File ref: IRC-5319 
19 September 2023 
 
John Doe 
[FYI request #23848 email] 
 
Kia ora 
 
Kent Terrace Cycleway 

 
Thank you for your request made under the Local Government Official Information and Meetings 
Act 1987 (the Act), received 15 August 2023. You requested the fol owing information: 
 
1. Traffic Model ing, Reporting and Calculations (Including SIDRA analysis) as it relates to the 
newly instal ed cycleway along Kent Terrace. To understand the predicted level of service 
decrease/increases for the following intersections: 
 
a) Oriental Parade and Cable Street. 

b) Kent Terrace and Courtenay Place 
c) Kent Terrace and State Highway 1 
 
2. What validation has been completed by WCC, since the instal ation of the cycleway including 

independent road safety audits and verification of the predicted level of service 
decrease/increases. 
 
Wel ington City Council has granted your request for information. Please see the below response 
to your questions. 
 
1. Traffic Modelling, Reporting and Calculations (Including SIDRA analysis) as it relates to the 
newly instal ed cycleway along Kent Terrace. 
 
Appendix 1 contains the modelling for intersections Kent Terrace and Courtenay Place and Kent 
Terrace and State Highway 1. Cable Street and Oriental Parade were not changed significantly 
enough to warrant the model ing resource. 
 
2. What validation has been completed by WCC, since the instal ation of the cycleway including 
independent road safety audits and verification of the predicted level of service 
decrease/increases. 
 
The transitional approach al ows us to implement changes to the roadway quickly and with 
adaptable materials, so generally minimal modelling is done on these projects as we can respond 
to issues as needed. On Cambridge Terrace we have already been able to address some 
congestion issues caused by the initial storage space in the Elizabeth St turn bay. 
 
 
 
 
 

While we have been preliminarily monitoring queue lengths and any pressing issues, most of the 
post-instal ation evaluation wil  not begin until 6 to 8 weeks after instal ation as users need this 
time to adapt to the new layout and flows to normalise. However, we can share that the predicted 
queues on Cambridge Terrace at Vivian Street are notably shorter than predicted by model ing. 
Further qualitative feedback wil  be col ected during the feedback phase of the project beginning 
mid-September. While not completed post instal ation, we have included the latest independent 
road safety audits on the 90% designs which may be of interest to you. 
 
Below are the documents that fal  in scope of your request and my decision to release the 
document.   
 
  Item   Document name/description  
Decision  

 Appendix 1 – Model ing 
Released 

Appendix 2 – Road Safety Audit 
Released 
 
 
Right of review 
If you are not satisfied with the Council’s response, you may request the Office of the Ombudsman 
to investigate the Council’s decision. Further information is available on the Ombudsman website, 
www.ombudsman.parliament.nz. 
 
Please note, we may proactively release our response to your request. 
 
Thank you again for your request, if you have any questions, please feel free to contact me. 
 
Ngā mihi nui 
 
 
Amber Smith 
Senior Advisor Official Information 
Wellington City Council   |   2 of 2