30 October 2023 
 
 
Barry Murphy 
[FYI request #24278 email] 
 
 
Dear Mr Murphy 
 
Thank you for your emails of 29 September and 11 October 2023 to Kāinga Ora – Homes 
and Communities, requesting information about the proposed Teitei Drive, Ohakune 
development under the Of icial Information Act 1982 (the Act). I have answered your 
individual questions below. 
 
Request of 29 September 2023: 
 
1./ Please provide costings and quotes and emails from TLC to connect power  
 
At the time of your request, Kāinga Ora had not received any costings or quotes from TLC 
to connect power, and therefore I am declining this part of your request under section 
18(e) as the information did not exist. However, subsequent to receiving your request, 
Kāinga Ora received and accepted a quote for a study to be undertaken with TLC to 
commission a study and produce cost estimates of the network upgrades required to cater 
for new proposed Teitei Drive subdivision. The quoted cost for this study is 
$4,000-$6,000. Once complete, this will inform the final scope of works put in place for the 
provision of power. 
 
2./ Please provide costings and quotes from Chorus and emails to connect 
telecommunications. 
 
Kāinga Ora has engaged Chorus for $2,500 to undertake early design. This work will 
inform the final scope of works put in place for the provision of telecommunications. 
Emails between Kāinga Ora and Chorus relating to telecommunications are attached. I 
have withheld names and contact details of Chorus and Cheal staff, and Kāinga Ora staff 
mobile numbers, under section 9(2)(a) of the Act to protect privacy. 
 
3./ Please provide latest contracted amounts for Teitei by table with headings: 
- contracted company 
- value signed 
- total amount agreed for contingency (or max contract value) 
- amount spent to date 
 
Please see attached spreadsheet. 
 
4./ Please list any contracts that have not yet been signed to date and the 
estimated value of the spend, for the avoidance of doubt, if water has not yet been 
quoted from Veolia then list it along with the latest total estimated cost. 
 

A full procurement plan will follow completion of the detailed design of the proposed site. I 
am withholding information relating to contracts that have not been signed and estimated 
costs under section 9(2)(b)(ii) as the release of this information “would likely unreasonably 
to prejudice the commercial position of the person who supplied or who is the subject of 
the information”. This information is also withheld under section 9(2)(j) to allow Kāinga Ora 
to “carry out, without prejudice or disadvantage, commercial activities”. 
 
5./ Please advise what costs Ruapehu District Council is required to pay. 
 
6./ Please provide the costing or estimates of future maintenance RDC will need to 

pay, i.e. 
- $x per annum for swales 
- $x per annum for detention ponds maintenance 
- $x per annum for pumping station maintenance 
- $x per annum for power for street lighting 
- $x per annum for road maintenance 
- $x per annum for mowing berms 
 
Kāinga Ora does not hold information relating to Ruapehu District Council costs. However, 
I note that the costs you requested cannot be determined prior to settling on an agreed 
design for the development. 
 
I understand that you asked these same questions (5 and 6) to the Council. They will 
respond to you in due course. 
 
Request of 11 October 2023: 
 
7./ Please provide all the costs or estimates along with a breakdown of what they 
are for, i.e. water, power, etc. 
 
I refer you to questions 3 and 4. 
 
8./ Please provide the cost estimate from The Lines Company (TLC) for providing 
power for the 47 connections that was requested. 
 
I refer you to question 1. 
 
9./ What is the total cost TLC is charging (i.e. if there are transformer costs that 
TLC are not paying for or have requested be shared cost). 
 
I refer you to question 1. 
 
10./ OIA documents revealed that a budget increase of $2m would be covered by 
KO. What caused these increases, please provide information on the amount and 
the service to which it relates, i.e. design, surveyors, earthworks, etc. 
 
Updated budget assessments are made periodically throughout the preliminary stages of 
a project and take into account current estimated values for proposed works, including 
market pricing. Al  budgets remain estimates and subject to change until services are 
contracted based on final design. 
 
Under section 9 of the Act, I consider that the public interest does not outweigh the 
reasons for withholding the information. You have the right to seek an investigation and 
review by the Ombudsman of my decision to withhold some information. Information about 


how to make a complaint is available at www.ombudsman.parliament.nz or Freephone 
0800 802 602. 
 
Please note that Kāinga Ora proactively releases our responses to official information 
requests where possible. Our response to your request may be published at 
https:/ kaingaora.govt.nz/publications/official-information-requests/ with your personal 
information removed. 
 
 
Yours sincerely 
 
Mark Fraser 
General Manager - Urban Development and Delivery