This is an HTML version of an attachment to the Official Information request 'Monetary Payment for Blessing of Rocks for North Mole'.

Regional Council 
27 April 2022 
  
Report No. 
 22-37 
Decision Required  
LOWER WHANGANUI SCHEME - TE PŪWAHA UPDATE 
  
1. 
PURPOSE 
1.1. 
This  item  updates  members  on  progress  with  the  river  training  infrastructure  upgrade 
component  of  the  Te  Pūwaha  /  Whanganui  Port  Revitalisation  Project.  The  item  also 
updates financial forecasts through to project completion and seeks Councils direction on 
budgets for the project.  
2. 
EXECUTIVE SUMMARY 
2.1. 
Te Pūwaha refers to the gateway, or river mouth. It is also the name of the Whanganui port 
revitalisation  project.  Te  Pūwaha  is  a  partnership  involving Whanganui  Iwi  and  five  other 
groups  invested  in  the  project:  Whanganui District Council  (WDC), Horizons  Regional 
Council (Horizons), Q-West Boat Builders, Whanganui District Employment Training Trust 
and  central  government.  The  total  investment  in  Te  Pūwaha  is  over  $50M,  with 
infrastructure  works  carried  out  in  several  sub  projects.  This  Council  item focuses  on  the 
component  of  the  project  to  strengthen  and  upgrade  old  river  training  structures  in  the 
lower  reach  of  the  Whanganui  River.  More  information  on  Te  Pūwaha  and  the  other 
components of work is available on Horizons and WDC websites. 
2.2. 
A  project  governance  structure  has  been  established  in  accordance  with  the  legislation 
requirements under the Te Awa Tupua (Whanganui River Claims Settlement) Act, 2017 
(Te  Awa  Tupua  Act).  Project  delivery  is  being  managed  as  a  partnership  between  Te 
Mata Pūau and Horizons staff. Te Mata Pūau are the hapū col ective leading application of 
Te  Awa  Tupua  framework  together  with  key  partners  across  the  governance  and 
operational levels.  
2.3. 
Te  Awa  Tupua  Act  was  enacted  to  implement  the  historical  Treaty  Settlement  with 
Whanganui  iwi  in  relation  to  the  Whanganui  River.  Te  Awa  Tupua  represents  a  new 
beginning  in  terms  of  respect for the Whanganui  River  and  recognition  of the  inalienable 
connection  between  Whanganui  Iwi  and  the  Whanganui  River.  This  is  a  detailed  set  of 
legislation which includes a range of mechanisms to recognise the Whanganui River as Te 
Awa Tupua and to provide legal expression to the relationship between Whanganui Iwi and 
the River.   
2.4. 
A fundamental driver for Te Pūwaha as a project is the requirement for al  communities and 
authorities to uphold the values of Tupua te Kawa are the intrinsic values that represent the 
essence of Te Awa Tupua. These values include:  
  Ko Te Kawa Tuatahi - Ko te Awa te mātāpuna o te ora: the River is the source of 
spiritual  and  physical  sustenance:  Te  Awa  Tupua  is  a spiritual  and  physical  entity 
that supports and sustains both the life and natural resources within the Whanganui 
River and the health and wel -being of the iwi, hapū, and other communities of the 
River.  
  Ko  Te  Kawa  Tuarua  -  E  rere  kau  mai  i  te  Awa  nui  mai  i  te  Kahui  Maunga  ki 
Tangaroa: the great River flows from the mountains to the sea: Te Awa Tupua is an 
indivisible  and  living  whole  from  the  mountains  to  the  sea,  incorporating  the 
Whanganui River and al  of its physical and metaphysical elements.  
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 1 
 


Regional Council 
27 April 2022 
  
  Ko Te Kawa Tuatoru - Ko au te Awa, ko te Awa ko au: I am the River and the River 
is me: the iwi and hapū of the Whanganui River have an inalienable connection 
with, and responsibility to, Te Awa Tupua and its health and wel -being.  
  Ko Te Kawa Tuawhā - Ngā manga iti, ngā manga nui e honohono kau ana, ka tupu 
hei  Awa  Tupua:  the  smal   and  large  streams  that  flow  into  one  another  form  one 
River:  Te  Awa  Tupua  is  a  singular  entity  comprised  of  many  elements  and 
communities,  working  col aboratively  for  the  common  purpose  of  the  health  and 
well-being of Te Awa Tupua.  
2.5. 
The River Training Structures part of the overal  Te Pūwaha programme is funded via an 
agreement  between  central  government,  via  the  Ministry  of  Business,  Innovation  and 
Employment  (MBIE),  and  Horizons  dated  10  July  2020.  This  provides  for  a  central 
government contribution of up to $7.5M towards a $15M project to strengthen and upgrade 
old  river  training  structures  in  the  lower  reach  of  the  Whanganui  River.  Horizons 
contribution to this project is $5.7M and WDC’s contribution $1.8M. 
2.6. 
The  project  as  scoped  included  three  stages  with  Stage  1  being  the  North  Mole 
reconstruction works and Stage 2 the South Mole reconstruction works. The third stage is 
the possible extension to the Tanae Groyne and improvements/strengthening of South Spit 
erosion  protection/training  structures  upstream  of  Tanae  Groyne.  Stage  1  of  the  3  stage 
project  is  now  well  advanced  and  is  scheduled  for  completion  in  late  2022.  Preliminary 
work  in  respect  of  Stage  2  is  also  wel   underway  with  commencement  of  physical  works 
scheduled for November 2022. 
2.7. 
This  paper  seeks  Council  direction  on  the  budgets  for  the  Whanganui  Scheme  related 
rates in the upcoming Annual Plan processes to account for the fol owing factors:  
1.  Increased costs for the delivery of Stage 1 and 2 which is now projected to be delivered 
for a total budget of $16.2M, being approximately $2.75M or 20% higher than original y 
budgeted. Cost increases relate to project management and communications $1.297M, 
consenting and design $0.254M, construction costs for stage 1 ($0.8M) and for Stage 2 
$0.4M.  It  is  noted  that  the  cost  projection  for  Stage  1  construction  includes  a 
provisional sum of an additional $0.75M for two fishing platforms and staff are working 
to get further certainty around this amount prior to the Council meeting;  
2.  Alignment  of  Horizons  funding  contribution  with  the  funding  commitments  of  the 
government  contract  for  the  River  Training  Structures  part  of  the  Te  Pūwaha  project. 
Currently  Horizons  Long-term  Plan  (LTP)  for  2018-2028  and  LTP  2021-2031  both 
overestimate  the  WDC  contribution  at  25%  rather  than  the  fixed  $1.8  mil ion 
contribution;  
3.  Updated  phasing  of  Horizons  planned  expenditure  on  this  project  given  new 
information from the current delivery of the project to the end of March 2022; 
4.  Removal  of  the  delivery  of  Stage  3  from  the  scope  of  the  Government  and  WDC 
co-funded  project  to  offset  the  increased  costs  for  the  Stage  1&2.  Note  the  paper 
recommends a resolution for Council to direct the CE to present further information on 
Stage 3 to the Annual Plan process in 2023-24;  
5.  Inclusion  of a  budget  of $100,000 over  two  years for scoping  and monitoring  work  to 
inform planning for Stage 3; 
6.  Providing  a  budget  for  further  scoping  and  delivery  of  amenity  enhancement  projects 
(noting this is additional to the costs provisioned for in 1 above); and 
7.  Other  changes  to  work  programmes  for  other  Whanganui  Scheme  related  activity  to 
further reduce the impact of the cost increases identified for Stage 1 and 2 above and 
in  recognition  of  the  readiness  of  that  other  activity  and  capacity  of  Horizons  and 
project partners to deliver this additional work during the next two years. 
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 2 
 


Regional Council 
27 April 2022 
  
2.8. 
It is noted that the project budgets are subject to further change as additional design and 
consenting  work  etc.  is  completed  and  inflationary  pressures,  contractor  pricing  etc.  are 
further accounted for. 
2.9. 
In total the increased funding required from Horizons for this project is $2.2M. As a part of 
the  review  of  the  LTP  year  2  budgets  to  the  Annual  Plan  for  2022-23  there  have  been 
revisions  to  the  budgets  and  phasing  of  works  and  associated  loan  repayments  for  the 
Lower Whanganui Scheme rates, which are funded 80% by targeted rate and 20% general 
rate. As a result the proposed impact of this change in budgets, the targeted rates required 
this  Annual  Plan  has  been  slightly  reduced  compared  to  year  2  of  the  LTP  (-$12k),  and 
$16k up on year 3 of the LTP.  It  is  noted  that some work  within  the Whanganui Scheme 
has been deferred to beyond that period, however this is not ful y scoped making it difficult 
to forecast budgets for that work.     
 
3. 
RECOMMENDATION 
It is recommended that Council:  
a.  receives the information contained in Report No. 22-37. 
b.  notes  progress  to  date  with  Te  Pūwaha  Project  Stage  1  physical  works  and  Stage 2 
preparatory work; 
c.  notes  the  revised  budget  estimates  indicate  an  overspend  of  $1.4M  against  the 
original  project  budget  of  $15M.  This  includes  additional  funding  for  Stages  1  and  2 
completion  (additional  $2.75M),  scoping  of  Stage  3  ($100,000)  and  scoping  and 
delivery of amenity enhancement works  ($100,000). Notes these additional costs  are 
partial y offset by  removing delivery of Stage 3 from  the work programme which  was 
budgeted  at  $1.587M.  Further  notes  design,  consenting,  inflationary  pressure  and 
other factors may lead to revised project budgets into the future. 
d.  notes  that  if  Stage  3  works  were  to  be  completed,  an  additional  budget  of  $2.5M  is 
estimated to be required, including additional design and consenting work beyond that 
which wil  be completed in the scoping study identified above.  
e.  directs the Chief Executive to present further information on Stage 3 of this project as 
a part of the Annual Plan process for budgets for the 2023-24 financial year.  
f.  notes  that  amenity  enhancement  works  are  being  identified  as  a  part  of  the  project 
with some being scoped/delivered within the budgets identified above and that further 
requests  for  Council  funding  of  such  elements  may  be  presented  to  Council  in  the 
future.  
g.  approves the al ocation of Horizons share of the funding for this project as revised in 
the  paper  taking  the  total  project  cost  to  $16.4M  including  MBIE  ($7.5M)  and  WDC 
($1.8M) share. This includes the additional funding for the completion of Stages 1 and 
2 as identified in the paper, scoping work for Stage 3 and including up to $100,000 for 
scoping and delivering amenity enhancement projects over the next two years.  
 
4. 
FINANCIAL IMPACT 
4.1. 
This item outlines revised budgets for the Whanganui River Training structures project part 
Te  Pūwaha  project  and broader  Lower Whanganui Scheme  over the next  two  years  and 
beyond. Financial impacts are discussed in the item including rating impact for the 2022-23 
and  2023-24 years.  This  is summarised in the Executive Summary above and in  Section 
12 below.  
 
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 3 
 


Regional Council 
27 April 2022 
  
5. 
Mouri Ora, Mouri Awa, Mouri Tangata 
5.1. 
Extensive  effort  has  been  made  to  place  Te  Awa  Tupua  at  the  heart  of  the  Te  Pūwaha 
programme in a way that has established  a unique  partnership model between  Horizons, 
Whanganui  Iwi,  WDC,  central  government,  private  business  and  the  Whanganui 
community.  
5.2. 
Hapū  play  a  significant  role  at  the  centre  of  the  project  through  the  establishment  of 
Te Mata Pūau to steer and guide the project. Te Mata Pūau is a hapū col ective that invites 
participation  from  al   hapū  with  interest.  Project  partners  have  needed  to  commit  to 
upholding  Te  Awa  Tupua  in  the  way  they  work.  Horizons  has  committed  to  this  process 
and  has  been  directed  and  supported  to  do  so  by  Te  Mata  Pūau,  supported  by  Ngā 
Tangata  Tiaki  and  a  Programme  Director.  The  project  has  and  wil   continue  to  have  a 
strong  focus  on  empowering  the  community  and  involving  the  community  in  discussions 
and approach to project issues and outcomes outside the regulatory process. 
5.3. 
Iwi and hapū need to be recognised for their contribution to ensuring the project has been 
developed  and  guided  by  Tupua  te  Kawa  and  in  the  context  of  the  Te  Awa  Tupua  Act.  
This  relationship  has  helped  guide  the  approach  through  Te  Pūwaha  Project  Framework 
and ensured a Te Awa Tupua lens has been applied to the overal  project. The support and 
guidance from iwi and hapū has helped ensure that the implementation of Te Awa Tupua 
Act  and  establishment  of  a  framework  for  this  project  has  been  upheld  across  the  key 
partners at both governance and operational levels. 
5.4. 
He  Ara  Tuku  Rau  is  an  abundance  model  that  has  been  developed  as  a  support 
mechanism for Te Mata Pūau and its decision making. He Ara Tuku Rau seeks to support 
Te Mata Pūau and in-turn the project partners to:  
  Address  historic  losses  and  provides  a  pathway  to  avoid  contemporary  adverse 
effects. 
  Set  long-term  visions  and  goals  for  enhancement  across  appropriate  dimensions 
aligned with Tupua te Kawa.  
  Place  Te  Mata  Pūau  at  the  centre  of  decision-making  enabling  adverse  effects  that 
undermine Tupua te Kawa (across al  dimensions) to be avoided.  
  Support decision-making in order to enhance Mouri Ora, Mouri Awa, Mouri Tangata. 
  Provide a pathway for activities to occur in and around Te Pūwaha. 
  Be based on recognised conceptual foundations and can incorporate existing models, 
methods and tools or those designed for a specific project. 
  Emphasise restoration and the concept of abundance. 
  Inform a monitoring programme that enables performance reporting for enhancement 
interventions that enrich Mouri ora, Mouri awa, Mouri Tangata. 
  Be robust, transparent, and repeatable. 
  Be able to be applied commensurate to the scale of the project. 
5.5. 
The environmental effects associated with the resource consent issues for the North Moles 
can  be  avoided,  remedied,  or  mitigated  and  are  assessed  to  be  no  more  than  minor. 
However, consistent with the way we are working on this project from a holistic manner the 
project partners are working towards a strategic outcome of Mouri Ora, Mouri Awa, Mouri 
Tangata.  
5.6. 
Horizons have committed to Te Awa Tupua and He Ara Tuku Rau. The outcomes achieved 
should not be considered positive effects in relation to the proposed activities, but more a 
set  of  deliberately  designed  outcomes  to  achieve  the  strategic  aspiration  of  Mouri  Ora, 
Mouri Awa, Mouri Tangata. These aspirations are implicit in what Tupua Te kawa is and a 
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 4 
 


Regional Council 
27 April 2022 
  
product of the community led approach. Some examples of how Horizons are contributing 
to these aspirations beyond the proposed activities are yet to be determined with Te Mata 
Pūau.  
5.7. 
There  are  some  clearly  defined  community  aspirations  which  are  the  product  of  a 
successful  community  engagement  process  led  by  Horizons  towards  consenting  for  the 
North  Mole.  The  proposed  works  are  considered  to  improve  the  integrity  of  key 
infrastructure  and  reduce  the  risk  of  erosion  and  flooding  to  the  lower  Whanganui 
community.  The  Resource  Consent  Conditions  note  that  works  wil   also  result  in  an 
improvement to the access of this area through the provision of fishing platforms and dune 
management. These are the agreed outcomes which funding is being sought for to achieve 
the community’s aspirations.   
6. 
SIGNIFICANT BUSINESS RISK IMPACT 
6.1. 
There is no significant business risk arising from this item. Some of the project-related risks 
are addressed elsewhere in the item. 
7. 
CLIMATE IMPACT STATEMENT 
7.1. 
While  the  work  associated  with  strengthening  the  river  training  structures  primarily 
addresses  deferred  maintenance  over  many  decades,  the  work  also  considers  climate 
change  effects,  including  rising  sea  levels,  more  frequent  storms,  and  a  changing  flood 
frequency for the awa. The design takes into account these factors and was reviewed by 
coastal engineering experts at engineering consultancy Tonkin and Taylor, to ensure that 
sufficient consideration was given, amongst other things, to climate change impacts. While 
the work seeks to provide greater resilience to storm and flood events, there are elements 
of the delivery that wil  contribute to climate impact for example the use of fossil fuels etc.  
8. 
BACKGROUND 
8.1. 
In December 2011 Horizons received a formal request from WDC to extend its then current 
river  management  function,  through  its  Lower  Whanganui  River  Scheme,  to  include 
maintenance  of  old  channel  management  infrastructure  along  the  lower  reach  of  the 
Whanganui  River.  While  a  decision  on  that  request  was  deferred  at  the  time,  Council 
instructed officers to work col aboratively with WDC to explore options for the longer term 
management of issues associated with both river and port management. 
8.2. 
Ultimately  the  scope  of  the  Lower  Whanganui  River  Scheme  was  extended  through 
adoption  of  the  2015-25  Long  Term  Plan,  initial y  to  accommodate  river  alignment  and 
erosion  control  along  the  South  Spit,  with  the  objective  of  maintaining  existing  river 
alignment upstream of the South Mole. 
8.3. 
Over the fol owing three years, some minor maintenance works were completed along the 
South  Spit;  monitoring  of  erosion  at  various  sites  was  undertaken;  and  further 
investigations were commissioned with respect to the wider issues. Costs were shared by 
WDC and Horizons. 
8.4. 
Investigations  undertaken  by  Tonkin  and  Taylor  Ltd  and  Coastal  Systems  Ltd  (Dr  Roger 
Shand) formed the basis of a Situations and Recommendations Report produced in March 
2017.  That  report  identified  that  infrastructure  was  in  a  worse  state  than  previously 
reported  and  noted,  amongst  other  things,  that  slumping  and  scouring  had  occurred  at 
various  sites  along  the  North  Mole  and  South  Spit  since  June  2015.  The  need  for 
maintenance or improvement works at certain sites was considered urgent. 
8.5. 
A joint Councils’ project team, established to progress the issue as a priority, held technical 
workshops involving coastal and river engineers having long associations with the subject 
river reach, and ultimately developed a programme of works that would achieve a balance 
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 5 
 


Regional Council 
27 April 2022 
  
between  the  risk  of  existing  structure  failure  and  a  spread  of  expenditure  that  best 
managed rating impacts. 
8.6. 
At the same time, the matter of apportionment of funding responsibility was considered and 
recommendations were put before both Horizons and WDC in August 2017 (Item 17-153). 
8.7. 
In its 2018-28 LTP, HRC made provision for a programme of essential maintenance works 
to ensure that the aging river control works, designed to regulate the alignment of the lower 
reach of river and protect the port, continues to function as intended. WDC, through its LTP 
(page 15), made  provision for funding  25% of work on the moles at  the river mouth for a 
period of 10 years.  
8.8. 
Concurrent  with  the  development  of  the  2018-28  LTP,  discussions  were  progressed  with 
Central  Government  in  an  effort  to  secure  funding  assistance  with  the  works  that  in 
particular would enable an accelerated programme and commensurate reduction in the risk 
of failure of existing structures. 
8.9. 
Ultimately  an  application  for  funding  through  the  Provincial  Growth  Fund  was  lodged  in 
August 2019 and in July 2020 an agreement between MBIE and Horizons was executed. 
The  agreement,  which  terminates  in  March  2025,  provides  for  a  defined  programme  of 
work, estimated to cost $15M, with a maximum MBIE contribution of $7.5M. Council item 
20-128 identified the change in  expenditure profile. With the Central Government funding 
secured,  Horizons  formal y  committed  to  the  River  Training  Structures  Project  and made 
provisions for funding through adoption of the 2021-31 Long Term Plan. 
8.10.  The agreement with MBIE included a key Establishment Condition Precedent requiring the 
funding  recipient  to  establish  a  governance  structure  consistent  with  legislative 
requirements  under  the  Te  Awa  Tupua  Act,  with  appropriate  stakeholder  and  community 
membership,  including  the  Recipient,  WDC  and  Ngā  Tāngata  Tiaki  o  Whanganui. 
Furthermore the Precedents required that the Project be a truly community led exercise in 
accordance  with  the  Te  Awa  Tupua  legislation;  that  there  be  effective  engagement  with, 
and the support of Whanganui Settlement Negotiations Trust and Ngā Tāngata Tiaki; and 
that  Tupua  te  Kawa,  the  innate  values  of  Te  Awa  Tupua  legislated  in  the  2017  Act,  be 
incorporated into the governance model and project delivery approach of the project. 
8.11.  In  accordance  with  these  precedents,  a  Governance  Group  has  been  established;  a 
Project  Director  (Hayden  Turoa)  has  been  appointed;  a  hapūtuawhā  mandated  group  of 
five  –  Te Mata  Pūau,  has  been  formed  to  lead  the  project  partners  to  a  greater 
understanding  of  their  obligations  to  Te  Awa  Tupua  and  Tupua  Te  Kawa;  and  formal 
approval for progression from Establishment Phase to Delivery Phases has been received 
from Kānoa – the Regional Development and Investment Unit of MBIE. At a delivery level, 
the river training structures project component of the overal  Whanganui Port Revitalisation 
Programme,  now  referred  to  as  Te  Pūwaha,  is  being  managed  as  a  true  partnership 
between Te Mata Pūau and Horizons staff.  
8.12.  The other components of Te Pūwaha are: 
  The Port Revitalisation Project (port structures and dredging) managed by WDC: 
  The Q West Project (relocation and expansion of boat building business), managed by 
Q-West Properties; and 
  The Te Ara Mahi Project (Port Employment Precinct) managed by Whanganui District 
Employment Training Trust. 
9. 
ORIGINAL PROJECT SCOPE & BUDGET 
9.1. 
A  summary  of  the  three  stages  of  the  River  Training  Structures  Project,  including  the 
budgets  as  approved  by  Central  Government  through  MBIE  is  shown  in  Table  1.  An 
overview of the location and works is provided in Figure 1. 
 
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 6 
 



Regional Council 
27 April 2022 
  
Table 1: Summary of the three stages of the project as approved by central government.  
Stage 
Description 
Original Estimated Cost ($) 

Project establishment and upgrade/strengthening of North Mole and 
7,026,667 
revetment 
2A 
Construction of trial section (50m) of Tanae Groyne and upgrade of 
1,000,000 
South spit Interface wal . 
2B 
Upgrade/strengthening of South Mole 
5,386,667 
 
Possible extension of Tanae Groyne and improvements/strengthening of 
1,586,667 

various South Spit training structures 
Total 
 
15,000,000 
 
Figure 1: Photo of the area showing the location of the North and South Mole, as wel  as the Tanae Groyne 
(labelled  Rock  Groyne  reconstruction  on  the  image).  Inset  shows  the  current  erosion  control  structures  and 
south spit embayment (upstream of the Tanae Groyne), relating to Stage 3. 
10. 
PROJECT PROGRESS  
10.1.  The project has successful y developed a project management structure that is consistent 
with  the  Te  Awa  Tupua  legislation;  obtained  resource  consents,  awarded  contracts  and 
progressing Stage 1 works. 
10.2.  Major  contracts  have  been  awarded  for  rock  supply  ($3,273,420)  and  North  Mole 
re-construction ($3,979,140), a total of $7,252,560. As at the end of March, rock supply is 
65%  completed  and  is  on  track for  completion  in  accordance with the  contract  schedule. 
The  placement  contract  has  been  blessed  with  some  extremely  clement  weather,  is 
approximately  28%  complete,  and  is  presently  on  schedule  for  completion  in  November 
2022. 
10.3.  With  Stage  1  works  now  wel   underway,  some  staff  resources  have  been  assigned  to 
preparatory  work  in  relation  to  both  Stages  2A  and  2B.  The  decision  to  separate  these 
components  was  driven  by  the  fact  that  for  Stage  2A  (trial  section  of  Tanae  Groyne  and 
associated works) design work had already been completed and relatively straight forward 
consenting  and  community  consultation  processes  were  anticipated.  By  comparison,  a 
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 7 
 


Regional Council 
27 April 2022 
  
significant  amount  of  design,  options  assessment,  and  execution  methodology  work  in 
respect of Stage 2B (South Mole) is yet to be undertaken. 
10.4.  To  date,  with  respect  to  Stage  2A  a  draft  assessment  of  environmental  effects  (AEE) 
has been completed and is presently being reviewed by Te Mata Pūau and a draft consent 
application is near completion. It is anticipated that a consent wil  be granted and that we 
wil  be in a position to cal  tenders for the work in July. Completion is programmed during 
year 2022/23. 
10.5.  As  for  Stage  2B,  Tonkin  and  Taylor  have  been  commissioned  to  undertake  preliminary 
design and option assessment work. Other consultants have been engaged to complete an 
aquatic  impact  assessment  and  to  prepare  a  draft  resource  consent  application.  It  is 
anticipated that design options, which could have significantly different cost impacts, wil  be 
available  for  assessment  and  for  Council’s  consideration  in  May.  Current  programming 
assumes that a single rock supply and placement contract for this work wil  be awarded by 
October 2022, and that al  work wil  be completed in the 2023/24 year. 
11. 
REVISED BUDGET 
11.1.  At  the  funding  application  stage,  estimates  were  necessarily  ‘rough  order  of  cost’  on 
account  of  the  substantial  quantities  of  particularly  large  sized  and  high  quality  rock 
required  and  the  known  difficulty  of  sourcing  that  material.  There  was  also  little  recent 
experience with placing such large material in such an exposed coastal location. 
11.2.  Now  that  the  major  contracts  have  been  awarded  for  Stage  1,  there  is  increased 
confidence in our revised estimated cost to completion of Stages 1 & 2 (Table 2). Revised 
cost estimates for Stages 2A and 2B take account of experience gained through Stage 1 
contract processes; reflect now understood broader project management costs; and to the 
extent possible, anticipate increased civil engineering works costs resulting from fuel price 
increases and strained industry capacity. Revised estimates for Stage 2A can be regarded 
with a reasonable degree of confidence, however until a preferred design for Stage 2B has 
been  approved,  and  consequently  rock type and  quantities are known,  estimates for  that 
work must be regarded as ‘rough order’. 
Table 2: Comparison of the original and proposed revised budget for Stage 1 & 2 of the project.     
Estimated 
Estimated 
Difference 
Difference 
Stages 1 & 2 
cost - original 
revised cost 
($) 
(%) 
budget ($) 
March 2022($) 
Project planning and support 
 
 
 
 
Consents 
130,000 
229,915 
99,915 
77% 
Investigation/designs 
160,000 
313,995 
153,995 
96% 
Comms + project management 
833,334 
2,130,970 
1,297,636 
156% 
Sub total 
1,123,334 
2,674,880 
1,551,546 
138% 
Construction 
 
 
 
 
Stage 1 North mole 
6,490,000 
7,286,638 
796,638 
12% 
Stage 2 A Tanae Groyne 
800,000 
1,000,000 
200,000 
25% 
Stage 2 B South Mole 
5,000,000 
5,200,000 
200,000 
4% 
Sub total 
12,290,000 
13,486,638 
1,196,638 
10% 
Total Stages 1 & 2 
13,413,334 
16,161,518 
2,748,184 
20% 
11.3.  The  current  estimated  cost  to  completion  for  Stage  1&2  (Table  2),  including  al   project 
establishment  and  management  costs,  is  $16,161,518  which  is  20%  over  the  original 
estimate ($13,413,334). The updated estimate does include a contingency sum and at this 
stage it is assumed that wil  be required. The main outstanding uncertainty is in relation to 
the  two  fishing  platforms  that  are  currently  the  subject  of  a  Provisional  Sum  in  the 
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 8 
 


Regional Council 
27 April 2022 
  
placement  contract.  Staff  are  aiming  to  have  a  firm  sub-contract  price  for  that  item 
confirmed for Council on 27 April.  
11.4.  These fishing platform costs are a key contributor to the variance for Stage 1. These are an 
example  of  the  cost  of  meeting  community  aspirations  for  enhanced  amenity  and  were 
committed to as a part of the consent for delivery within the project works. Developing such 
ideas is an integral part of the project (see Section 14 below). Within the Stage 1 project 
the two original fishing platforms that had to be demolished as part of the works comprised 
simple concrete slabs at the top of the river bank. Estimated cost to demolish and replace 
these at the top of the raised and reconstructed rock lining was identified and budgeted at 
$250,000.  However,  an  extensive  engagement  process  has  arrived  at  a  preference  for 
more  elaborate  stepped  concrete  structures  which  wil   provide  for  considerably  improved 
fishing amenity and a multi-purpose function. A detailed design has been completed and a 
Provisional  Sum  of  $1.0M  is  included  in  the  placement  contract  for construction  of  these 
much more  complex  structures.  Further  comment  is  made  below  with  regard  to  potential 
amenity enhancement costs over the balance of the project. 
11.5.  A variety of factors contribute to the other variances in the revised budget for Stage 1&2, 
including  (primarily)  the  above  referred  to  uncertainty  around  rock  supply  and  placement 
costs; project-heavy communications activity, and costs related to the Project Director role 
and the application of the of the principles of Tupua Te Kawa being largely unbudgeted at 
the time of seeking PGF funding. These costs were not included in the estimates submitted 
with the funding application and Council via item 20-128 authorised Horizons entering into 
a funding agreement between NgāTangita Tiaki, WDC, and Horizons “… that provides for 
both a Project Director and that al ows for Ngā Tangata Tiaki to fulfil its statutory function 
as defined by the 2017 Te  Awa  Tupua (Whanganui River Claims Settlement) Act”. While 
these  costs  were  not  original y  identified  with  the  project  budgets  MBIE  has  recently 
confirmed that they are eligible for the 50% funding assistance, but only to the extent that 
they  can  be  accommodated  within  the  fixed  government  contribution  of  $7.5M.  A 
breakdown of budgeted project management costs for the project (al  three stages) and the 
updated estimates through to the completion of Stage 2, is shown in Table 3.  
Table 3: Summary of changes to River Training Structures project management costs for the project.  
Description 
Original 
Revised 
Difference 
HRC share 
Estimate ($) 
budget ($) 
($) 
of cost ($) 
Horizons  River  Management  staff  inputs  to  funding 
1,200,000 
1,366,489 
166,489 
1,366,489 
application, consents, community consultation, contract 
documentation, 
tender 
processes, 
contract 
management, works supervision, reporting. 
Project Director - overal  Te Pūwaha Project leadership. 
nil 
215,834 
215,834 
215,834 
Note this is 30% of the overal  cost. The other 70% (not 
shown in this table) is paid for by WDC over and above 
the  WDC  commitment  to  the  river  training  structures 
component of the Te Pūwaha project. This arrangement 
reflects  Horizons  funding  the  Project  Director 
contribution to the River Training Structures part of the 
broader Te Pūwaha project. 
Te Mata Pūau - leading the funded project partners to a 
nil 
201,640 
201,640 
201,640 
greater  understanding  of  their  obligations  to  Te  Awa 
Tupua  and  Tupua  Te  Kawa.  Horizons  portion  (30%  of 
total cost for the broader project).   
Cultural Monitor / Iwi Advisor 
nil 
192,146 
192,146 
192,146 
Total 
1,200,000 
1,976,109 
776,109 
1,976,109 
11.6.  A summary of revised estimated costs for Stages 1 and 2, relative to original estimates for 
the whole project, is presented in the Table 4 below. As a result of the increases in costs 
for delivery of Stages 1 & 2 there is insufficient budget to complete both Stages 1 & 2 and 
a reduced scope for the project as Stage 3 can no longer fit into the budget.  
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 9 
 


Regional Council 
27 April 2022 
  
11.7.  To  complete  Stages  1&2  it  is  estimated  that  $1.162M  of  further  funding  wil   be  required 
over  and  above  the  total  project  budget  of  $15M.  For  the  purposes  of  the  resolution  for 
Council  this  paper  has  included  additional  sums  of  $100,000  for  scoping  in  relation  to 
Stage 3 works (see Section 13 below) and $100,000 for amenity enhancement works (see 
Section 14 below). The total additional budget required to complete Stage 1&2 and these 
additional  pieces  of  work  is  estimated  at  $1.36M  above  the  original  project  budget.  As 
noted above there are uncertainties in this estimate and for the purposes of the resolution 
the  amount  has  been  rounded  to  $1.4M,  noting  uncertainties  stil   remain  even  with  that 
increased amount.  
11.8.  Horizons have notified the Governance Group of the project, WDC and MBIE of the budget 
shortfal s including the reduction in scope to remove Stage 3 from the central government 
co-funded  project.  MBIE  have  verbal y  accepted  this  change  in  scope,  and  Horizons  are 
awaiting written confirmation of the acceptance of this change in scope to the contract.  
 
 Table 4: Comparison of the original and proposed revised budget for the project.    
Estimated cost 
Estimated revised 
 
Difference 
Difference 
Stage 
- original 
cost - March 2022 
($) 
(Percentage) 
budget ($) 
($) 

7,026,667 
8,563,647 
1,536,980 
22% 
2A 
1,000,000 
1,200,000 
200,000 
20% 
2B 
5,386,667 
6,397,871 
1,011,204 
19% 
Stage 1 & 2 subtotal 
13,413,334 
16,161,518 
2,748,184 
20% 
Stage 3 
1,586,667 

-1,586,667 
removed from scope 
Stage 3 scoping only 
 
100,000 
100,000 
new 
Further amenity enhancement 
 
100,000 
100,000 
new 
scoping & implementation 
Total 
15,000,000 
16,361,518 
1,361,517 
8% with reduced scope 
Funding 
KANOA/MBIE 
7,500,000 
7,500,000 

0% 
Horizons 
5,700,000 
7,061,518 
1,361,518 
24% 
WDC 
1,800,000 
1,800,000 

0% 
Total 
15,000,000 
16,361,518 
1,361,518 
8% with reduced scope 
12. 
POTENTIAL RATING IMPACT 
12.1.  The  River  Training  Structures  part  of  the  overal   programme  is  funded  via  an  agreement 
between MBIE and Horizons dated 10 July 2020. This provides for a Central Government 
contribution  of  up  to  $7.5M  towards  a  $15M  project  to  strengthen  and  upgrade  old  river 
training structures in the lower reach of the Whanganui River. Horizons contribution to this 
project is $5.7M and WDC’s contribution $1.8M. Horizons contribution to this project is loan 
funded  over  25  years  from  2021/22.  The  loan  being  serviced  via  the  Lower  Whanganui 
River  Scheme  that  has  a  funding  policy  of  80%  targeted  rates  and  20%  general  rate 
contribution.  
12.2.  The Lower Whanganui Scheme has other current/planned capital projects including:  
  Kowhai Park Egress Gate upgrade which is loan funded over 20 years from 2023/24;  
  Kowhai Park water inflated property protector (WIPP) replacement which is loan funded 
over 20 Years from 2021/22; 
  Putiki Stopbank Project which is loan funded over 20 Years from 2023/24; 
  CBD Upgrades/Climate Change which is loan funded over 20 Years from 2023/24; 
  Q-West Stopbank Upgrade which is planned to be loan funded.  
12.3.  The  proposed  changes  to  the  Annual  Plan  budget  for  2022-23  and  beyond  include 
consideration of a range of factors as outlined below.  
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 10 
 


Regional Council 
27 April 2022 
  
12.4.  A  primary  consideration  for  the  revised  budgets  is  the  forecast  increased  costs  for  the 
delivery  of  Stages  1  and  2  which  are  now  projected  to  be  delivered for  a  total  budget  of 
$16.2M,  being  approximately  $2.75M  or  20%  higher  than  original y  budgeted.  Cost 
increases  relate  to  project  management  and  communications  $1.297M,  consenting  and 
design $0.254M, construction costs for stage 1 ($0.8M) and for Stage 2 $0.4M. It is noted 
that the cost projection for Stage 1 construction includes a provisional sum of an additional 
$0.75M for two fishing platforms and  staff  are  working to  get further certainty around this 
amount prior to the Council meeting;  
12.5.  Proposed budgets for the Annual Plan also require alignment with Horizons rating with the 
funding commitments of the government contract for the River Training Structures part of 
the  Te  Pūwaha  project.  Currently  Horizons  LTP  for  2018-2028  and  LTP  2021-2031  both 
overestimate the WDC contribution at 25% rather than  the fixed $1.8 mil ion contribution. 
This  requires  an  increase  of  the  Horizons  contribution  via  the  loan  and  is  partial y  offset 
over the longer term by Horizons having committed additional funding to this work over a 
longer period of time in the LTP.   
12.6.  The revised budgets also account for new information on the phasing of Horizons planned 
expenditure on this project. This includes under expenditure in previous years and updated 
budgets  for  the  next  two  years.  The  Lower  Whanganui  Scheme  was  $3.065  mil ion 
underspent  in  the  2020-21  year  (last  financial  year)  including  $2.883M  for  the  River 
Training  Structures  project.  The  forecast  for  the  current  year  is  to  spend  $5.633M  of  the 
$6.698M  budget  a saving  of  $1.065M for  the  Lower Whanganui  Scheme  projects.  These 
savings to the budgets have an impact of lower loan repayment requirements for this and 
the future years until the works programme “catches up”.  
12.7.  The  underspends  in  the  previous  years  have  also  required  additional  work  to  be 
programmed,  and  budget  to  be  al ocated,  for  the  next  two  years  in  order  to  deliver  the 
River  Training  Structures  project,  including  the  increased  costs  that  have  been  identified 
above. These costs wil  impact on the loan repayments to a limited extent in the year the 
work is completed and more so in the years of the loan after the work is completed.  
12.8.  The  phasing  of  other  Lower  Whanganui  Scheme  related  work  has  also  been  revised  as 
shown in Table 5. Overal  the increased costs for the two years is $1.365M more than the 
LTP noting some works previously budgeted have been deferred to 2024 or beyond. 
Table 5: Comparison of LTP and proposed revised budgets for the 2022-23 and 2023-24 financial years. 
LTP 
Forecast      Difference 
LTP 
Forecast      Difference 
LTP 
Forecast      Difference 
Project 
Budget           
Budget           
Budget           
2022-23 
2022-23 
2022-23 
2023-24 
2023-24 
2023-24 
2022-24 
2022-24 
2022-24 
Q-West stopbank 
upgrade 
175,026 
25,361 
-149,665 

23,520 
23,520 
175,026 
48,881 
-126,145 
Climate change 
impact - CBD 
178,768 
28,061 
-150,707 
162,639 
176,100 
13,461 
341,407 
204,161 
-137,246 
Kowhai Park - 
replacement of 

243,104 
243,104 
161,461 
19,725 
-141,736 
161,461 
262,829 
101,368 
portable flood barriers 
Kowhai Park egress 
gate 
0   

164,172 
164,603 
431 
164,172 
164,603 
431 
Putiki flood protection 
project 
26,914 
26,912 
-2 
529,830 
472,668 
-57,162 
556,743 
499,580 
-57,163 
Sub total 
380,708 
323,438 
-57,270  1,018,101 
856,616 
-161,485  1,398,809  1,180,054 
-218,755 
River Training works 
6,455,608  7,661,444  1,205,836  1,863,806  2,241,933 
378,127  8,319,414  9,903,377  1,583,963 
Total Lower 
Whanganui Scheme 
6,836,316  7,984,882  1,148,566  2,881,907  3,098,549 
216,642  9,718,223  11,083,431  1,365,208 
12.9.  The under expenditure in previous and current years, re-phasing of budgets and the loan 
mechanism for Horizons funding al   combine  to  limit the  impact  of  the  increased  budgets 
for the River Training Structures project on Lower Whanganui Scheme Rates over the next 
two years (Table 6). However the deferral of other Lower Whanganui Scheme works and 
increased  work programme  on  the  River  Training  Structures  over the  next  two  years are 
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 11 
 


Regional Council 
27 April 2022 
  
projected  to  result  in  increases  in  2024-25  and  beyond.  These  increases  are  difficult  to 
forecast at this stage, as some of the work is not ful y scoped at this point in time, including 
if the potential budgets for Stage 3 of the River Training Structures project.    
Table 6: Comparison of Horizons targeted rate contributions to the Lower Whanganui Scheme.    
Financial year 
2021-22 
2022-23 
2023-24 
Total 
Long Term Plan year 



 
Project year 
Year 2 
Year 3 
Year 4 
 
LTP Targeted rate  ($) 
$619,019 
746,911 
807,357 
2,173,287 
New Annual Plan targeted rate ($) 
$619,019 
735,055 
823,033 
2,177,107 
Movement ($) 

-11,856 
15,676 
3,820 
13. 
STAGE 3 WORKS  
13.1.  The works proposed under Stage 3 comprised of: 
  Possible extension of Tanae Groyne; and 
  Improvements/strengthening  of  South  Spit  erosion  protection/training  structures 
upstream of Tanae Groyne. 
13.2.  The  purpose  of  Tanae  Groyne  is  to  deflect  river  flows  into  the  port  entrance  adjacent  to 
Wharf  1, to  facilitate  necessary sedimentation for south  westerly  wave  dissipation and  to 
protect  the  South  Mole  and  Interface  Wal   structures.  Deflecting  river  flows  wil   ensure  a 
navigable depth for vessels to  enter the turning basin and possibly  reduce the  amount  of 
dredging  that  is  required.  The  purpose  of  strengthening  the  very  old  South  Spit  erosion 
control  structures  would  be  to  maintain  river  alignment  and  reduce  the  likelihood  of  the 
river breaching through the Spit (as happened in 1946, Figure 3) and outflanking the South 
Mole, particularly at the South Spit embayment.  
13.3.  The possible need to extend the initial 50m length of Tanae Groyne (to be constructed in 
Stage  2A),  in  order  to  achieve  the  desired  degree  of  sedimentation  and  main  flow 
deflection  from  South  Spit,  has  previously  been  raised  by  Tonkin  and  Taylor.  However 
before a decision is made in that regard, some monitoring of the performance of the initial 
trial  section  of  Groyne  should  be  undertaken.  It  is  likely  to  require  at  least  two  or  three 
annual  floods  before  effects  are  apparent  and  accordingly  it  is  difficult  at  this  stage  to 
predict if an extension is indeed required, what scale of extension might be required, and 
what the timing of any works should be.  
13.4.  A  similar  situation  applies  with  regards  to  improvements  to  certain  erosion 
protection/training  structures  along  South  Spit  (Figure  4,  Figure  5).  In  particular  the 
treatment  of  a  large  erosion  embayment  immediately  upstream  of  the  Tanae  Groyne  is 
specifical y  identified  in  the  funding  agreement.  However  the  nature  and  extent  of  works 
required,  and  possibly  even  the  need  for  works,  could  wel   be  influenced  by  the 
performance  of  the  trial  section  of  Tanae  Groyne  being  constructed  as  Stage  2A  of  the 
project (scheduled for completion by 30 June 2023). 
13.5.  Accordingly, given that the ful  cost of Stage 3 works wil  need to be funded by Horizons. 
Council may wish to defer any Stage 3 work at this time and to receive separate proposals 
for funding of such works under the Whanganui River Scheme, as and when their need is 
confirmed.  In  this  case,  staff  would  recommend  that  the  sum of  $100,000  be  included  in 
the revised Te Pūwaha project budget to al ow for monitoring of completed Stage 1 and 2 
works and for scoping investigations into possible Stage 3 measures. Detailed design and 
consenting  for  any  ultimately  recommended  measures  would  then  be  included  in  future 
estimates.   
 
 
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 12 
 




Regional Council 
27 April 2022 
  
 
 
Figure 3: Photos of the breach of the South Spit in 1946 (Source unknown).  
 
 
 
Figure  4:  Photo  of  the  area  showing  the  location  of  key  river  management  infrastructure  in  the  lower 
Whanganui River. Note Stage 3 of the project relates to structures upstream of the Tanae Groyne on the same 
side of the river, including the South spit embayment, south spit Groynes and concrete walls. Map created in 
2017.  
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 13 
 



Regional Council 
27 April 2022 
  
 
 Figure 5: Map of the South Spit erosion protection/alignment control works. 
14. 
Amenity enhancement projects 
14.1.  The amenity enhancement works that have been specifical y included in the revised project 
budgets are those relating to the enhanced fishing platform construction referred to above; 
a North Mole amenity concept design and a star compass design. A report on the He Ara 
Tuku Rau abundance model has also been completed, in February 2022, as a part of the 
project  providing  an  abundance  focussed  assessment  framework  to  support  decision 
making.  
14.2.  Other  additional  potential  amenity  enhancement  items  that  have  been  identified  to  date 
through community engagement include those identified in Table 6 below. Cost estimates 
have  been  derived  through  an  informal  working  group  including  the  Project  Director, 
members from Horizons, WDC, and the community group Progress Castlecliff. Some items 
have been priced to a reasonable degree of accuracy, for example the carpark, which was 
estimated  by  the  WDC  Roading  Al iance.  The  majority  of  estimates  are  however  ‘rough 
order’,  being  based  on  concepts  rather  than  defined  outcomes.  There  is  clearly  a  desire 
from  the  community  that  Horizons  and  WDC  deliver  these  outcomes,  with  as  much 
external  funding  assistance  as  can  possibly  be  sourced,  however,  no  commitment  has 
been given to delivery or funding of these at this point in time. It is important to note that 
WDC  are currently  recruiting  for a  Project  Manager  to drive  these  sub-projects,  including 
the  application for external funding, and it  has been  proposed that Horizons contribute  to 
this position. 
14.3.  This  paper  highlights  to  Council  the  types  of  projects  that  are  being  considered  and 
discussed  as  a  part  of  the  community  engagement  and  includes  a  provision  for  some 
projects (as outlined above). The proposed revised budgets above also make provision for 
further scoping and potentially further implementation of some of these up to a total budget 
of  $100,000  over  the  next  two  years  with  any  further  proposals  to  be  decided  on  by 
Council ors  through  the  usual  Council  processes  including  Annual  Plan  and  Long-term 
Plan processes.    
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 14 
 


Regional Council 
27 April 2022 
  
 
Table 6: Potential projects identified through community engagement in relation to the Te Pūwaha Project.    
 
Item 
‘Rough  order’ 
estimated cost 

Improved North Mole Car Park (including services, lighting and viewing area) 
$1,500,000 

Toilet & Shower 
$250,000 

Dune Restoration (North and South) 
$200,000 

Additional Fishing Platforms (x2) – further to those in Stage 1 
$800,000 

Star Compass 
$100,000 

North Mole Landscaping (Arts & Design eg interpretive panels and māori artwork 
$200,000 

Upstream Amenities (smal  carpark, picnic area, seating etc.) 
$500,000 

Project Management Resource to deliver outcomes 
$600,000 
 
Total 
$4,150,000 
15. 
CONSULTATION 
15.1.  Community engagement  through  Te  Mata  Pūau wil   be  ongoing  for the term of  the  River 
Training Structures project. No additional consultation is planned at present, however it is 
likely  that  the  Te  Pūwaha  project  could  be  included  in  some  form  of  further  consultation 
related to the forthcoming Annual Plan processes. 
16. 
TIMELINE / NEXT STEPS 
16.1.  Councils  decisions  on  this  paper  wil   be  incorporated  into  the  Annual  Plan  process  and 
inform next steps for the project.   
17. 
SIGNIFICANCE 
17.1.  This  is  not  a  significant  decision  according  to  the  Council’s  Policy  on  Significance  and 
Engagement. 
Al an Cook 
 
 
 
Dougal Ross   
PROJECT ENGINEER 
 
PROJECT ENGINEER 
 
 
 
Adrian Smith    
 
 
Jon Roygard 
CHIEF FINANCIAL OFFICER 
GROUP MANAGER CATCHMENT OPERATIONS 
 
 
ANNEXES 
There are no attachments for this report.     
 
Lower Whanganui Scheme - Te Pūwaha Update 
Page 15