Thank you for your information request dated 18 December 2024, for information about the 
cost to repair the Te Wero Wynyard Crossing Bridge. The specific details of your request 
and our response is below. 
 
•  I would like to see itemised breakdown of repair costs $11m in total for Wynard 
bridge 
 
The budget to repair the bridge was based on a competitive process. The project was 
tendered and costs were determined by Contractors based on defined scope. 
Contingency levels were set based on risk profile for the project in line with industry best 
practice. These costs were reviewed by a quantity surveyor within the wider project 
team. The figures are broken down further below.  
 
Workstream 
Estimate at completion 
DELIVERY 
 
MAIN CONTRACT / STRUCTURAL 
 
Contract Award Value 
4,903,383 
Miscellaneous Repairs 
114,898 
Additional Inspections 
79,208 
Structural Steel Repairs 
357,666 
Structural Modifications 
67,313 
Additional Coating Scope 
15,000 
Additional Corrosion Protection 
45,000 
Additional JUB Hire 
122,551 
MC / STRUC. SUB-TOTAL 
5,705,019 
MECHANICAL 
 
Early Works and Procurement 
1,044,517 
Mechanical Modifications 
106,943 
Mechanical Reinstall 
645,710 
Private Bag 92300, Auckland 1142  |  aucklandcouncil.govt.nz  |  Ph 09 301 0101 

Workstream 
Estimate at completion 
ELECTRICAL 
 
Electrical Component Replacement 
982,800 
Electrical Reinstall & Commissioning 
257,000 
M&E SUB-TOTAL 
3,036,969 
MISC. / OTHER COSTS 
44,904 
DELIVERY SUB-TOTAL 
8,741,988 
INTERNAL RESOURCES 
134,192 
CONSULTANCY 
532,265 
CONSENTS 
15,283 
  C&C SUB-TOTAL 
547,548 
CONTINGENCY 
 
   Contingency - General 
662,804 
   Contingency - Acceleration 
499,200 
CONTINGENCY SUB-TOTAL 
1,162,004 
TOTAL 
10,630,636 
 
With respect to the required main contract/ structural repair work, the full extent of 
corrosion only became known once the bridge was dismantled and high-pressure water- 
and abrasive blasting was underway, allowing full inspection of the steel structure. 
 
Sub-standard welds and previous repairs were also discovered once the old protective 
paint coating was fully removed. These were remediated as part of this project. 
 
There have been numerous condition assessments done on the bridge in previous 
years, however the full extent of the corrosion could only be understood while the bridge 
was dismantled and could be fully inspected. 
 
Following the dismantling of the bridge and thorough inspection of its Mechanical & 
Electrical parts was completed. The repair works includes full replacement and upgrades 
of all electrical panels, hardware, software and lighting, except for the drives and motors, 
which were refurbished. 
 
There is considerable information regarding the Wynyard Crossing Bridge available on 
our website which may assist. Some links below. 
 
https:/ www.ekepanuku.co.nz/projects/wynyard-crossing-bridge-maintenance/ - please 
note this project page has links to all previous notifications and newsletters at the bottom 
 
https:/ www.ekepanuku.co.nz/news/december-explainer-returning-te-wero-wynyard-
crossing-bridge-to-service/ 
 
https:/ www.ekepanuku.co.nz/news/frequently-asked-questions-wynyard-crossing-
bridge/ 
 
Previous LGOIMA request responses regarding the bridge can be found on our website 
here below the board information: 
Private Bag 92300, Auckland 1142  |  aucklandcouncil.govt.nz  |  Ph 09 301 0101 


https:/ www.ekepanuku.co.nz/about/public-information/ 
 
The decision by Auckland Council to release the information contained in this response was 
made by Letitia Edwards, Acting General Manager Assets and Delivery, Eke Panuku 
Development Auckland. 
 
You have the right to seek an investigation and review of this response by the Ombudsman. 
Information about how to make a complaint is available at www.ombudsman.parliament.nz 
or freephone 0800 802 602. 
 
If you have any questions please contact me at [email address] or 
contact me on 09 301 0101, quoting LGOIMA No. 8140015162. 
 
 