This is an HTML version of an attachment to the Official Information request 'AT Auckland Cycle Model Review and Validation'.


technical note 
PROJECT 
WAITEMATĀ HARBOUR WALKING AND CYCLING CONNECTION 
DEMAND AND ECONOMIC BENEFITS ASSESSMENT OF FERRY AND BUS 
SUBJECT 
OPTIONS 
Out of scope  (WAKA KOTAHI), Section 9(2)(a)
TO 
(COMMUTE) 
FROM 
Section 9(2)(a)
REVIEWED BY 
Section 9(2)(a)
DATE 
18 FEBRUARY 2022 (UPDATED 22 MARCH 2022) 
Flow  Transportation  Specialists  (Flow)  has  been  commissioned  by  Waka  Kotahi  the  New  Zealand 
Transport Agency (Waka Kotahi) to assess a number of walking and cycling connection options across 
Auckland’s Waitematā Harbour. Our assessment has focused on 

each option’s potential for cycling trips across the harbour

each option’s economic benefits

benefit cost ratio, for select options.
The options being investigated include 3 potential new ferry/bus connections, 2 options that improve 
existing ferry services, in addition to 1 option that makes use of the existing Auckland Harbour Bridge 
(AHB). Each of these investment options would better link the lower North Shore to central Auckland, 
connecting Waka Kotahi’s proposed Northern Pathway walking and cycling path to the city centre. The 
need for these connections has arisen since the previous proposal of a dedicated walking and cycling 
bridge across the Waitematā Harbour is no longer being considered. 
Importantly, our assessment has focused on the potential for each investment option to cater to cycling 
trips. Our assessment does not consider the impacts each option may have on public transport trips1. 
1  THE FERRY AND BUS OPTIONS ASSESSED 
under the Official Information Act 1982
Our assessment has considered 6 walking and cycling connection options provided by Waka Kotahi. Each 
of  the  6  connection  options  includes  the Akoranga  to  Sulphur  Point section  of Northern Pathway,  in 
addition to a new or improved connection across the Waitematā Harbour 

Option  2F:  a  new  ferry  service  between  Sulphur  Point  (the  southern  extent  of  Waka  Kotahi’s
proposed Northern Pathway) and Westhaven

Option 2G: a new ferry service between Sulphur Point and North Wharf in the Wynyard Quarter
Released 
1 Each of the 5 bus/ferry investment options may result in changes to the number of people walking, driving and/or 
busing to the ferry/bus terminals. 



 
 
Option 2H: increased frequencies of the existing Northcote to Downtown ferry service, as well as 
improved cycle-ferry transfer facilities 
 
Option 3D: increased frequencies of the existing Devonport to Downtown ferry service, as well as 
improved cycle-ferry transfer facilities 
 
Option  5E:  a  new  bus  service  between  the  toll  plaza  on  the  Northern  Motorway  (close  to  the 
southern extent of Waka Kotahi’s proposed Northern Pathway) and the Shelly Beach Road/Curran 
Street ramps (assumed to turn around via Onewa Road and Jervois Road) 
1982
 
Option AHB: a new shared use path across the existing Auckland Harbour Bridge (AHB). Space for 
this  facility  is  expected  to  be  made  by  removing  one  or  more  traffic  lane  on  the  bridge.  The 
resulting shared path is expected to be in the order of 3 m wide, which is relatively narrow given 
Act 
the level of demand anticipated. This width, and the proximity to motorway traffic, will have an 
impact on the quality of service provided to users, and on the capacity of the path. 
2  HOW WE HAVE ASSESSED THE OPTIONS 
We have used the Auckland Cycle Model (ACM) to estimate cross-harbour cycling trips for each of the 
options.  The  ACM  estimates  future  cycling  and  e-bike  demands,  and  responds  to  anticipated  future 
changes in  
Information 
 
Infrastructure – the ACM recognises that people are more likely to ride bikes and e-bikes if quality 
cycle infrastructure is provided along their route 
 
Future e-bike uptake – the ACM assumes that over time, the accessibility of e-bikes will increase, 
giving more people the option to cycle more often, and greater distances 
 
Trip characteristics – the ACM recognises that shorter trips are more likely to be carried out on a 
Official 
bike, as are trips to work and school, and trips without steep gradients 
 
The underlying demand for travel – the ACM is informed by the regional transport model, being 
the 
Auckland’s Macro Strategic Model (MSM) 
 
Land use growth – the ACM is informed by Auckland Council’s land use forecasts. 
We have assessed each of the 6 options by considering the “generalised cost” of cross harbour cycling 
trips with each option. Generalised costs sum the monetised and non-monetised costs of a journey, and 
under 
include the financial cost (fare) for the journey, waiting time, loading/unloading time, the actual journey 
time,  as  well  as  a  “transfer  penalty”.  The  transfer  penalty  is  a  perceived  time  penalty  due  to  the 
inconvenience of transferring between modes. The ACM uses time as a measure of generalised costs, 
with monetised costs converted to time using standard Waka Kotahi values of time2. 
The financial fare of each trip is the most significant component of the generalised cost, accounting for 
around  50%-70%  of  the  total  for  each  bus  or  ferry  connection  option.  This  is  because  our  default 
assessment assumes the current ferry and bus fares would apply to the new/improved services: $5.66 
Released 
 
2 We have applied a weighted average of Waka Kotahi’s standard values of time for cyclists of $12.52/hour, based on 
80% commuting to work ($6.60/hr), 10% work travel purposes ($21.70/hr) and 10% other ($4.25/hr), and the December 
2021 update factor of 1.59 (Monetised Benefits and Costs Manual, table 13) 
 
 


1982
Act 
Information 
Official 
the 
under 
Released 



 
Four of the investment options (2F, 2G, 2H and 5E) are predicted to result in very comparable outcomes, 
with 510-590 daily cycle trips across the harbour in 2028. Option 3D however (improvements to the 
Devonport ferry terminal and services), is not predicted to result in any significant increase in cyclists 
using the Devonport ferry. A small increase in cyclists using the Northcote ferry is predicted however – 
a result of the improved connections to this ferry terminal provided by the Akoranga to Sulphur Point 
section of Northern Pathway. 
Our assessment of each option has relied on a series of assumptions for each cross-harbour connection 
1982
option. We have sensitivity tested some of those key assumptions, including 
 
A lower quality transfer: the default assessment assumes a seamless integration between cycle 
and ferry, at a purpose built facility. This test considers the effects of a lower standard of transfer 
Act 
facility 
 
Akoranga to Constellation (A2C): the default assessment includes the Akoranga to Sulphur Point 
section of Northern Pathway with each new connection option, but not the onward connection 
from A2C. This sensitivity test considers the impact of including this section of Northern Pathway 
(completing the route from Sulphur Point to Albany) 
 
Low  fare:  the  default  assessment  assumes  the  new  connection  will  have  a  fare  matching  the 
existing inner harbour ferry/bus route fares. This sensitivity test considers the effects of reducing 
this fare to $2 per trip 
Information 
 
A combination of low fare and including A2C 
 
Zero fare: this sensitivity test considers the impact of a fare-free trip across the harbour 
 
A combination of zero fare and including A2C 
 
For  option  2G,  a  range  of  sensitivity  tests  that  additionally  assume  reduced,  20 minute  ferry 
Official 
frequencies (all other options assume 10 minute frequencies). 
The results are presented in Table 2. We note that the default assumptions and first 3 sensitivity tests 
the 
all include a fare component for the ferry and bus options. This component is not relevant for the AHB 
path option, which is expected to be free.  
under 
Released 
 
 


1982
Act 
Information 
Official 
the 
under 
Released 


1982
Act 
Information 
Official 
the 
under 
Released 



 
We note that option 3D (Devonport ferry) has estimated discounted benefits of Section 9(2)(j). This benefit 
is the result of completing the Akoranga to Sulphur Point section of Northern Pathway, rather than the 
result of any improvements to the Devonport ferry.  
The  estimated  benefits  for  each  of  the  other  options  can  then  be  viewed  in  light  of  this Section 9(2)(j) 
benefit. Option 2F for example is predicted to result in Section 9(2)(j) in benefits: Section 9(2)(j) associated 
with the Akoranga to Sulphur Point section of Northern Pathway, and a further Section 9(2)(j) associated 
with the additional ferry link. 
1982
The economic benefits presented in Table 3 point to the incremental benefits of a series of potential 
investment steps. In the case of Option 2G (Sulphur Point to Wynyard Quarter), these incremental steps 
Act 
are: 
 
Section 9(2)(j)  in benefits for the Akoranga to Sulphur Point section of Northern Pathway 
 
a further Section 9(2)(j) in benefit, should the new option 2G ferry route be provided (with standard 
fares charged but low ferry frequencies) 
 
a further Section 9(2)(j) in benefit, should the new ferry route have increased ferry frequencies 
 
a further Section 9(2)(j) in benefit should the new ferry route also be fare free 
 
a further Section 9(2)(j) in benefit, should the A2C section of Northern Pathway also be provided  
Information 
 
a further Section 9(2)(j) in benefit, should a constrained shared path be provided using an existing 
traffic lane on the existing harbour bridge, rather than the ferry route 
 
at  least  a  further Section 9(2)(j)  in  benefit,  should  a  high  quality,  dedicated  walking  and  cycling 
connection be provided, rather than the above constrained shared path on the existing bridge. 
Official 
The Section 9(2)(j)  now  assessed  for  a  shared  path on  the  existing  harbour  bridge,  plus  the remaining 
sections of Northern Pathway, falls comfortably below  the estimated Section 9(2)(j) for the previously 
proposed dedicated bridge. Lower benefits are expected in this case due to the narrower path width 
the 
now proposed, and the close proximity to motorway traffic. This is expected to result in less use overall, 
relative to the previously proposed new bridge. 
3.3  Estimated benefit cost ratios 
under 
Table  4  presents  the  BCRs  for  select  investment  scenarios,  based  on  the  following  cost  estimates 
provided by Commute: 
 
Section 9(2)(j)   capital  costs  for  Wynyard  to  Akoranga.  We  have  assumed  a  further  1%  annual 
maintenance costs Section 9(2)(j) per year) 
 
Section 9(2)(j)   capital  costs  for  the  Option  2G  ferries  and  terminals,  with  a  further Section 9(2)(j) 
annual operating and maintenance costs. These operating costs have been offset by the estimated 
fare revenue, for relevant scenarios 
Released 
 
Section 9(2)(j)   capital  costs  for  A2C.  We  have  assumed  a  further  1%  annual  maintenance  costs 
Section 9(2)(j)  per year). 
 
 



 
Table 4:  Estimated benefit cost ratios – Option 2G (Sulphur Pt to Wynyard) 
 
Standard fare 
Low fare 
Zero fare 
Without A2C 
0.14 
0.61 
0.78 
With A2C 
0.30 
0.56 
0.67 
We have assessed a range of sensitivity tests on the above BCRs, based on the low fare, without A2C 
scenario. Those sensitivity tests have included the implications of: 
1982
 
reduced ferry frequencies (20 minute frequencies applied), allowing for 1 fewer ferry purchase 
and reduced operating costs 
Act 
 
10%  lower  implementation  costs  for  Sulphur  Point  to  Akoranga,  reflecting  a  value-engineered 
design 
 
P95 implementation costs for Sulphur Point to Akoranga Section 9(2)(j) 
 
a scenario where future changes to travel demands and/or infrastructure allows 2 lanes of the 
existing AHB to be dedicated to walking and cycling. This has been assumed to occur after  the 
ferries have been operating for 15 years, when: 
o  ferry and terminal operating and maintenance costs cease 
Information 
o  ferry service benefits cease 
o  ferry fare revenues cease 
o  Section 9(2)(j) in capital costs are incurred to retrofit the existing AHB and its approaches 
o  a  wide,  high  quality  walking  and  cycling  path  is  provided.  We  have  assumed  annual 
benefits will be equal to those calculated previously for the dedicated walking and cycling 
Official 
across the Waitematā harbour (assessed in August 2021). Ie not the narrower, single-
lane shared path assessed previously in this document 
the 
this sensitivity test does not account for the cost of any wider intervention(s) needed to enable 
the 2 AHB lanes to be repurposed. 
 
capping growth in demand at 2038 (the final forecast year) 
 
lower/higher uptake in e-bikes and other forms of micro-mobility 
under 
 
applying  MBCM  standard  benefit  rates  for  reductions  in  private  vehicle  travel.  Our  default 
assessment  uses  area-specific  benefit  rates  for cross-harbour  and  lower  North  Shore car  trips, 
developed  using  the  Northern  Corridor  Improvements  (NCI)  SATURN  models.  The  MBCM  rate 
does not reflect the traffic congestion experienced locally on the approaches to the AHB, or how 
this congestion is expected to change over time 
 
higher/lower  cycle  demand  estimates,  reflecting  wider  levers  that  may  affect  cycle  demands 
across  the  harbour,  including  changes  to  future  fuel  costs,  car  parking  availability,  car  and/or 
Released 
public transport infrastructure, congestion charging, and extended investment in the wider cycle 
network, among other levers. 
 
 


1982
Act 
Information 
Official 
the 
under 
Released 


10 
 
is some uncertainty about how the ACM responds to changes in generalised costs for ferry and bus trips 
across the harbour. 
Wider changes that affect cycling 
ACM is unable to reflect changes to other modes of travel that indirectly affect the uptake of cycling. 
These include future changes in fuel costs, car parking costs or availability, general traffic congestion, 
public transport fares or road pricing. Each of these wider regional levers has the potential to affect the 
numbers of people who chose to cycle across the harbour, and elsewhere.  
1982
Tourism and recreational trips 
Act 
Previous  assessments  of  the  walking  and  cycling  potential  across  the  Waitematā  Harbour  have 
considered the tourism and recreational potential. This has been necessary because previous proposals 
have been bridge connections across the harbour, which were expected to be fare free, but to also offer 
elevated  views of  the  harbour  and  city,  on  a  high-quality  facility.  A  future  ferry  or  bus  connection  is 
unlikely to have the same level of appeal, and the transfers required are unlikely to be used by sports-
recreational cyclists. As a result, we have assumed there would be no significant recreation or tourist 
trips  on  any  of  the  bus  and  ferry  options  assessed.  This  may  not  be  the  case  should  the  ferry/bus 
connection be fare free, but our assessment has maintained this assumption to be consistent across all 
Information 
bus/ferry scenarios, and due to the uncertainty in estimating the recreational and tourist potential of a 
ferry or bus service. 
Large scale behaviour change 
There is greater uncertainty in the scenarios where higher demand potential is forecast. For the lowest 
Official 
demand scenarios, the bus and ferry demands predicted are not significantly different to the existing 
numbers of cyclists using ferries across the Waitematā Harbour, so there is a fair level of confidence that 
these forecasts are achievable. The highest demand forecasts however require widespread behaviour 
the 
change among existing car and public transport users throughout the North Shore. There is a greater 
level of uncertainty in these scenarios, due to the large scale changes in travel behaviours required. 
Off-peak bus/ferry frequencies 
under 
The  ACM  develops estimates  of  daily  cycle  trips  based  on  modelled  commuter  peak  periods, scaling 
these up to account for off-peak and weekend trips. In the case of the bus and ferry options, interpeak 
frequencies  may  be  lower  than  the  modelled,  peak  frequencies.  As  a  result,  off-peak  and  weekend 
bus/ferry demands may be proportionally lower than estimated. The scaling factors used to estimate 
daily cycle demands do not account for any off-peak reduction in quality of service. 
Interchange facilities 
Released 
Our modelling has assumed a very high quality of interchange facilities between cycling and bus/ferry 
services. This would typically include indoor waiting areas, seating, toilets, and facilities to top up Hop 
cards if fares are to be charged. Any lesser standard may result in lower demands than those forecast 
above. 
 
 


11 
 
Wider economic benefits 
The  2021  economic  evaluation  of  a  new  walking  and  cycling  bridge  across  the  Waitematā  harbour 
included Section 9(2)(j) in annual agglomeration benefits. These benefits were associated with bringing 
the Takapuna Metropolitan Centre and Auckland City Centre ‘closer together’, and were developed by 
MRCagney in 2018. 
We have not allowed for any agglomeration benefits for the bus/ferry options. For the AHB shared path 
option however, we have allowed for 50% of these agglomeration benefits 
1982
Section 9(2)(j) per year, after 
applying current update factors). This acknowledges that the lower standard of path proposed will have 
reduced agglomeration effects, relative to the previously proposed dedicated bridge.  
Act 
For the scenario where 2 AHB traffic lanes are removed after 15 years of operation, we have applied the 
full annual agglomeration benefit, reflecting the higher quality and capacity of this link. 
 
 
 
Information 
 
 
 
Official 
 
 
the 
 
 
under 
 
 
 
 
 
Released 
 
 
Reference: P:\NZTA\207 Waitemata Harbour W&C Connection Options\4.0 Reporting\TN1C220321 Waitemata W&C Connection Assessment.docx - 
Section 9(2)(a)