From: Dave Smith
Sent: Friday, September 1, 2023 11:45 AM
To: Patrick Hanaray <[email address]>
Cc: Suzanne Rushmere <[email address]>; Jared White
Subject: Upper Hutt Future Model Development
Hi Patrick
Firstly, a very quick note to say that our Messines Ave survey yesterday morning and afternoon was successful and
the modelling is progressing well.
Thanks again for your support with the Upper Hutt modelling. Below is a quick summary of the scope of our existing
commission (in italics):
Stages
Update base year model to 2022 - we recommend a base year of 2022 as opposed 2023 as part of the base
model update will require validation against traffic counts and travel time data to ensure it replicates on-the-
ground traffic behaviour in the base year. This would typically be representative of activity levels in
March. As there are likely to be few if any traffic counts available in March 2023 we recommend the base
year reflect March 2022. Specific subtasks include:
a. Update transport network to 2022 including all new roading projects and new subdivision activity
since 2009 base model
b. Prepare 2022 land use file based on 2018 census data and consent data from 2018-2022. We will
also source education rolls from Ministry of Education and liaise with GWRC regarding boundary
conditions and through traffic which can be sourced from the WTSM model.
c. Update model file structure to 2022 base year and test to run on latest Tracks software
d. Collect traffic count data from Council and Waka Kotahi (we have direct access to WK TMS system
already)
e. Extract travel time data from Tomtom analytics for key corridors
f. Validate 2022 morning peak, interpeak and evening peak traffic models to meet Waka Kotahi’s
Transport Model Development Guidelines validation criteria
g. Converge models to meet Waka Kotahi’s Transport Model Development Guidelines model
convergence criteria
h. We will also factor together an all day traffic model from the three period models using local daily
traffic profiles
i. Prepare a technical note summarising the model update process, inputs, validation and convergence
performance
Benchmark new base model against previous set of models – this will involve the preparation of a short
technical note which presents traffic volumes (at key locations), network travel totals and network
deficiencies in the road network from the previous model (2006 and 2026 years) compared to the same from
the newly updated 2022 model. They will be presented in the form of tables and link and intersection Level of
Service and provide a clear picture of how network performance has changed over this period.
Build 2033, 2043 and 2053 future models – three future morning peak, interpeak and evening peak models
(that is nine in total) will be prepared. Specific subtasks for all three future year sets of models include:
a. Update transport networks to 2033/43/53 including all planned and committed roading projects and
new subdivision activity since 2022 base model
b. Prepare 2033/43/53 land use files based on urban growth forecasts and other resources/directives
from Council. We will liaise with GWRC regarding boundary conditions and through traffic which can
be sourced from the WTSM model.
c. Update model file structure to 2033/43/53 and test to run on latest Tracks software
2
d. Converge models to meet Waka Kotahi’s Transport Model Development Guidelines model
convergence criteria
e. We will also factor together an all day traffic model from the three period models using local daily
traffic profiles
f. Prepare a technical note summarising the future model development process, inputs and
convergence performance
Future model deficiency analysis – we will run all models to produce traffic volumes (at key locations),
network travel totals, and link and intersection Level of Service outputs in the same manner as the previous
study. These would be prepared for each year and each period (morning peak, interpeak and evening
peak). The output will be a fourth technical note which presents deficiencies (in terms of Level of Service) as
well as travel totals on the road network for each year and include commentary as to how network
performance changes over this period.
Fee estimate
The total fees excluding GST for each stage are as fol ows:
1. $36,000 (which includes budget for [purchasing Tomtom data for travel time validation)
2. $5,000
3. $25,000
4. $10,000
The total fees are estimated to be $76,000 + gst.
We note that Stages 1 and 2 are 100% complete and to date two variations have been approved as follows:
Variation 1 - Additional Modelling Task 1 - Trentham Mixed Use Development – total fees $8,500 and is
100% complete
Variation 2 - Additional Modelling Task 2 - Messines Ave Paramics Model Build and Test – total fees are
$20,250 and work is ongoing
With respect to next steps and acknowledging the scope of works received on 26th July 2023 from Suanne Rushmere
and subsequent traffic modelling phasing and numbers received on 31st August (which supercedes much of the
earlier email), the fol owing tasks (and fees) are recommended:
Stage 3 as above from original scope aligning with Scenario 1 for all three years = $25,000 (note $1,500 of this
$25,000 has been invoiced to date)
A new stage 3a is then proposed to address the scenario assessments as follows:
a) Re-run 2053 models to reflect Scenario 2 and Scenario 3 alternative land use scenarios
b) Undertake a sensitivity test on one 2053 scenario to consider the impact of a higher level of mode share
c) (only if required) run 2033 and 2043 models to reflect Scenario 2 and Scenario 3 alternative land use
scenarios
Total fees for Stage 3a if only the 2053 models and sensitivity test tasks (that is a) and b) above) are completed is
$6,000 + gst or if 2033 and 2043 models are also run for scenarios (that is a), b) and c) prepared) is $14,000 + gst.
Stage 4 is then more extensive to capture the reporting for all scenarios to include Scenario 2 and Scenario 3
outputs. Total fees to capture all reporting for Stage 3 as per original offer of service is $10,000 + gst. This is no
superceded by total fees to include reporting for Stage 3 and Stage 3a (2053 only) is $14,000 + gst or Stage 3 and
Stage 3a reporting (if 2033, 2043 and 2053 all run) is $20,000 + gst.
Summary of fees going forwards (noting that $1,500 + gst of this has already been invoiced under Stage 3) is then:
Stage 3, 3a and 4 fees is Scenarios 2 and 3 run at 2053 only: $45,000 + gst (corresponding to a $10,000 extension to
existing Stage 3 and 4 fees); or
Stage 3, 3a and 4 fees is Scenarios 2 and 3 run at 2033, 2043 and 2053: $59,000 + gst (corresponding to a $24,000
extension to existing Stage 3 and 4 fees).
Feel free to contact me if you require any more detail, points of clarification, or a more formal offer of service.
3
Regards
Dave
Dave Smith MPhil BTech(Hons) CMILT MEngNZ
Technical Director, Transportation Planning
Auckland + Wellington + Christchurch
abley.com
Be inspired - sign up now!
The information contained in this email and any attachments is confidential and intended for the
named recipients only. If you are not the intended recipient, please notify the sender immediately
and delete this email.
4