Re: Telco Infrastructure 
 
 
Thank you for your email of 3 May 2023. Your specific request and our response are set out below. 
  1.  What is the total number of tower/ pole/ light or building mounted sites that are currently in 
operation on land controlled by Auckland Council.  
 
10 on Tātaki Auckland Unlimited sites 
45 on Eke Panuku sites 
 
2.  How many new sites proposed for Auckland Council land that are not yet in operation is 
Auckland Council aware of/ have applications for. 
 
1 (one) for East Stand at Mt Smart Stadium 
  3.  How many existing sites have upgrade applications or notifications in with Council. 
 
0 (Zero) Currently 
 
4.  How long is the lease term for existing sites and what is the average lease fee/ administration 
fee per site. 
 
Tātaki Auckland Unlimited sites (10) 
 
Facility Name 
Lessee 
Lease Start Date 
Lease renewal due 
Mt Smart Stadium 
Spark New Zealand Trading Ltd - MSS 
31/10/2014 
30/10/2020 
Mt Smart Stadium 
Kordia Limited 
01/04/2017 
31/03/2022 
Mt Smart Stadium 
Vodafone New Zealand Ltd C/- Colliers International 
28/07/2015 
27/07/2025 
New Zealand Maritime Museum 
Spark 
01/08/2014 
28/02/2027 
New Zealand Maritime Museum 
Vodafone NZ Ltd 
15/02/2017 
31/03/2027 
North Harbour Stadium 
Spark New Zealand Trading Ltd - NHS 
01/06/2018 
31/05/2024 
North Harbour Stadium 
Kordia Limited 
01/04/2018 
31/03/2023 
Private Bag 92300, Auckland 1142 | aucklandcouncil.govt.nz | Ph 09 301 0101 

Vodafone New Zealand Ltd 
North Harbour Stadium 
C/- Colliers International 
01/03/2019 
24/02/2024 
Western Springs Stadium 
Spark New Zealand Trading Ltd - WSS 
01/09/2015 
31/08/2021 
Vodafone New Zealand Ltd 
Western Springs Stadium 
C/- Colliers International 
28/07/2015 
27/07/2025 
    
TAU’s lease ‘initial’ terms are mostly between 4-6 years, though some agreements are for 10 years. 
The leases with shorter terms generally have renewal clauses which allows the parties to extend the 
leases once or twice more, typically for the same ‘initial’ duration. 
 
The fee information is commercially sensitive. TAU has only 4 sites with a telco cellular antennas or 
satellite on floodlight poles, therefore disclosing even the average fee may potentially jeopardise 
any future lease negotiations with the suppliers. 
 
Eke Panuku Sites (45) 
 
The term of Eke Panuku managed telecommunications licences range from 3 months to 30 years, 
typically with initial terms of  4-6 years with several rights of renewal of similar term. In many cases 
these are the terms granted by the previous owner of the site and inherited by Eke Panuku when 
the site was purchased.   
 
New telecommunication licences negotiated by Eke Panuku wil  generally have terms of 5 years 
with no rights of renewal, with some variation if required for site specific circumstances. 
 
The range of fees for the 45 Eke Panuku telco sites is $0 to $28,400 + GST per annum.  
 
The average fee for the 45 Eke Panuku telco sites is $10,148.80. 
 
Decisions relating to the information contained in this response (q’s 1-4) was made by Paul Tyler, 
General Manager Property, for Tātaki Auckland Unlimited sites, and a senior manager with the 
delegated authority from the Chief Executive of Eke Panuku
 
                 
5.  How many proposed tower/ pole/ light/ building mounted site proposals or installation designs 
have been modified by Auckland Council. Please include the details of the initial proposed 
locations or designs and the final locations or designs as put forward by Auckland Council. 
 
We are unable to respond to this portion of the request under Section 17(e) of the Local 
Government Of icial Information and Meetings Act 1987, where the information requested 
does not exist. 
  6.  Was there any design review process to optimise the look of the tower/ pole/ streetlight and 
building mounted towers to minimise the impact on visual amenity. If so can you please 
provide the details of this process, and explain how the current grey cylinder look was 
decided upon.  
 
We are unaware of who designed the ‘current grey cylinder’ and there is no set Auckland 
Council review process. In the majority of cases, the telcos were in place on the land when 
the land was purchased by Auckland Council  
 
Private Bag 92300, Auckland 1142 | aucklandcouncil.govt.nz | Ph 09 301 0101 


7.  What affected party notification process does the Council undertake in relation to sites on 
land controlled by it, or sites on land controlled by a CCO or private landowner i.e., 
Notification of Council or/ Local Board/ Resident or Ratepayer. Please provide details of this.  
  The is no set notification process.  As mentioned above most of the telco installation existed 
on the land prior to Auckland Council purchasing the property or the property is otherwise 
transferred to Eke Panuku.  
 
The decision by Eke Panuku to release the information contained in this response (q’s 5-7)was 
made by a senior manager with the delegated authority from the Chief Executive of Eke 
Panuku. 
 
Should you believe Auckland Council has not responded appropriately to your request, you have the 
right by way of complaint, under section 27(3) of the LGOIMA, to apply to the Ombudsman to seek 
an investigation and review of the decision. 
Information about how to make a complaint is available at www.ombudsman.parliament.nz or 
freephone 0800 802 602. 
 
If you have any further queries, please contact me on 09 301 0101 quoting official information request 