This is an HTML version of an attachment to the Official Information request 'All project reports relating to any funding received by HPANZ'.


        EECA LEVCF FUND 03-149 
 
Project Summary 
Short description 
Tourism Holdings Limited (thl) and Holiday Parks Association New Zealand (HPANZ) 
embarked on a process to make an Electric Campervan trip a possibility in New 
Zealand as a low emission alternative to the current options. 
THL started R&D on EVs in 2017 and introduced a Nissan ENV 200 van for road 
testing and user insights in Dec/Jan and worked on completing a first electric 
motorhome which was on display for the first time for industry trade at Trenz in early 
May 2018 and for the public at EV world in Aug and Big Boys Toys in Nov 2018. Thl 
proceeded ahead of the EECA schedule and put 10 eLDVs on fleet in December 
January to start getting further insights 
Thl and HPANZ have been working on 2 itineraries based on user insights and to 
create a new experience. Now bookable itineraries are here : 
https://www.britzev.com/ 
Overall project 
The first pilot of the EV programme at thl has now been completed. The insights have 
success 
been gathered around the 3 important parts of the thl business model: build- rent – 
sell 
thl is committed to electric vehicles going forward, and the question based on the 
current insights is how quickly the customers, the products (batteries especially)  
market and the infrastructure will catch up.  
New EV strategy is being formulated. 
Timing Status 
Start date 
01/03/2018 
Original completion date 
10/12/2018 
Revised completion date 
30/03/2019 
 
Project Milestones 
 
Milestones 
Deliverables/Tasks 
Evidence 
Milestone 1 
Insights 
Complete 
Milestone 2 
•  Confirming electric 
Complete  
 
campervan purchase and 
Delivery by 
deployment 
31Oct18 
•  Confirmation of 
itineraries and EV 
charging locations 
Milestone 3 
•  Confirming installation 
 
 
and commissioning EV 
Delivery by 
charging stations 
20Dec18 
•  Supplier Declaration of 
Conformity 
documentation for the EV 
chargers 
Milestone 4 
Confirming results of the 
Complete 
 
tasks 
Delivery by 
•  Establishment and 
31Oct18 
training of support team 
•  Test drives using current 
ENV 200, and 
 
Dec 18  
COMMERCIAL IN CONFIDENCE 



        EECA LEVCF FUND 03-149 
 
•  Promotional events and 
media engagement 
Milestone 5 
•  Confirming installation 
 
 
and commissioning of EV 
Delivery by 
charging stations 
20Dec18 
•  Supplier Declaration of 
Conformity 
documentation for the EV 
chargers 
Milestone 6 
•  Results of user trials and 
Complete 
Delivery by 
learnings for new van 
30Nov18 
design 
Milestone 7 
Confirmation of successful 
Complete  
 
conversion and certification 
Delivery by 
30Jan18 

Milestone 8 
•  Confirm future build 
 
 
plans and EV campervan 
Delivery by 
additions to fleet with 
30Mar19 
results measured against 
specified project success 
factors 
Milestone 9 
•  Update documentation 
 
 
and project close-out 
Delivery by 
report 
30Mar19 
Evidence 
1) Progress summary report 
supplied 
2)  Invoices  
3) progress reports for milestone 8 and 9 
4) invoice detail for all holiday parks  
 
 
 
 
Dec 18  
COMMERCIAL IN CONFIDENCE