This is an HTML version of an attachment to the Official Information request 'Addition of Beach and Bay Streets to HA08 in PC56'.


30 June 2023 
 
 
 
 
 
 
Chris Milne 
Susan Sales 
Senior Advisor Official Information and Privacy 
[FYI request #22647 email] 
04 570 6666 / 0800 488 824 
[email address] 
Our reference: LGOIMA 
 
 

Dear Chris 
Request for Information – Local Government Official Information and Meetings Act 1987 
(LGOIMA) 

We refer to your official information request dated 3 May 2023 for information, from 1 February 
2023, about the addition of Bay Street and Beach Street to HA08.  
The information you have requested in questions 1 - 3 is enclosed (see Appendix 2). Our 
response to question 4 was provided to you on 30 May 2023. 
Some parts of this information have been withheld under sections 7(2)(a), 7(2)(f)(i) and 7(2)(g) 
of the LGOIMA.  More detail on these withholding grounds is provided in Appendix 1 of this 
letter.  In making the decision to withhold this information, we have determined that the 
withholding of that information is not outweighed by other considerations which render it 
desirable, in the public interest, to make that information available. 
Please note that this response to your information request and your name may be published 
on Hutt City Council’s website, on the following link: www.huttcity.govt.nz/council/contact-
us/make-an-official-information-act-request/proactive-releases 

You have the right to seek an investigation and review by the Ombudsman of this response. 
Information about how to make a complaint is available at www.ombudsman.parliament.nz or 
freephone 0800 802 602. 
 
Yours sincerely 
 
Susan Sales 
Senior Advisor Official Information and Privacy 
 
Encl:-   
Appendix 1 – Section 7(2) withholding grounds 
Appendix 2 - HA08 attachments 

Appendix 1 – Section 7(2) LGOIMA withholding grounds 
(2) Subject to sections 6, 8, and 17, this section applies if, and only if, the withholding of  the 
information is necessary to— 
(a) protect the privacy of natural persons, including that of deceased natural persons; or 
(b) protect information where the making available of the information— 
(i) would disclose a trade secret; or 
(ii) would be likely unreasonably to prejudice the commercial position of the person who 
supplied or who is the subject of the information; or 
(ba) in the case only of an application for a resource consent, or water conservation order, or a 
requirement for a designation or heritage order, under the Resource Management Act 1991, to 
avoid serious offence to tikanga Maori, or to avoid the disclosure of the location of waahi tapu; 
or 
(c) protect information which is subject to an obligation of confidence or which any person has 
been or could be compelled to provide under the authority of any enactment, where the making 
available of the information— 
(i) would be likely to prejudice the supply of similar information, or information from the 
same source, and it is in the public interest that such information should continue to be 
supplied; or 
(ii) would be likely otherwise to damage the public interest; or 
(d) avoid prejudice to measures protecting the health or safety of members of the public; or 
(e) avoid prejudice to measures that prevent or mitigate material loss to members of the public; 
or 
(f) maintain the effective conduct of public affairs through— 
(i) the free and frank expression of opinions by or between or to members or officers or 
employees of any local authority, or any persons to whom section 2(5) applies, in the 
course of their duty; or 
(ii)  the  protection  of  such  members,  officers,  employees,  and  persons  from  improper 
pressure or harassment; or 
(g) maintain legal professional privilege; or 
(h)  enable  any  local  authority  holding  the  information  to  carry  out,  without  prejudice  or 
disadvantage, commercial activities; or 
(i)  enable  any  local  authority  holding  the  information  to  carry  on,  without  prejudice  or 
disadvantage, negotiations (including commercial and industrial negotiations); or 
(j) prevent the disclosure or use of official information for improper gain or improper advantage. 
 

BEFORE THE INDEPENDENT HEARINGS PANEL 
IN THE MATTER OF: 
Hutt  City  Proposed  District  Plan 
Change  56:  Enabling  Intensification 
in Residential and Commercial Areas 
SECTION 42A REPORT OF CHESSA STEVENS – HERITAGE ASSESSMENT 
Dated 7 March 2023 
under the Local Government Official Information and Meetings Act
Released 


 
Submissions for the Extension of the Petone Foreshore Heritage Area  
43. The heritage values of the Petone Foreshore Heritage Area can be summarised 
as follows: 
(a)  The area has high historic values as an example of some of the earliest 
Act
residential development in Wellington. 
(b)  The area has high physical values derived from the consistent late 19th 
and  early  20th  century  subdivision  patterns,  and  the  integrity  of  its 
Meetings 
traditionally constructed late 19th and early 20th century timber frame 
buildings.  There is also high potential for further information about 
and 
the  past  of  Petone,  Lower  Hutt  and  New  Zealand  to  be  revealed 
through investigation by archaeological methods. 
(c)  The area has high social values, holding sentimental significance for 
Information 
the  generations  of  people  who  have  lived  there,  and  being  well 
recognised by the community as contributing to the shared history and 
identity of Petone. 
Official 
(d)  The  area  has  high  rarity  for  its  intact  late  19th  and  (predominantly) 
early 20th century residential buildings. 
(e)  The area features good examples of buildings of a particular age and 
Government 
type, conferring a high level of representativeness. 
Local 
44. The Desktop Heritage Inventory Review Report issued in April 2021 identified 
Nelson Street, Bay Street, Beach Street, Queen Street, Buick Street and Bolton 
the Street between Jackson Street and the Esplanade for potential inclusion in a 
Petone Foreshore Heritage Area.  The boundaries of the proposed area did not 
under  change in the Draft Heritage Inventory Review Report issued in June 2021.   
45. Following  the  June  2021  Draft,  HCC  requested  a  review  of  the  Petone 
Foreshore Heritage Area due to its size, particularly given the intensification 
Released 
requirements  of  the  NPS-UD  and  the  treatment  of  historic  heritage  as  a 
qualifying matter.  
 
14 
 

 
46. This review confirmed that Queen, Buick, and Bolton Streets were the most 
intact,  and  were  therefore  critical  to  the  heritage  values  of  the  proposed 
Petone  Foreshore  Heritage  Area;  while  modern  redevelopment  at  the 
northern and southern ends of Nelson Street, at  the  northern end of Beach 
Street,  and  sporadically  along  Bay  Street  had  eroded  their  cohesion  and 
integrity.    The  proposed  Petone  Foreshore  Heritage  Area  was  therefore 
Act
reduced to Queen, Buick and Bolton Streets. 
47. In  submission  102.1,  Graeme  Lyon  requests  that  consideration  be  given  to 
Meetings 
extending  the  Petone  Foreshore  Heritage  Area  to  include  Beach  and  Bay 
Streets, but does not provide a detailed explanation as to why.  The submission 
and 
focusses  more  strongly  on  the  need  for  appropriate  “zoning”  to  require  “in 
character development” within the wider foreshore area.  My evidence does 
not discuss the definition of ‘character’ or the difference between ‘character’ 
and ‘heritage’.  This will be addressed by other experts on behalf of HCC. 
Information 
48. In submission 44.1, Laura Skilton requests that the Petone Foreshore Heritage 
Area be extended to include Bay Street and Beach Street “as a minimum” on 
Official 
the  grounds  that  they  “are  not  substantially  different”  to  Queen,  Buick  and 
Bolton Streets.   In the submission,  Laura Skilton has  provided an analysis of 
Beach and Bay Streets against the criteria of Policy 21 of the RPS.4   In general, 
I  agree  with  the  statements  made  in  this  analysis,  particularly  as  regards 
Government 
historic themes and associations, architectural and townscape values, age and 
representativeness, noting that there has been some dilution of these values 
Local 
through modern development.   
the 
49. I have reviewed the extent of the proposed Petone Foreshore Heritage Area, 
and  I  agree  that  Bay  Street  (particularly  the  western  side)  and  Beach  Street 
under  (particularly the south end) have heritage values that are consistent with the 
other streets included in the proposed Area, and therefore meet the criteria of 
                                                             
Released 
4 Laura Skilton’s submission and analysis refer multiple times to “the report”, “the analysis” and “the summary 
document” without specifying which particular report, analysis or summary document are being referred to.  I 
have not cross checked all of these references in reviewing her Policy 21 analysis as I do not believe it changes 
the general nature of the statements made.  
 
15 
 


Act
Meetings 
and 
Information 
Official 
Government 
Local 
the 
under 
Released 

 
Review Report undertaken in 2021 was necessarily high level.  It is possible that 
more  detailed  analysis  of  the  area  bounded  by  the  railway  line,  the  river, 
Jackson Street, Kensington Ave and Cuba Street may identify other areas with 
heritage value.   
52. However, I note the Petone 2040 Spatial Plan did not use the criteria of RPS 
Act
Policy  21  to  assess  “Areas  of  Cohesive  and  Intact  Traditional  Housing”  and, 
therefore it cannot be assumed that these areas would necessarily qualify as 
Heritage Areas. 
Meetings 
53. I  also  note  that  the  “Areas  of  Cohesive  and  Intact  Traditional  Housing” 
and 
encompass other proposed Heritage Areas, including the Riddlers Crescent and 
Patrick  Street  Heritage  Precincts,  and  the  Hutt  Road  Railway,  Petone  State 
Flats, and Moera Railway Heritage Areas.  Therefore, consideration has already 
been given to these areas. 
Information 
Out of scope
Official 
Government 
Local 
the 
under 
Released 
 
17 
 


 
 
 
 
 
Chessa Stevens 
WSP Principal Conservation Architect and National Built Heritage Lead 
Act
7 March 2023 
 
Meetings 
and 
Information 
Official 
Government 
Local 
the 
under 
Released 
 
28 
 



s 7(2)(f)(i)
Act
From: Nathan Geard <[email address]>  
Sent: Wednesday, 19 April 2023 10:25 am 
Meetings 
To: Tim Johnstone <[email address]>; Ceinwen Curtis <[email address]> 
Cc: Alison Geddes <[email address]>; Michelle Palmer <[email address]>; Cam 
Meads <[email address]> 
and 
Subject: RE: Heritage housing messaging 
Good morning 
In response to Tim’s question about residents wanting to make submissions, I have spoken on the phone to 
someone in the last couple of weeks who was asking about whether they could make a submission on the process. I 
Information 
advised them that unfortunately the opportunity to make a submission on this process has passed, but that there 
will be opportunity to be involved through the full District Plan Review. 
Cheers 
Official 
Nathan 
Nathan Geard 
Government 
Policy Planning Manager 
Hutt City Council, 30 Laings Road, Hutt Central, Lower Hutt, Lower Hutt 5010  
Local 
P: s7(2)(a)
  M:   W: www.huttcity.govt.nz 
the 
under 
From: Tim Johnstone <[email address]>  
Sent: Wednesday, 19 April 2023 9:55 AM 
To: Ceinwen Curtis
Released   <[email address]> 
Cc: Nathan Geard <[email address]>; Alison Geddes <[email address]>; Michelle 
Palmer <[email address]>; Cam Meads <[email address]> 
Subject: RE: Heritage housing messaging  
I don’t think we have any requests from the residents to make a submission to the process – Nathan is that correct? 
1



Here some background points: 
 The article relates to District Plan Change 56 which is the Council’s response to the national direction
requiring Council to change its planning rules to enable higher and denser development in some parts of our
city.
 This was a fully notified plan change meaning that anyone could make a submission.  The plan change was notified
on 18 August 2022 until 20 September 2022.  A total of 275 submissions were received.
 Council provided all of the submissions received on its website, along with a summary of the decisions requested
in the submissions.
Act
 There was then another submission period from 10 November to 24 November when people could make a further
submission in support or opposition to any of the decisions requested in the original submissions.  25 further
submissions were received.
Meetings 
 In relation to Bay Street and Beach Street in Petone – an original submission was received requesting the
inclusion of additional heritage areas in the plan change including these streets.   No further submissions
and 
were received in response to this original submission.
 Council’s expert heritage advisor reviewed the submission and evidence and recommended extending the
heritage area to Beach and Bay Streets.   Council’s reporting officer has agreed with this recommendation.
 The plan change is now being considered by an independent hearing panel.  The hearing is currently taking place
Information 
until the 28th April.  The decisions from the hearing panel are due by August 2023.
 The panel can recommend to Council to either accept or reject the submission point seeking the expansion
of the Heritage Area.
Official 
 When the panel has made its recommendation on the submission, Council is then required to decide
whether to accept or reject that recommendation.
 The final decision on whether to extend the heritage area to and Bay Street and Beach Street has not yet
been made.
Government 
 This plan change has followed the statutory process set out in the Resource Management (Enabling Housing
Supply and Other Matters) Amendment Act 2021.
Local 
the 
Tim Johnstone 
Head of Planning  
Hutt City Council, 30 Laings
under   Road, Lower Hutt 5040  
M: s7(2)(a)
   W: www.huttcity.govt.nz 
Released 
From: Ceinwen Curtis <[email address]>  
Sent: Tuesday, 18 April 2023 11:34 am 
To: Tim Johnstone <[email address]> 
Subject: Fwd: Heritage housing messaging  
3

Kia ora Tim, 
Ceinwen Curtis here from the comms team – I’m media advisor. 
I’m looking for some key messages on the issue of heritage housing regarding the article below. 
We may be asked to respond to media queries on this. 
Are you able to help with this? 
Act
Ngā mihi, 
Ceinwen 
'Hutt City Council adds two new heritage streets without consultation' | Voxy.co.nz 
Meetings 
and 
The Hutt City Council has added over 80 new houses to the proposed heritage area on the Petone Foreshore without consulting 
residents, which the Hutt Voluntary Heritage Group (VHG) says could breach the Local Government Act. 
The extension was made in response to a request from a few individual submitters to include Bay Street, King Street, Richmond 
Information 
Street, and Nelson Street in the Petone Foreshore Heritage area - one of 10 proposed heritage areas in the Hutt to mitigate the 
Government’s intensification law. 
The Council Officer responded by recommending the Petone Foreshore heritage area be extended to include over 80 houses in 
Official 
Beach Street and Bay Street. 
The shocking discovery was made by the VHG while analysing the 176-page Council Officers Report. VHG Convenor Phil Barry 
says the extension is unacceptable as they were not part of the original proposal, and therefore homeowners have not been 
adequately consulted. 
Government 
"An additional 82 homeowners are now impacted by the new heritage area rules, many of which are likely not aware of the 
Local 
consequences for their property." 
the 
"Residents on Bay and Beach Street won’t have an opportunity to have their say as submissions have already closed. This could 
breach the Council’s responsibilities under the Local Government Act." 
under 
The Consultation Principles of the Local Government Act guide consultation processes to ensure communities receive information, 
engagement opportunities, and the ability to express their opinions. 
Barry says this has not been done. 
Released 
"Sneaking in over 80 more households into an already underway process goes against every principle set out for consultations in 
the Local Government Act. 
"Mayor Campbell Barry and his Councillors should be ashamed and start asking questions of the Council’s planning team right 
now." 
4

"The Council should walk back the extension and apologise." 
"At the absolute least, the Council should invite homeowners to submit at the hearings taking place this month, which are currently 
only accessible to previous submitters - those included in the heritage areas from the beginning." 
The Council Officer has discretion to add and remove individual properties from the proposed heritage areas in response to 
submissions, but Barry says the addition of two whole streets is extraordinary and requires new consultation. 
"82 families are probably still under the impression that they have escaped the Council’s intensification controls." 
Act
"It’s simply not acceptable that these people would find out their house is subject to strict new heritage rules, without ever being 
given a chance to say something about it." 
Meetings 
"When the consultation principles are ignored like they are here, the trust between council and community is eroded." 
and 
Barry says the Hutt City Council wants to avoid consultation because it knows the heritage areas would not stand up to scrutiny, 
and it’s hastily trying to limit the effects of Government-sanctioned intensification. 
"The inclusion of Bay and Beach Street is consistent with the Council’s crusade against intensification in the area. 
Information 
"The Council Officer’s acceptance of these areas, based on the belief that the ‘practical effect of the Petone Foreshore Heritage 
Area is to limit building height and density to existing levels,’ is just pretext for the council’s anti-intensification agenda. 
Official 
"The Council’s actions throughout the entire process demonstrate that it does not care in the slightest about preserving any 
supposed heritage value of Petone homes. 
"This strategy of forcing residents into heritage areas so the Council can display some semblance of control over housing density 
exhibits a complete disregard for the community it serves." 
Government 
Ceinwen Curtis 
Media Advisor 
Local 
Hutt City Council 
s7(2)(a)
the 
[email address] 
under 
Released 
5

Out of Scope
Act
Meetings 
and 
Information 
Official 
Government 
Local 
the 
under 
From: Ceinwen Curtis 
Sent: Monday, 24 April 2023 11:11 AM 
To: Alison Geddes < [email address] > ; Tim Johnstone < [email address] 
> ; Cam Meads < [email address] > ; Caryn Ellis < [email address] > ; Jarred
Griffiths < [email address] >
Released 
Cc: Michelle Palmer < [email address] > ; Frances Gregory <
[email address] >
Subject: FYI: Media query on Voluntary Heritage Group
Kiaora tatou katoa, 
For your awareness, the statement below will go to Stuff reporter s7(2)(a)
 shortly in response to this 
question: 

s7(2)(a)
query: 
Why are the extended heritage areas in Plan Change 56 needed? 
Were the houses, as Phil Barry claims, just added in to avoid implementing the NPS-UD more broadly? 
If not, why did the heritage assessment in 2022 (after the NPS-UD came out) recommend so many more 
homes for inclusion than previous assessments? 
HCC’s response: 
The proposal to add properties in Beach Street and Bay Street to the proposed 
Act
Petone Foreshore Heritage Area is in response to submissions received during the 
first notification process from 18 August 2022 until 20 September 2022.  A total of 275 
submissions were received. 

Council’s independent qualified heritage expert reviewed these streets and found 
them to have heritage values consistent with the other streets in the heritage area. 

Meetings 
The proposed heritage areas in Plan Change 56 are not proposed for protection on 
and 
the grounds of ‘character’.  They are proposed for protection because they have 
been assessed to have historic heritage values that meet the strict requirements of 
the tests of the RMA and the Regional Policy Statement. 

They are not an attempt to avoid implementing the NPS-UD, but an integral part of 
implementing the NPS-UD, which directs councils to provide for intensification in a 

Information 
way that also delivers on other issues of national significance identified by the RMA, 
such as preserving historic heritage and protecting people and property from natural 
hazards. 

Official 
Council provided al  submissions received on its website, along with a summary of the 
decisions requested in the submissions. 

Fol owing the first submission period there was a subsequent period for further 
submissions from 10 - 24 November. Twenty-five submissions were received during 
this period. 

Government 
This plan change is fol ow
Local ing the Intensification Streamlined Planning Process which 
is a statutory process set by the Resource Management Act.     This process 
prevents people 

the from making submissions at the hearing if they did not make an 
original or further submission. 
The proposed new heritage areas in Plan Change 56 account for less than one 
under 
percent of the residential properties in Lower Hutt.  
ENDS 
Released 
Ngā mihi, 
Ceinwen Curtis 
Media Advisor 
Hutt City Council 
s7(2)(a)
[email address] 

Out of Scope
Act
Meetings 
and 
From: Tim Johnstone 
Sent: Saturday, 22 April 2023 3:23 pm 
To: Ceinwen Curtis < [email address]> ; Cam Meads < [email address]> ; 
Alison Geddes < [email address]> ; Caryn Ellis < [email address]> 
Information 
Cc: Michelle Palmer < [email address]> ; Frances Gregory < 
[email address]> 
Subject: RE: [EXTERNAL] Media query on Voluntary Heritage Group 
Official 
Hi Ceinwen 
Here’s a few additional points: 

Council has been reviewing its heritage inventory as part of the ongoing full review of the district 
plan, begun in 2019. This is the most complete, city-wide assessment of historic heritage since the 
current district plan was prepared in the 1990s.   There has been a lot of change in central 
Government 
government and regional council policy direction about heritage assessment since then, which 
Council is now required to give effect to. 
Local 

The proposed new heritage areas in Plan Change 56 account for less than 1% of the residential 
properties in Lower Hutt.  They are proposed for protection for their significance to the region and 
the 
country. 

They are not an attempt to avoid implementing the NPS-UD, but an integral part of implementing 
the NPS-UD, w
under  hich directs councils to provide for intensification in a way that also delivers on other 
issues of national significance identified by the RMA, such as preserving historic heritage and 
protecting people and property from natural hazards. 

Following the original submissions stage, and in response to specific submissions received on 
Beach Street and Bay Street, Council’s independent qualified heritage expert reviewed these 
Released 
streets and found them to have heritage values that are consistent with the other streets in the 
proposed Petone Foreshore Heritage Area. 
• It is also noted in response to the reporters comment on Wellington’s character areas that the 
proposed heritage areas in Plan Change 56 are not proposed for protection on the grounds of 
“character”.  They are proposed for protection because they have been assessed to have historic 
heritage values that meet the strict requirements of the tests of the RMA and the Regional Policy 
Statement. 

Below is my initial suggest response and background comments for ease of reference. 
This is part of the Proposed District Plan Change 56 process, which fol ows the 
Intensification Streamlined Planning Process set by the Resource Management Act. 
Decisions on the proposed plan change wil  be made later this year. 

The plan change is now being considered by an independent hearing panel.  The hearing is 
currently taking place until the 28 th April.  The decisions from the hearing panel are due by 
August 2023. 

Hutt City Council is unable to comment further until the panel has decided whether to 
Act
recommend the expansion of the Heritage Area .   
BACKGROUND NOTES: 
Meetings 
• This relates to District Plan Change 56 which is the Council’s response to the national direction 
requiring Council to change its planning rules to enable higher and denser development in some 
and 
parts of our city. 
• This was a fully notified plan change meaning that anyone could make a submission.   The plan change 
was notified on 18 August 2022 until 20 September 2022.   A total of 275 submissions were received. 
Information 
• Council provided al  of the submissions received on its website, along with a summary of the decisions 
requested in the submissions.  
Official 
• There was then another submission period from 10 November to 24 November when people could 
make a further submission in support or opposition to any of the decisions requested in the original 
submissions.   25 further submissions were received. 
• In relation to Bay Street and Beach Street in Petone – an original submission was received requesting 
the inclusion of additional heritage areas in the plan change including these streets.   No further 
Government 
submissions were received in response to this original submission. 
• Council’s expert heritage advis
Local or reviewed the submission and evidence and recommended extending 
the heritage area to Beach and Bay Streets.     Council’s reporting officer has agreed with this 
recommendation. 
the 
• The plan change is now being considered by an independent hearing panel.  The hearing is currently 
under 
taking place until the 28 th April.  The decisions from the hearing panel are due by August 2023. 
• The panel can recommend to Council to either accept or reject the submission point seeking the 
expansion of the Heritage Area.  
Released 
• When the panel has made its recommendation on the submission, Council is then required to 
decide whether to accept or reject that recommendation. 
• The final decision on whether to extend the heritage area to and Bay Street and Beach Street has 
not yet been made. 


• This plan change has followed the statutory process set out in the Resource Management (Enabling 
Housing Supply and Other Matters) Amendment Act 2021. 
Tim Johnstone 
Head of Planning   
Hutt City Council, 30 Laings Road, Lower Hutt 5040  
M:s7(2)(a)
  W:  www.huttcity.govt.nz 
Act
Out of Scope
Meetings 
and 
Information 
Official 
Government 
Local 
the 
under 
Released 

From:
Michelle Palmer <[email address]>
To:
__CLT <[email address]>
CC:
Ceinwen Curtis <[email address]>; Frances Gregory
<[email address]>
Subject:
FW: Heritage housing messaging 
Date:
18.04.2023 22:45:04 (+02:00)
Kia ora CLT 
Forwarding the key points as FYI. 
Act
Additional to the below, planning team have advised that the opportunity to make a submission on this 
process has passed, but that there will be opportunity to be involved through the full District Plan Review. 
Nga mihi 
Michelle 
Meetings 
From: Alison Geddes <[email address]> 
and 
Sent: Wednesday, 19 April 2023 9:46 am
To: Ceinwen Curtis <[email address]>; Tim Johnstone <[email address]>
Cc: Nathan Geard <[email address]>; Michelle Palmer <[email address]>; 
Cam Meads <[email address]>
Subject: RE: Heritage housing messaging 
Information 
CLT   would  probably benefit f for knowing this  background too. 
From: Ceinwen Curtis <[email address]> Official 
Sent: Wednesday, 19 April 2023 9:41 am
To: Tim Johnstone <[email address]>
Cc: Nathan Geard <[email address]>; Alison Geddes <[email address]>; 
Michelle Palmer <[email address]>; Cam Meads <[email address]>
Subject: RE: Heritage housing messaging 
Hi Tim, 
Government 
That’s right, yes. 
Local 
The request is for some messaging if a media query pops up. 
the 
Are we able to respond to the requests the residents are making to be able to submit to the process? 
Looping in Cam Meads here who will need this information. 
under 
Noho ora mai, 
Ceinwen 
Released 

Out of scope
Act
Meetings 
IMPORTANT: The information contained in this e-mail message may be legally privileged or confidential. The information is intended 
and 
only for the recipient named in the e-mail message. If the reader of this e-mail message is not the intended recipient, you are notified 
that any use, copying or distr bution of this e-mail message is prohibited. If you have received this e-mail message in error, please notify 
the sender immediately. Thank you.
From: Elected Members Requests <[email address]>
Information 
Sent: 26 April 2023 14:00
To: __Mayor & Councillors <__Mayor&[email address]>; Belinda Moss 
<[email address]>; Mike Fisher <[email address]>; Te Awa Puketapu 
<[email address]>
Official 
Cc: __CLT <[email address]>
Subject: Media coverage relating to extension of proposed Petone Foreshore Heritage Area
Kia ora koutou 
Please see below from Tim Johnstone, Head of Planning, regarding recent media coverage relating to the 
Government 
extension of proposed Petone Foreshore Heritage Area to include Beach Street and Bay Street in Petone 
as part of District Plan Change 56.

Local 
Background 
There has been some recent media coverage on this:
the 
https://news.fuseworksmedia.com/78bc95df-1b3f-4e75-80ae-0df84082478f
under 
This story is being driven by the Voluntary Heritage Group who are opposed to Council listing private 
residential properties as heritage areas without homeowner consent.
We have also been contacted by a reporter from Stuff and are expecting some more coverage, so we want 
to provide Councillors with all of the facts.
Released 
Process
 This relates to District Plan Change 56 which is Council’s response to the national direction requiring
Council to change its planning rules to enable higher and denser development in some parts of the city.
 This plan change is following the Intensification Streamlined Planning Process which is a statutory process 
set by the Resource Management Act. 
 This was a ful y notified plan change meaning that anyone could make a submission.  The plan change was 
notified on 18 August 2022 until 20 September 2022.  A total of 275 submissions were received. 

 Council provided all of the submissions received on its website, along with a summary of the decisions 
requested in the submissions. 
 There was then another submission period from 10 November to 24 November when people could make a 
further submission in support or opposition to any of the decisions requested in the original submissions.  25 
further submissions were received.
 The plan change is now being considered by an independent hearing panel.  The hearing is taking place until 
the 28th April.  
 The Voluntary Heritage Group made a submission on the plan change and last week they presented 
their submission at the hearing to the independent panel.
Beach Street and Bay Street
Act
 These streets were not originally included within the proposed Petone Foreshore Heritage Area when 
the plan change was notified.
 Two submissions were received requesting the inclusion of these Streets within the heritage area.  No 
further submissions were received on this. 

Meetings 
In response to these submissions, Council’s independent qualified heritage expert reviewed the streets 
and found them to have heritage values consistent with the other streets in the proposed Petone 
Foreshore Heritage Area.
and 
 The heritage expert therefore recommended extending the heritage area to include Beach Street and Bay 
Street, and Council’s reporting officer agreed with this recommendation.  
 This will be considered by the independent hearing panel, along with other submissions such as that 
from the Voluntary Heritage Group.
Response to specific points raised by the Voluntary Heritage Group Information 
Response to concerns raised by the Voluntary Heritage Group in relation to lack of consultation:
 It is correct that the residents in Beach Street and Bay Street have not been directly contacted in 
relation to this matter.  This is an outcome of this plan change process.
 Council is correctly following the Intensification Streamlined Planni
Official ng Process which is a statutory process 
set by the Resource Management Act.   This process prevents people from making submissions at the 
hearing if they did not make an original or further submission.
Response to concerns raised by the Voluntary Heritage Group that the addition of these streets to the 
heritage area is an attempt to avoid implementing the intensification required under the National Policy 
Statement on Urban Development (NPS-UD):
Government 
 The addition of these streets to the heritage area is not an attempt to avoid implementing the NPS-UD, 
but is in fact an integral part of implementing the NPS-UD, which directs councils to provide for 
intensification in a way that also delivers on other issues of national significance identified by the RMA, 
Local 
such as preserving historic heritage and protecting people and property from natural hazards.
 The proposed new heritage areas in Plan Change 56 account for less than 1% of the residential 
the 
properties in Lower Hutt.  
Next steps

under 
The final decision on whether to extend the heritage area to and Bay Street and Beach Street is yet to 
been made.
 The decisions from the hearing panel are due by August 2023.
 The panel can recommend to Council to either accept or reject the submission point seeking the 
expansion of the heritage area.  

When th
Released e panel has made its recommendation on the submission, Council is then required to decide 
whether to accept or reject that recommendation.  

If it rejects the recommendation then the matter is referred to the Minister for the Environment, who 
has the final decision-making power in respect of panel recommendations that have been rejected by 
Council.
Ngā mihi 


Hamish Bell
Elected Member Support Coordinator 
Hutt City Council, 30 Laings Road, Lower Hutt 5010
M: s7(2)(a)
W: www.huttcity.govt.nz
Act
Meetings 
and 
Information 
Official 
Government 
Local 
the 
under 
Released 


From:
Tim Johnstone <[email address]>
To:
Hamish Bell <[email address]>
CC:
Alison Geddes <[email address]>
Subject:
Memo to be circulated to Councillors - Beach Street and Bay Street
Date:
24.04.2023 03:56:06 (+02:00)
Attachments:
Briefing for Councillors on Beach Street and Bay Street media coverage.docx (3 
pages)
Hi Hamish 
Can this please be circulated to elected members and copied to CLT. 
Act
Alison has cleared the content of the memo. 
Tim Johnstone
Meetings 
Head of Planning  
Hutt City Council, 30 Laings Road, Lower Hutt 5040 
and 
M: s7(2)(a)
W: www.huttcity.govt.nz
Information 
Official 
Government 
Local 
the 
under 
Released 


MEMORANDUM 
To: 
All Councillors 
Copy: 
Corporate Leadership Team 
From: 
Tim Johnstone, Head of Planning 
Act
Date: 
24 April 2023 
SUBJECT: 
MEDIA COVERAGE RELATING TO EXTENSION OF PROPOSED PETONE 
Meetings 
FORESHORE HERITAGE AREA TO INCLUDE BEACH STREET AND BAY 
and 
STREET IN PETONE AS PART OF DISTRICT PLAN CHANGE 56 
Background 
There has been some recent media coverage on this: 
Information 
https://news.fuseworksmedia.com/78bc95df-1b3f-4e75-80ae-0df84082478f 
This story is being driven by the Voluntary Heritage Group who are opposed to Council 
Official 
listing private residential properties as heritage areas without homeowner consent. 
We have also been contacted by a reporter from Stuff and are expecting some more 
coverage, so we want to provide Council ors with al  of the facts. 
Government 
Process 
Local 
• This relates to District Plan Change 56 which is Council’s response to the national
direction requiring Council to change its planning rules to enable higher and denser
the 
development in some parts of the city.
• This plan chan
under ge is following the Intensification Streamlined Planning Process which is a
statutory process set by the Resource Management Act.
• This was a ful y notified plan change meaning that anyone could make a submission.  The
plan change was notified on 18 August 2022 until 20 September 2022.  A total of 275
Released 
submissions were received.
• Council provided al  of the submissions received on its website, along with a summary of the
decisions requested in the submissions.
Page 1 of 3 

• There was then another submission period from 10 November to 24 November when people
could make a further submission in support or opposition to any of the decisions requested
in the original submissions.  25 further submissions were received.
• The plan change is now being considered by an independent hearing panel.  The hearing is
taking place until the 28 h April.
• The Voluntary Heritage Group made a submission on the plan change and last week
Act
they presented their submission at the hearing to the independent panel.
Beach Street and Bay Street 
Meetings 
• These streets were not original y included within the proposed Petone Foreshore
Heritage Area when the plan change was notified.
and 
• Two submissions were received requesting the inclusion of these Streets within the
heritage area.  No further submissions were received on this.
• In response to these submissions, Council’s independent qualified heritage expert
Information 
reviewed the streets and found them to have heritage values consistent with the other
streets in the proposed Petone Foreshore Heritage Area.
Official 
• The heritage expert therefore recommended extending the heritage area to include
Beach Street and Bay Street, and Council’s reporting officer agreed with this
recommendation.
• This wil  be considered by the independent hearing panel, along with other submissions
such as that from the Voluntary Heritage Group
Government  .
Response to specific points raised by the Voluntary Heritage Group 
Local 
Response to concerns raised by the Voluntary Heritage Group in relation to lack of 
the 
consultation: 
under 
• It is correct that the residents in Beach Street and Bay Street have not been directly
contacted in relation to this matter.  This is an outcome of this plan change process.
• Council is correctly following the Intensification Streamlined Planning Process which is a
Released 
statutory process set by the Resource Management Act.   This process prevents people
from making submissions at the hearing if they did not make an original or further
submission.
Page 2 of 3

Response to concerns raised by the Voluntary Heritage Group that the addition of these 
streets to the heritage area is an attempt to avoid implementing the intensification 
required under the National Policy Statement on Urban Development (NPS-UD): 
• The addition of these streets to the heritage area is not an attempt to avoid
implementing the NPS-UD, but is in fact an integral part of implementing the NPS-UD,
which directs councils to provide for intensification in a way that also delivers on other
issues of national significance identified by the RMA, such as preserving historic
Act
heritage and protecting people and property from natural hazards.
• The proposed new heritage areas in Plan Change 56 account for less than 1% of the
residential properties in Lower Hutt.
Meetings 
Next steps 
and 
• The final decision on whether to extend the heritage area to and Bay Street and Beach
Street is yet to been made.
• The decisions from the hearing panel are due by August 2023. 
Information 
•  The panel can recommend to Council to either accept or reject the submission point
seeking the expansion of the heritage area. Official 
• When the panel has made its recommendation on the submission, Council is then
required to decide whether to accept or reject that recommendation.
• If it rejects the recommendation then the matter is referred to the Minister for the
Environment, who has the final decision-maki
Government ng power in respect of panel
recommendations that have been rejected by Council.
Local 
the 
Tim Johnstone 
under 
Head of Planning 
Released 
Page 3 of 3

From:
Nathan Geard <[email address]>
To:
Emily Campbell <[email address]>
Subject:
Date:
09.03.2023 22:55:13 (+01:00)
I've had a look in the heritage files and it doesn't look like Beach and Bay Street were sent letters in the 
April 2021 mail-out (I'll confirm this with Stephen next time he is in the office as he helped with that 
mail-out). I think we should deal with them separately, as the message we need to give them is quite 
different. 
Act
Meetings 
and 
Information 
Official 
Government 
Local 
the 
under 
Released 

Hutt City Council 
District Plan Change 56: Enabling Intensification in Residential and Commercial 

Areas 
 
Brief for Heritage Evidence to Respond to Submissions 
Evidence for the PC56 hearing to cover the following matters: 
Act
(a)  Introduction, covering qualifications, experience and role in plan change including preparation of 
technical advice and information which has informed Plan Change 56 
(b)  Provide heritage evidence responding to the fol owing submission points, by either reconsidering 
the original assessment or explaining the reasoning for the decision 
Meetings 
Out of scope
and 
Information 
Official 
44.1 
Laura Skilton 
Extend the Petone Foreshore 
The process for identifying 
Heritage Precinct to include Bay 
heritage areas and how this 
Street and Beach Street as a 
relates to the submitter’s 
minimum, and consider t
Government he area  proposed additions. 
covered in Figure 2.1.5 of the 
 
Petone 2040 Spatial Plan. 
(Figure 2.1.5 is attached as a 
Local 
separate file). 
Out of scope
the 
under 
102.1  Graeme Lyon 
Confirm … the Petone Foreshore 
The relevance of Queen, Beach, 
Heritage Area, perhaps extending it  and Bay Streets to the heritage 
to Queen, Beach, and Bay Streets. 
area 
Out of scope
Released 


Act
Meetings 
and 
Information 
Official 
Government 
Local 
the 
under 
Released 
Figure 2.1.5: Heritage Assets
P2040: Petone Spatial Plan      McIndoe Urban Ltd      June 2017
19

Document Outline