Cash Flow in Year (Before Tax)
    1
  ,021,220      ( 398,942)     1
  ,630,001     1
  ,262,077     1
  ,692,905     1
  ,723,851     1 ,353,877     1 ,784,186     1 ,814,524     1 ,443,800
Cumulative Cash Flow (Before Tax)
    1
  ,021,220       6
  22,278     2
  ,252,279     3
  ,514,356     5
  ,207,262     6
  ,931,112     8 ,284,989   1 0,069,175   1 1,883,699   1 3,327,500

K
AWA

TIRI BU
SINES
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING /
 RMC
2
A P P E N D I X   B
SURVEYOR  
REPORT

















K
AWA

TIRI BU
SINES
S REVIEW - DETERMINING THE FUTURE OF BULLER DREDGING /
 RMC
2
A P P E N D I X   C
ANTHONY 
HARPER  
LEGAL ADVICE



 
MEMORANDUM 
 
To 
Ray Mudgway, RMC2 Limited and to Buller District Council 
From 
Chris Dann, Anthony Harper 
Subject 
KAWATIRI DREDGE - CONTRACTING APPROACH, RISKS AND ISSUES 
Date 
17 March 2021 
 
1. 
We understand that RMC2 Limited has been engaged by the Buller District Council to 
undertake a review into the Council's dredging operations.  The Council provides dredging 
services, using the Council owned Kawatiri dredge, for other NZ ports from time to time 
under contract, in addition to the Kawatiri being required to dredge the Buller River. 
2. 
In connection with RMC2's review, you have asked us to outline some high level key 
considerations for dredging contracts in light of our experience of the same in our work for 
other ports. 
Approach 
3. 
First, we think that there are two general 'approach' considerations: 
3.1.  We recommend a relational/"partnering" approach with the client in order to minimise 
the risk of surprises which can lead to risk and dispute.  Two aspects are particularly 
important: 
(a) 
proper definition of the full scope of works (explained further below); and 
(b) 
identifying and properly allocating risks to the party best placed to address those 
risks (including, where that party is the Council, ensuring that the Council is 
properly remunerated for those risks). 
3.2.  The form of contract should be appropriate for dredging services.  In our view, an 
industry standard construction contract (e.g. NZS 3910 – 3916 suite) is not 
appropriate for dredging services.  There are considerations which are unique to 
dredging operations that are not addressed in a construction contract (and vice versa).  
We suggest that the Council considers either:  
(a) 
preparing a template dredging contract which is specifically designed for 
dredging services by the Council using Kawatiri; or  
(b) 
uses the standard form "FIDIC® Form of Contract for Dredging and Reclamation 
Works".  
One advantage of the FIDC form of contract is that has the same 'look and feel' as a 
standard construction contract (an "Appendix" of specific details, bespoke "Particular 
Conditions" if required and a set of "General Conditions"), so we expect that Council 
staff will find it relatively user friendly, yet it is specifically designed for dredging (both 
capital and maintenance dredging, as well as reclamation work and ancillary 
construction) and somewhat simpler than a standard form construction contract. 
Scope of works 
4. 
As noted above, proper upfront definition of the scope of the required works is crucial – to 
identify risks, properly price the works and properly plan the execution of the works. Scope 
issues include the following: 
4.1.  Soils information: Good quality and comprehensive information on the nature and 
extent of the soils to be dredged and disposed of is required. Failure to obtain, and 
properly take account of the implications of, this information prior to contracting is 
likely to lead to delays and additional costs.  Consider how much material needs to be 
removed (and/or to what depth) and from what areas.  Put another way, what is the 
CSD-370207-1-14-1 

 
definition of 'success'?  Understand where the disposal areas are and any 
access/timing issues – how long will it take to sail from the dredging area to the 
disposal area? 
4.2.  Environmental information: This information will be required in order to obtain the 
necessary consents for the works but will also be important to the contractor's ability 
to properly scope the works (e.g. tidal information and hydrographic plans). 
4.3.  Measurement: It is necessary to specify a method and process for measurement of the 
dredging works (including calibration of measurement equipment and supervision and 
timing of measurement). Typically there will be 'in' and 'out' surveys at the beginning 
and end of the works and interim surveys for payment certificates. Consider whether 
there should be defined "tolerances" for the works (relative to the defined scope 
requirements) for both payment and completion. 
5. 
Normally the design of the works is a matter for the client (called the "Employer" in the 
FIDIC form of contract) but if the contractor is to have some design responsibility it is 
essential that the Employer’s requirements are described clearly and precisely.  The FIDIC 
contract Guidance Notes suggest the following relevant considerations: 
5.1.  the purpose for which the works are required; 
5.2.  the size, speed and draught of vessels using the relevant harbour/waterway; 
5.3.  the design storm surge level and wave height and period; 
5.4.  the earthquake forces to be accounted for; 
5.5.  the stability criteria; and 
5.6.  the volume of acceptable over-topping. 
Programme for works 
6. 
Once the overall scope of the works is ascertained, a specific programme for carrying out the 
works should be prepared and agreed.  Consider the following: 
6.1.  Usually, efficient and cost effective dredging works requires the contractor to be able 
to work continuously by day and by night.  Ideally, the contractor would obtain 
contractual assurance that he is able to do that. Consider what might interfere with 
continuous works (e.g. shipping) and develop a programme (and a remuneration 
model) to mitigate (and/or compensate the contractor for) interruption and 
interference. 
6.2.  Normally the contract will expressly provide for the client ("Employer") to 'take over' 
each area in respect of which the dredging work has been completed (i.e. in sections, 
rather than the entire programme when all works are completed).  Otherwise, the 
contractor will effectively be responsible for the maintenance of the dredging work 
after completing each section. 
6.3.  A right for the contractor to be able to influence the scheduling of the dredging 
programme, postpone the commencement of a dredging programme and/or suspend 
works during a dredging programme, in order to return home as and when necessary 
to attend to "emergency dredging" of the Buller River (or at any other port) to clear 
the navigational channel and enable normal shipping operations to safely continue 
following a storm or other event. 
Timeframes 
7. 
The contract would normally define a "Commencement Date" and a "Time for Completion" 
for the works. Obviously care is needed to ensure those dates/timeframes are achievable, 
having regard to the scope and programme factors outlined above.  Issues to watch out for 
here include: 
7.1.  When the contractor is entitled to an extension of time.  The FIDIC form of contract set 
out a series of "Defined Risks" for which an extension of time is permitted (discussed 
in paragraphs 8-9 below).  The contractor should consider any other circumstances in 
which further time should be allowed for the works (i.e. how might delays arise which 
the contractor should not be responsible for?). 
CSD-370207-1-14-1 
Page 2 

 
7.2.  Any contractual consequences of late completion.  The FIDIC form of contract 
contemplates liquidated damages being payable by the contractor, although in our 
experience LDs are often successfully resisted/rejected by a contractor. 
Defined Risks 
8. 
The FIDIC form of contract provides for prescribed "Defined Risks", the implications of which 
are placed on the client/Employer.  Regardless of the form of contract used, the concept is 
important – in what circumstances should the contractor be relieved of liability (including for 
delay) and/or be entitled to recover additional costs? 
9. 
These Defined Risks are typically force majeure type events (i.e. events/circumstances 
outside the contractor's control), including: 
9.1.  "interruptions due to ship movements in excess of those specified in the Contract 
Data" 
9.2.  "climactic or hydrological conditions more adverse than those specified in the Contract 
Data" 
9.3.  Unforeseeable physical obstructions or conditions. 
The contractor should consider what other events/circumstances should be client, not 
contractor, risks. 
Engineer 
10. 
Just like for construction contracts, it is usual for dredging contracts to make provision for an 
"Engineer", often an employee of the client, to be responsible for valuing, certifying and 
making determinations in relation to the dredging works. While the Engineer is required to 
act promptly and fairly, the contractor may wish to insist upon an independent expert to fill 
this role. 
Pricing/remuneration 
11. 
There are a number of different pricing models for dredging work, like with construction 
works. Examples include: 
11.1.  lump sum price;  
11.2.  re-measurement (i.e. a fixed sum, subject to re-measurement at agreed rates);  
11.3.  cost plus; and 
11.4.  schedule of rates. 
12. 
Consider the following different types of rates: 
12.1.  hourly rate;  
12.2.  tonnage rate;  
12.3.  standby rate (when unable to dredge due to Defined Risks or client suspensions (e.g. 
for shipping));  
12.4.  periodic (e.g. daily) layup charge (for extended suspensions where, for instance, it 
may be possible to demobilise the crew but not the vessel); 
12.5.  mobilisation and demobilisation charges. 
13. 
The selection of the appropriate pricing methodology will depend, among other things, on the 
efficiency of the dredging operations, taking account of the likelihood of interruptions, 
characteristics of the soils being dredged, location of dumping grounds relative to the 
dredging areas, etc. 
14. 
Other issues for consideration include the following: 
14.1.  What other costs may be incurred by the contractor are those costs taken into account 
in the remuneration arrangements (either as an additional charge payable by the client 
or the risks/costs are factored into the contractor's rates/price). For example: 
(a) 
consents; 
(b) 
travel, accommodation, crew shift changes, other crew costs; 
CSD-370207-1-14-1 
Page 3 

 
(c) 
port costs (including, wharfage, berthage (including for bunkering), pilotage);  
(d) 
dumping fees. 
14.2.  Should the contract include minimum aggregate charge payable to the contractor for 
the dredging works, either for a particular dredging programme or over the term of a 
contract if not one-off? 
14.3.  In the case of a contract for works of long duration, allow adjustment for the "rise and 
fall" in the cost of resources such as labour, materials and fuel. Often such an 
adjustment mechanism is linked to an appropriate public index or components of an 
index (e.g. CPI) 
Payment 
15. 
When can the contractor render invoices and what are the payment terms?  Consider the 
following: 
15.1.  advance payments to fund mobilisation costs; 
15.2.  periodic interim payments – typically monthly.  Payment could also be based on the 
achievement of milestones or a schedule of activities to which values are assigned; 
15.3.  retentions. 
Performance security 
16. 
Will a bank guarantee or other form of performance security be required by the client?  If so, 
the amount should reduce pro-rata to the sections of work taken over by the client following 
completion so that the contractor minimises the cost and risk of the guarantee.  Those 
guarantee costs also need to be factored into the contractor's pricing. 
Liability limits 
17. 
The contract should include limitations and exclusions on the contractor's liability: 
17.1.  Any liability for indirect and consequential loss, loss of profit, loss of contract, loss of 
opportunity, and special, exemplary or punitive loss/damage should be entirely 
excluded. 
17.2.  A per event and/or aggregate liability cap should be included. There is no single right 
or wrong answer to the calculation of such limits. A contractor friendly option is for a 
limitation to be linked to the total amount paid or payable by the client. At worst, 
ensure any limitation is consistent with the amount recoverable (or recovered) under 
insurance. 
17.3.  A defects liability/permitted claim period should be included. As in construction 
contracts, that period is commonly 1 year from completion. 
Insurance 
18. 
We recommend that the Council carefully reviews its current insurance programme 
(including, if thought appropriate, consulting with expert brokers) to ensure that the 
appropriate type and level of cover is in place for dredging services. It is trite to say that 
dredging services are not 'ordinary course' activities for most councils so the unique risks of 
dredging services and dredging vessels are unlikely to be addressed with standard liability 
policies. Similarly, double insurance should be avoided. 
19. 
While we are not insurance experts, we understand that relevant insurance cover for 
dredging services includes the following: 
19.1.  Material damage (e.g. a "hull and machinery" policy). 
19.2.  Protection and indemnity (including for oil pollution and wreck removal).  A P&I policy 
is a form of marine insurance which we understand is different in scope to standard 
public liability cover. 
19.3.  Contract works would normally only be required for marine construction works 
involving more than just dredging. For dredging works alone, our understanding is that 
contract works insurance is generally not suitable/necessary.  
19.4.  Professional indemnity cover would only be required if the Council is responsible for 
some or all of the design of the dredging works. 
 
CSD-370207-1-14-1 
Page 4 


 
 
 
Chris Dann 
Partner | Head of the Corporate Advisory team 
 
 
E: chris.dan[email address] 
P: +64 3 964 5835 
M: +64 27 672 8721 
 
Summary 
 
Chris’ in-house experience in the UK as Corporate Legal Manager at Exel Plc, then the world’s 
largest logistics company, provided him with a commercially pragmatic approach and an in-depth 
understanding of the shipping and logistics industry.  
 
He has continued to develop this expertise and is now regarded as one of the country’s leading 
transport and logistics lawyers.  Chris is ranked as a "Leading Individual" in the 2018-2021 Legal 
500 Asia Pacific Guides. In 2020 he was awarded the Chartered Institute of Logistics and 
Transport's Communication Award for his contributions to the sector. 
 
Chris heads Anthony Harper's corporate advisory team and has over 20 years’ of experience in 
commercial contracts, procurement, manufacturing, supply and distribution, corporate structuring 
and governance, joint ventures and mergers and acquisitions. 
 
Examples of work 
• 
Advising Lyttelton Port Company on a range of development, transport, logistics, relationship 
and procurement arrangements (including dredging works; and vessel, crane and container 
handling equipment procurement (construction, purchase, hire and charter)). 
• 
Acting for a number of Ports in preparing and negotiating container terminal, depot services 
and stevedoring/marshalling agreements with shipping lines and other parties. 
• 
Advising CentrePort in relation to the establishment of its inland container terminal in 
Wanganui and on a range of services and relationship arrangements (including with KiwiRail 
for CentrePort’s “CentreRail” freight transportation service). 
• 
Advising Southland District Council on both template and bespoke procurement contracts for 
services and minor works. 
• 
Advising Southland District Council on the procurement process and approach and regulatory 
issues and implications in relation to contracts for community services, including under the 
Local Government Act and Local Authorities (Members' Interests) Act 1968, following a 
service delivery review under s17A of the LGA. 
• 
Lead advisor to the Ministry of Business, Innovation and Employment in relation to the 
domestic and international procurement of petroleum reserves for the New Zealand 
Government, including tendering, procurement and probity advice and documentation, 
tender evaluation, and contract drafting and negotiation. 
 
CSD-370207-1-14-1 
Page 5 

Ray Mudgway
Managing Director
+ 64 27 575 7993
[email address]