EECA LEVCF FUND 03-149
Project Summary
Short description
Tourism Holdings Limited (
thl) and Holiday Parks Association New Zealand (HPANZ)
embarked on a process to make an Electric Campervan trip a possibility in New
Zealand as a low emission alternative to the current options.
THL started R&D on EVs in 2017 and introduced a Nissan ENV 200 van for road
testing and user insights in Dec/Jan and worked on completing a first electric
motorhome which was on display for the first time for industry trade at Trenz in early
May 2018 and for the public at EV world in Aug and Big Boys Toys in Nov 2018. Thl
proceeded ahead of the EECA schedule and put 10 eLDVs on fleet in December
January to start getting further insights
Thl and HPANZ have been working on 2 itineraries based on user insights and to
create a new experience. Now bookable itineraries are here :
https://www.britzev.com/
Overall project
The first pilot of the EV programme at
thl has now been completed. The insights have
success
been gathered around the 3 important parts of the thl business model: build- rent –
sell
thl is committed to electric vehicles going forward, and the question based on the
current insights is how quickly the customers, the products (batteries especially)
market and the infrastructure will catch up.
New EV strategy is being formulated.
Timing Status
Start date
01/03/2018
Original completion date
10/12/2018
Revised completion date
30/03/2019
Project Milestones
Milestones
Deliverables/Tasks
Evidence
Milestone 1
Insights
Complete
Milestone 2
• Confirming electric
Complete
campervan purchase and
Delivery by
deployment
31Oct18
• Confirmation of
itineraries and EV
charging locations
Milestone 3
• Confirming installation
and commissioning EV
Delivery by
charging stations
20Dec18
• Supplier Declaration of
Conformity
documentation for the EV
chargers
Milestone 4
Confirming results of the
Complete
tasks
Delivery by
• Establishment and
31Oct18
training of support team
• Test drives using current
ENV 200, and
Dec 18
COMMERCIAL IN CONFIDENCE
EECA LEVCF FUND 03-149
• Promotional events and
media engagement
Milestone 5
• Confirming installation
and commissioning of EV
Delivery by
charging stations
20Dec18
• Supplier Declaration of
Conformity
documentation for the EV
chargers
Milestone 6
• Results of user trials and
Complete
Delivery by
learnings for new van
30Nov18
design
Milestone 7
Confirmation of successful
Complete
conversion and certification
Delivery by
30Jan18
Milestone 8
• Confirm future build
plans and EV campervan
Delivery by
additions to fleet with
30Mar19
results measured against
specified project success
factors
Milestone 9
• Update documentation
and project close-out
Delivery by
report
30Mar19
Evidence
1) Progress summary report
supplied
2) Invoices
3) progress reports for milestone 8 and 9
4) invoice detail for all holiday parks
Dec 18
COMMERCIAL IN CONFIDENCE