This is an HTML version of an attachment to the Official Information request 'Waikato Expressway 110km/hr speed limit, environmental review, economic evaluation'.


 
DETAIL DESIGN ROAD SAFETY AUDIT 
SH1 WAIKATO EXPRESSWAY 110 KM/H SPEED 
REVIEW PROJECT TAMAHERE 
1982
PREPARED FOR  WAKA KOTAHI NZ TRANSPORT AGENCY 
26 October 2021 
Act 
 
 
Information 
Official 
the 
under 
Released 

 
This document has been prepared for the benefit of Waka Kotahi NZ Transport Agency.  No liability is 
accepted by this company or any employee or sub-consultant of this company with respect to its use by 
any other person. 
This disclaimer shall apply notwithstanding that the report may be made available to other persons for an 
application for permission or approval to fulfil a legal requirement. 
 
QUALITY STATEMENT 
1982
PROJECT MANAGER 
 
ROAD SAFETY AUDIT TEAM LEADER 
s 9(2)(a)
s 9(2)(a)
 
Act 
 
 
 
PREPARED BY 
s 9(2)(a)
s 9(2)(a)
 
 
26 October 2021 
 
CHECKED BY
 
s 9(2)(a)
 
26 October 2021 
 
REVIEWED BY
 
s 9(2)(a)
Information 
 
26 October 2021 
 
APPROVED FOR ISSUE BY
 
s 9(2)(a)
 
26 October 2021 
 
Official 
 
 
 
the 
 
 
 
 
under 
 
AUCKLAND 
Level 3 Stantec House, 111 Carlton Gore Road, Newmarket, Auckland 1023 
PO Box 13-052, Armagh, Christchurch 8141 
TEL  +64 9 580 4500 
 
 
Released 
Stantec  │  SH1 Waikato Expressway 110 km/h Speed Review Project Tamahere  │  26 October 2021 
Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE Client Response (v2) 
(002) 

 
 
Abbreviations 
ATP 
audio tactile profiled (road marking) 
RRPM 
reflectorised raised pavement marker 
SH1 State 
Highway 

1982
Waka Kotahi 
Waka Kotahi NZ Transport Agency 
 
Act 
 
Information 
Official 
the 
under 
Released 
Stantec  │  SH1 Waikato Expressway 110 km/h Speed Review Project Tamahere  │  26 October 2021 
Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE Client Response (v2) (002) 
│ Page i 

 
Waka Kotahi NZ Transport Agency 
SH1 Waikato Expressway 110 km/h Speed Review Project Tamahere 
 
CONTENTS 
1982
Abbreviations ...................................................................................................................................................... i 

Introduction ............................................................................................................................................ 1 
1.1 
Safety Audit Definition and Purpose ...................................................................................................... 1 
Act 
1.2 
The Project .............................................................................................................................................. 2 
1.3 
The Road Safety Audit Team ................................................................................................................. 2 
1.4 
Previous Road Safety Audits .................................................................................................................. 2 
1.5 
Scope of this Road Safety Audit ............................................................................................................ 2 
1.6 
Briefing, Site Visit, Audit, Exit Meeting .................................................................................................... 3 
1.7 
Report Format ......................................................................................................................................... 3 
1.8 
Documents Provided ............................................................................................................................. 4 
1.9 
Disclaimer ............................................................................................................................................... 4 
Information 

Safety Concerns .................................................................................................................................... 5 
2.1 
Barriers ..................................................................................................................................................... 5 
2.2 
Maintenance Bays ............................................................................................................................... 13 
2.3 
Road Signs and Markings ..................................................................................................................... 14 

Audit Statement ................................................................................................................................... 17 
Official 

Response and Decision Statements .................................................................................................... 18 
4.1 
Designer’s Responses ........................................................................................................................... 18 
the 
4.2 
Safety Engineer’s Comments (if applicable) ...................................................................................... 18 
4.3 
Project Manager’s Decisions ............................................................................................................... 18 
4.4 
Designer’s Statement ........................................................................................................................... 18 
4.5 
Safety Audit Close Out ......................................................................................................................... 18 

References ........................................................................................................................................... 20 
under 
 
LIST OF TABLES 
Table 1-1: Crash Frequency Descriptor .............................................................................................................. 3 
Table 1-2: Concern Assessment Rating Matrix ................................................................................................... 3 
Table 1-3: Concern Categories .......................................................................................................................... 4 
 
Released 
LIST OF FIGURES 
Figure 1: Project location .................................................................................................................................... 2 
Figure 2: Median barrier (Google, 2021) ............................................................................................................ 5 
Stantec  │  SH1 Waikato Expressway 110 km/h Speed Review Project Tamahere  │  26 October 2021 
Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE Client Response (v2) (002) 

 
Figure 3: Bridge barrier (Google, 2021) .............................................................................................................. 5 
Figure 4: Roadside barriers across gul y (Google, 2021) .................................................................................... 6 
Figure 5: Flexible to semi-rigid barrier transition detail ....................................................................................... 7 
Figure 6: Proposed barriers along northbound exit ramp .................................................................................. 7 
Figure 7: Trees and lighting column along northbound exit ramp (Google, 2021) .......................................... 8 
Figure 8: Proposed barriers along northbound entrance ramp ........................................................................ 8 
Figure 9: Trees and lighting column along northbound entrance ramp (Google, 2021)................................. 9 1982
Figure 10: Proposed barriers along southbound exit ramp................................................................................ 9 
Figure 11: Trees and lighting column along southbound exit ramp (Google, 2021) ......................................  10 
Act 
Figure 12: Proposed barriers along southbound entrance ramp .................................................................... 11 
Figure 13: Lighting column near southbound entrance ramp merge ............................................................ 11 
Figure 14: Lighting column close to edge of expressway (Google, 2021) ...................................................... 12 
Figure 15: Maintenance access bay detail ..................................................................................................... 13 
Figure 16: Proposed location of maintenance bays ....................................................................................... 13 
Figure 17: Exit ramp cyclist crossing at Cambridge (west) interchange (Google, 2019) ............................... 15 
Figure 18: Existing RRPM position in relation to edge line ................................................................................ 16 
 
Information 
  
 
 
Official 
the 
under 
Released 
Stantec  │  SH1 Waikato Expressway 110 km/h Speed Review Project Tamahere  │  26 October 2021 
Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE Client Response (v2) (002) 

 

Introduction 
1.1 
Safety Audit Definition and Purpose 
A road safety audit is a term used internationally to describe an independent review of a future road 
project to identify any safety concerns that may affect the safety performance. The audit team considers 
the safety of all road users and qualitatively reports on road safety issues or opportunities for safety 
improvement.  
1982
A road safety audit is therefore a formal examination of a road project, or any type of project which 
affects road users (including cyclists, pedestrians, mobility impaired etc.), carried out by an independent 
competent team who identify and document road safety concerns. 
Act 
A road safety audit is intended to help deliver a safe road system and is not a review of compliance with 
standards. 
The primary objective of a road safety audit is to deliver a project that achieves an outcome consistent 
with Safer Journeys and the Safe System approach, which is a safe road system free of death and serious 
injury. The road safety audit is a safety review used to identify all areas of a project that are inconsistent 
with a Safe System and bring those concerns to the attention of the client so that the client can make a 
value judgement as to appropriate action(s) based on the risk guidance provided by the safety audit 
team. 
The key objective of a road safety audit is summarised as: 
‘to deliver completed projects that contribute towards a safe road system that is free of death and serious 
injury by identifying and ranking potential safety concerns for all road users and others affected by a road 
Information 
project.’ 
A road safety audit should desirably be undertaken at project milestones such as: 
 
concept stage (part of business case); 
 
scheme or preliminary design stage (part of pre-implementation); 
 
detail design stage (pre-implementation or implementation); or 
Official 
 
pre-opening or post-construction stage (implementation or post-implementation). 
A road safety audit is not intended to be a technical or financial audit and does not substitute for a design 
check of standards or guidelines. Any recommended treatment of an identified safety concern is intended 
the 
to be indicative only, and to focus the designer on the type of improvements that might be appropriate. It 
is not intended to be prescriptive and other ways of improving the road safety or operational problems 
identified should also be considered. 
In accordance with the procedures set down in the NZTA Road Safety Audit Procedures for Projects 
Guidelines - Interim release May 2013 the audit report should be submitted to the client who will instruct the 
designer to respond. The designer should consider the report and comment to the client on each of any 
under 
concerns identified, including their cost implications where appropriate, and make a recommendation to 
either accept or reject the audit report recommendation. 
For each audit team recommendation that is accepted, the client will make the final decision and brief 
the designer to make the necessary changes and/or additions. As a result of this instruction the designer 
shall action the approved amendments. The client may involve a safety engineer to provide commentary 
to aid with the decision. 
Decision tracking is an important part of the road safety audit process. A decision tracking table is 
embedded into the report format at the end of each set of recommendations. It is to be completed by 
the designer, safety engineer, and client for each issue, and should record the designer’s response, client’s 
decision (and asset manager's comments in the case where the client and asset manager are not one 
Released 
and the same) and action taken. 
A copy of the report including the designer's response to the client and the client's decision on each 
recommendation shall be given to the road safety audit team leader as part of the important feedback 
loop. The road safety audit team leader will disseminate this to team members. 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 1 



 
1.2 
The Project 
Roadside and median safety barriers are to be installed along sections of the SH1 Waikato Expressway 
between Hampton Downs and Tamahere to provide continuous protection and to meet the safety criteria 
for raising the speed limit from 100 km/h to 110 km/h. 
The Tamahere project location is shown circled in blue in Figure 1. It comprises the short 1.5 km section 
between the southern end of the Hamilton Bypass (under construction) and the northern end of the 
Cambridge Bypass, which was competed in 2015. 
1982
Act 
Information 
 
Figure 1: Project location 
Flexible roadside protection barriers are proposed on both sides of the expressway from the south-facing 
Official 
ramps of the Tamahere interchange to the existing roadside barriers installed along the Cambridge Bypass. 
No alterations to the existing back-to-back semi-rigid median barrier are proposed. The roadside shoulders 
are to be widened to provide 3 m between the face of the barrier and the edge line. 
the 
1.3 
The Road Safety Audit Team 
This road safety audit has been carried out in accordance with the NZTA Road Safety Audit Procedure for 
Projects Guidelines – Interim release May 2013, by: 
 
Keith Weale, Stantec, 
under 
 
Tegwen Atkinson, Stantec, and 
 
Heather Liew, Waka Kotahi. 
1.4 
Previous Road Safety Audits 
There have been no previous road safety audits of the current project. 
1.5 
Scope of this Road Safety Audit 
This is a detail design road safety audit of the proposed installation of roadside barriers along the 
Released 
Tamahere section of the Waikato Expressway between the south-facing entrance and exit ramps of the 
Tamahere diamond interchange and the existing flexible roadside barriers along the Cambridge Bypass 
section.  
The designers are contemplating extending the barriers along the ramps of the Tamahere interchange and 
thus asked the road safety audit team to include the interchange ramps in the safety audit. 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 2 

 
1.6 
Briefing, Site Visit, Audit, Exit Meeting 
Lydia Gray of WSP (the designers) and Jeremy Froger of BBO, Shane Small of Waka Kotahi, and Thayalan 
Sivachelvan of Blue Barn (seconded to Waka Kotahi) briefed the road safety audit team on Wednesday 13 
October 2021, after which the road safety audit team undertook a desktop audit via MS Teams. 
A site visit was not permitted due to Auckland and Waikato being under Covid-19 Level 3 restrictions on 
movement and gatherings, and two of the road safety audit team members being based in Auckland. The 
safety audit team therefore conducted the safety audit using Google Street View images and Argonaut 
Roadrunner videos. 
1982
An exit meeting was held with the designers and Waka Kotahi representatives later that afternoon.  
1.7 
Report Format 
Act 
The potential road safety problems identified have been ranked as follows. 
The expected crash frequency is qualitatively assessed on the basis of expected exposure (how many 
road users will be exposed to a safety issue) and the likelihood of a crash resulting from the presence of the 
issue. The severity of a crash outcome is qualitatively assessed on the basis of factors such as expected 
speeds, type of collision, and type of vehicle involved. 
Reference to historic crash rates or other research for similar elements of projects, or projects as a whole, 
have been drawn on where appropriate to assist in understanding the likely crash types, frequency and 
likely severity that may result from a particular concern. 
The frequency and severity ratings are used together to develop a combined qualitative risk ranking for 
each safety issue using the concern assessment rating matrix in Table 1-2. The qualitative assessment 
requires professional judgement and a wide range of experience in projects of al  sizes and locations. 
Information 
In ranking specific concerns, the auditors have considered the objectives of the Safe System approach, i.e. 
to minimise fatal or serious injury crashes. 
In undertaking this assessment, the safety audit team has utilised the following descriptor tables to enable 
a fair and reasonable rating of the risks. 
Table 1-1: Crash Frequency Descriptor 
Crash Frequency 
Indicative Description  
Official 
Frequent Multiple 
crashes 
(more than 1 per year)  
Common 
1 every 1-5 years  
Occasional 
1 every 5-10 years  
the 
Infrequent 
Less than 1 every 10 years 
Crash severity is determined on the likelihood of a crash resulting in death or serious injury. The reader is 
advised that the severity of an injury is determined in part by the ability of a person to tolerate the crash 
forces. An able-bodied adult will have a greater ability to recover from higher trauma injuries, whereas an 
elderly person may have poor ability to recover from high trauma injuries. The auditors consider the likely 
under 
user composition, and hence the likely severity of injury to that user. 
Table 1-2: Concern Assessment Rating Matrix 
Severity 
Frequency (probability of a crash) 
(likelihood of death or 
serious injury) 
Frequent 
Common 
Occasional 
Infrequent 
Very likely 
Serious 
Serious 
Significant 
Moderate 
Likely 
Serious 
Significant 
Moderate 
Moderate 
Released 
Unlikely 
Significant 
Moderate 
Minor 
Minor 
Very unlikely 
Moderate 
Minor 
Minor 
Minor 
While all safety concerns should be considered for action, the client or nominated project manager will 
make the decision as to what course of action will be adopted based on the guidance given in this 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 3 

 
ranking process with consideration to factors other than safety alone. As a guide a suggested action for 
each concern category is given in Table 1-3. 
Table 1-3: Concern Categories 
Concern 
Suggested action 
Major safety concern that must be addressed and requires changes to avoid serious 
Serious 
safety consequences. 
Significant safety concern that should be addressed and requires changes to avoid 
Significant 
serious safety consequences. 
1982
Moderate 
Moderate safety concern that should be addressed to improve safety. 
Minor 
Minor safety concern that should be addressed where practical to improve safety. 
Act 
In addition to the ranked safety issues, it may be appropriate for the safety audit team to provide 
additional comments with respect to items that may have a safety implication but lie outside the scope of 
the safety audit. A comment may include items where the safety implications are not yet clear due to 
insufficient detail for the stage of project, items outside the scope of the audit such as existing issues not 
impacted by the project or an opportunity for improved safety but not necessarily linked to the project 
itself. While typically comments do not require a specific recommendation, the auditors may give 
suggestions in some instances. 
1.8 
Documents Provided 
The road safety audit team was provided with the following documents for this audit. 
2-32875.31 
C01 to C02 
Rev A 
General layout plan 
Information 
2-32875.31 C03 
Rev 

Typical 
section 
2-32875.31 
C04 
Rev A 
Maintenance bay detail 
2-32875.31 
C05 
Rev A 
Barrier transition type 1 
2-32875.31 
C06 
Rev A 
Barrier transition type 2 
SNP Tamahere Barriers Memo for RSA prepared by WSP (dated 7.10.2021) 
Official 
The fol owing supporting drawings of the Hamilton Bypass were provided for information only 
3311244-DR-CG-0738 
Rev 1 
Plan and longitudinal section of southern tie-in 
3311244-DR-CG-0739 
Rev B 
Plan and longitudinal section of southern tie-in 
the 
3311244-DR-CB-0738 
Rev 3 
Barriers at southern tie-in (issued for construction) 
3311244-DR-CB-0739 
Rev B 
Barriers at southern tie-in (not for construction)* 
In addition to the above, an email titled ‘SNP Tamahere barriers on ramps and gore areas’ (dated 
12.10.2021) was provided. This email outlined high level barrier locations and designs for the Tamahere 
interchange ramps. 
under 
*It is noted that the barriers shown extending along the ramps on this drawing are superseded by the ‘for 
construction’ drawings, which show the barriers termination at the nose of the exit ramp and the gore of 
the entrance ramp, the latter having been already installed. 
1.9 
Disclaimer 
The findings and recommendations in this report are based on an examination of available relevant plans, 
the specified road and its environs, and the opinions of the road safety audit team. However, it must be 
recognised that eliminating safety concerns cannot be guaranteed since no road can be regarded as 
absolutely safe and no warranty is implied that all safety issues have been identified in this report. Safety 
Released 
audits do not constitute a design review nor are they an assessment of standards with respect to 
engineering or planning documents. 
Readers are urged to seek specific technical advice on matters raised and not rely solely on the report. 
While every effort has been made to ensure the accuracy of the report, it is made available on the basis 
that anyone relying on it does so at their own risk without any liability to the safety audit team or their 
organisations. 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 4 





 

Safety Concerns 
A site visit was not permitted due to Auckland and Waikato being under Covid-19 Level 3 restrictions on 
movement and two of the road safety audit team members being based in Auckland. The safety audit 
team therefore conducted the safety audit using recent Google Street View images and Argonaut 
Roadrunner videos. 
2.1 
Barriers 
1982
2.1.1  Existing median and roadside barriers 
Moderate
The existing back-to-back semi-rigid median barrier and semi-rigid roadside barriers are likely to have been 
produced and installed to NCHRP 350 TL-3 standards. 
Act 
Although the barriers appear not to have received any recent strikes (as would be evidenced by replaced 
sections of barrier) their performance in preventing a vehicle (especially a high centre of gravity vehicle) 
from crossing the median into opposing traffic or crashing into the gully or road below may be 
questionable. The main concern is their low mounting height in relation to the road surface, particularly on 
the interchange bridge. 
Information 
Official 
 
the 
Figure 2: Median barrier (Google, 2021) 
under 
Released 
 
Figure 3: Bridge barrier (Google, 2021) 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 5 



 
1982
Act 
 
Figure 4: Roadside barriers across gully (Google, 2021) 
Recommendation(s) 
1.  Replace the existing median and roadside barriers (and especially the bridge barriers) with a taller and 
more appropriate level of performance barrier system. 
 
Information 
Frequency 
Severity 
Rating 
Crashes are likely to be 
Death or serious injury is 
The safety concern is 
infrequent 
likely 
moderate 
Designer 
Agree in general principles, though this is currently outside the scope of the work, 
response 
and would require some specialist bridge input into the affixing replacement barriers 
to the bridge deck. We have sourced plans of the original bridge, and preliminary 
advice is that concrete barriers would not be able to be placed without 
Official 
considerable strengthening of the bridge, and semi-rigid TL4 barrier (eg thribeam) 
would be more likely to be the appropriate treatment. 
The replaced roadside barriers would be at the same offset from the edgeline, 
which is in the order of 2.0m – considerably less that the 3.0m RONS standard 
the 
elsewhere on the Waikato Expressway. 
The median barrier currently existing with a 5. 0m grassed median (with the 
exception of the bridge crossing itself), narrower than the desired minimum for wire 
rope barrier medians. It is noted that the Hamilton Section terminates with a double 
sided F shape concrete barrier TL4 height. A suitable treatment would likely be a 
double sided semi rigid barrier until the median widens to the existing   
Safety Engineer 
Designer response is acknowledged. It is recommended to the client that all barriers 
under 
comment 
including  interchange bridge barrier be replaced thereby providing safety to road 
users.  
Client decision 
This work is beyond the original scope of works and requires review. 
 
If mitigation of the existing risk is required, impact on the WEX 110km/h project 
(schedule, time, cost) to be approved and funding allocated. 
 
Action taken 
A scope change request has been developed identifying the risk with the 
 
performance of the existing barriers and potential mitigation options. Date of 
resolution tbc. 
Released 
 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 6 



 
2.1.2  Flexible to semi-rigid barrier transition detail 
Comment
The transition from flexible to semi-rigid barrier, which would be applied only near the northbound exit 
ramp, shows a 1 m lateral step from the widened shoulder width of 3 m to tie into an existing shoulder 
width of 2 m. 
Normally the projected faces of the flexible barrier and the semi-rigid barrier would line up, i.e. be the 
same offset from the edge line, and the flexible barrier would deviate behind the semi-rigid barrier only 
locally.  
1982
Act 
3 m 
2 m 
 
Figure 5: Flexible to semi-rigid barrier transition detail 
Although the proposed detail appears to adopt the same performance principles as shown in the RSB7A 
standard drawing of Waka Kotahi, it may be worth checking that Waka Kotahi is comfortable with the 
proposed detail.  
 
Designer 
Accepted. Propose to use a flared guardrail extension and terminal to widen to 
Information 
response 
3.0m rather than a lateral step. Detail updated. 
Safety Engineer 
Agree with designer’s response. 
comment 
Client decision 
Agree with SAT and RSE 
 
Action taken 
The design has been updated to reflect the designers response. 
 
Official 
 
2.1.3  Proposed northbound exit ramp barriers 
Comment
the 
The designers are contemplating providing barriers along the right-hand side of the exit ramp and 
connecting these to the existing barriers behind the nose with a crash cushion as indicated in Figure 6. 
under 
 
Figure 6: Proposed barriers along northbound exit ramp 
Released 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 7 






 
1982
Act 
 
Figure 7: Trees and lighting column along northbound exit ramp (Google, 2021) 
Information 
The proposal would be a positive safety improvement as there are a number of large trees next to the 
ramp in Figure 7. 
Refer to Section 2.1.7 concerning the proximity of the lighting column in Figure 6 (yel ow circle) and Figure 
7 to the proposed barrier and crash cushion. 
2.1.4  Proposed northbound entrance ramp barriers 
Comment
Official 
The designers are contemplating providing barriers along the left-hand side of the entrance ramp as 
shown in red in Figure 8 and Figure 9 and extending the existing barriers to the nose as indicated by the 
green line in Figure 8 and Figure 9. The southern end of the flexible barrier system already installed on the 
the 
Hamilton Bypass project is shown by the yellow arrow in Figure 9. 
under 
 
Figure 8: Proposed barriers along northbound entrance ramp 
 
Released 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 8 




 
1982
Act 
 
Figure 9: Trees and lighting column along northbound entrance ramp (Google, 2021) 
The proposal would be a positive safety improvement as there are a number of large trees and a lighting 
column next to the ramp. 
The ramp joins the expressway as a lane gain so intervisibility between drivers entering the expressway and 
drivers using the expressway should not be a significant factor. 
Refer to Section 2.1.7 concerning the proximity of the lighting column in Figure 8 (yel ow circle) and Figure 
Information 
9 to the proposed barrier next to the expressway. 
2.1.5  Proposed southbound exit ramp barriers 
Comment
The designers are contemplating providing barriers along both sides of the entrance ramp as shown in red 
in Figure 10 and extending the existing barriers to the nose as indicated by the green line in Figure 10. 
 
Official 
the 
under 
 
Figure 10: Proposed barriers along southbound exit ramp 
Released 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 9 




 
1982
Act 
 
Figure 11: Trees and lighting column along southbound exit ramp (Google, 2021) 
Information 
The proposal would be a positive safety improvement as there are a number of large trees next to the 
ramp. 
However, the designers expressed concern that installing barriers along the exiting edge of seal on both 
sides of the ramp would not provide enough width (5 m to 5.5 m) for broken down vehicles to stop or for 
emergency vehicles to pass without significant widening of the pavement. 
The barriers on both sides of the ramp probably do not need to be extended as far down the ramp as 
Official 
proposed. The is a farm gate about halfway down the ramp, to which access would need to be 
maintained. the barriers could probably end at the gate. The ramp is straight and has good sight distance 
along it. Speeds would be bleeding off as drivers slowed for the ramp terminal intersection. The greatest 
risk of a crash would be close to the nose where drivers might suddenly realize that they have reached the 
the 
exit and swerve across the gore losing control and crashing into the trees on either side of the ramp. 
If the decision to provide barriers or not is to be based on the need to widen the ramp, then it is suggested 
that the left-hand barriers rather be set back beyond the existing kerbs close to the fence line than be 
omitted. If the barriers were set back sufficiently from the kerb, the kerb should not be a factor provided 
that the strip between the kerbs and the barrier were filled with hardfil . Again, it would be safer to provide 
the barriers and accept a slight risk of less than perfect barrier performance, than to omit the barriers. 
under 
Refer to Section 2.1.7 concerning the proximity of the lighting column in Figure 10 (yel ow circle) and Figure 
11 to the proposed barrier next to the expressway. 
2.1.6  Proposed southbound entrance ramp barriers 
Comment
The designers are contemplating providing barriers along both sides of the entrance ramp as shown in red 
in Figure 12 and extending the existing barriers to the nose as indicated by the green line in Figure 12. 
Released 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 10 





 
1982
 
Act 
Figure 12: Proposed barriers along southbound entrance ramp 
Information 
Official 
 
the 
Figure 13: Lighting column near southbound entrance ramp merge 
With the exception of the lighting column shown in Figure 13, there are no other significant hazards that 
motorist need to be protected from in the vicinity of the merge area. 
The ramp joins the expressway as a standard entrance ramp merge so intervisibility between drivers 
entering the expressway and drivers using the expressway is a significant factor to be considered when 
under 
placing the barriers in a position that could obstruct the intervisibility. 
Refer to Section 2.1.7 concerning the proximity of the lighting column in Figure 12 (yel ow circle) and Figure 
13 to the proposed barrier next to the expressway. 
2.1.7  Lighting columns 
Minor
Figure 14 shows a typical lighting column close to the edge of the expressway. Some, such as the one 
arrowed in Figure 14 at the northbound exit ramp are behind existing barriers. Others, such as the one in 
the foreground of Figure 14 at the southbound entrance ramp are currently exposed. 
Released 
The designers are contemplating extending the barriers on all four ramps up to the nose as described in 
the preceding Sections 2.1.3, 2.1.4, 2.1.5, and 2.1.6. In all cases there one or more lighting columns that 
would be within the operating zone of a barrier. The performance of the existing and proposed barriers, 
and of the slip base lighting columns, would be unpredictable in a crash. 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 11 



 
1982
Act 
 
Figure 14: Lighting column close to edge of expressway (Google, 2021) 
It is acknowledged that the installation of the roadside barriers would be a safety improvement, even if 
they were not installed in accordance with accepted normal operating clearances. However, 
consideration should be given to mitigating the departure, like using a stiffer less deflective barrier system 
or replacing the lighting columns with fewer high mast lighting columns in less vulnerable positions. 
Recommendation(s) 
Information 
1.  Mitigate the consequence of the potentially narrow gap between the lighting columns and the back 
of the roadside barriers by using a stiffer less deflective barrier system. 
2.  In conjunction with the recommendation above, specify on the cross-section edge details what 
minimum clearance between the lighting columns and the back of the barrier would be sought.  
3.  Where lighting columns might need to be relocated, specify ground-planted frangible lighting columns 
to replace the slip-base columns. 
 
Frequency 
Severity 
Rating 
Official 
Crashes are likely to be 
Death or serious injury is 
The safety concern is 
occasional 
unlikely 
minor 
Designer 
Agreed, included in plan and details. 
the 
response 
Safety Engineer 
Acknowledge designer’s response. It is recommended to the client that slip base 
comment 
light columns are the preferred option. Clearance from the proposed barrier to all 
light columns should be as per Waka Kotahi guidelines 
Client decision 
Agree with SAT and RSE. 
 
 
However, M23 Appendix A,  notes the below: 
under 
 
‘m) For new installations, lighting columns shall be installed so that there is at least 
1.5 m clearance between the closest parts of the barrier system and the lighting 
column.  In retrofit situations only, this may be reduced to 1.0 m with application to, 
and acceptance by, the Lead Safety Advisor. Lighting columns behind barriers 
should not be on a frangible ‘slip base’ (for retrofit installations these should be 
modified to reduce the risk of being activated by a deflecting barrier).’ 
 
Based on this requirement, ground-planted frangible lighting columns are to be 
specified. 
Released   
Action taken 
The design has been updated to ground-planted frangible lighting columns. 
 
 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 12 




 
2.2 
Maintenance Bays 
2.2.1  Manoeuvring width 
Moderate
The proposed maintenance bays, which are intended to give access to the berm in both directions, are 
shown in Figure 15 and Figure 16. Although the detail shows a width of 4 m, the layout indicates 3 m. 
The designers explained that entry would be in the forward direction, as opposed to reversing into the bay.  
1982
Act 
 
Figure 15: Maintenance access bay detail 
Information 
Official 
the 
 
Figure 16: Proposed location of maintenance bays 
The effective width of the maintenance bay in the detail in Figure 15would be less than the 4 m width 
under 
shown when the widths of the end terminals are taken into account. There is thus unlikely to be enough 
width for a maintenance truck to manoeuvre into the maintenance bay from the shoulder and a portion 
of the through lane will likely be required for the manoeuvre. Similarly, exiting the bay might require the 
front of the vehicle to swing wide into the adjacent lane. This would mean blocking the through lane while 
manoeuvring in or out, effectively bringing all traffic in that lane to an unexpected halt. This would be 
unsafe, not only for the general traffic, but also for the maintenance personnel. 
The proposal to reduce the width to 3 m, due to space constraints, could render the maintenance bay 
almost unusable for any vehicle other than a ute. 
The possibility of using a lane closure traffic management plan with attenuation vehicles was discussed in a 
similar audit of the Hampton Downs section. However, the risk is that a maintenance person might try to 
Released 
use the bay not realising that it required a special temporary traffic management plan. 
From a safety in design perspective, a driver trying to climb out of a vehicle is likely to stand on or fall over 
the barriers, even if parked beyond the double barrier section as the available width for the maintenance 
bay would still be limited by the road reserve boundary and cut or fill embankment.  
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 13 

 
Furthermore, the gap in the roadside barrier will leave any worker of vehicle in the maintenance bay 
exposed to the risk of a vehicle leaving the road at that point. 
Recommendation(s) 
1.  Amend the design to a disengaging overlapping barrier layout that will allow maintenance vehicle 
drivers to pull over onto the shoulder first and then access the maintenance bay without encroaching 
into the adjacent through lane, while also fully shielding the maintenance vehicle and any personnel 
in the maintenance bay. This may require additional access bays or alternative arrangements to 
service the berm in both directions. 
1982
 
Frequency 
Severity 
Rating 
Crashes are likely to be 
Death or serious injury is 
The safety concern is 
infrequent 
likely 
moderate 
Act 
Designer 
The current location shown is the widest location within the project length. Tracking 
response 
paths with a 8m truck have been run on the current arrangement, which indicates 
that an additional 5m of length is required for the vehicle to make the entry. Also we 
acknowledge the difficultly exiting the vehicle, and have extended the paved area 
of the maintenance bay 12m beyond the rear barrier terminal to enable a vehicle 
to park clear of the barrier obstructing the doorway. Detail updated. 
An alternate arrangement to ensure that the appropriate TMP is followed is to 
remove the gap, and allow access into the bay area by means of a wire rope drop 
in conjunction with the lane drop. This would al ow the rear barrier to be removed as 
well. 
Safety Engineer 
Concern from SAT is noted, while it is preferable to have overlapping barriers , the 
comment 
option proposed by the designer also mitigates the risk highlighted by SAT. An 
Information 
alternate arrangement is not preferable.  it is recommended to the client that the 
arrangement proposed by designer be opted. 
Client decision 
Agree with Designer and RSE. 
 
Action taken 
The design has been amended to improve maintenance bay vehicle entry and 
 
personnel exiting the vehicle within the maintenance bay. 
 
Official 
2.3 
Road Signs and Markings 
the 
2.3.1  Gore signs and markings 
Minor
The existing exit and entrance ramp gore areas have no hatching. Since there may now be crash cushions 
on the exit noses, thus reducing the area on and behind the noses for recovery, both exit ramps would 
benefit from increased visibility. It is acknowledged that the interchange is lit, but speeds will be higher. 
All exit gores should be marked with diagonal chevron bars for consistency along the Waikato Expressway. 
under 
Te Kauwhata, Rangiriri and Huntly interchanges are marked, but interchanges such as  Hampton Downs, 
Ohinewai, and Tamahere are not. 
The exit signs on the noses may need to be relocated to allow the crash cushions to be installed.  
 
Recommendation(s) 
1.  Mark the exit and entrance gore areas with diagonal chevron bars. Apply this to all exits on the 
Waikato Expressway for consistency. 
2.  Check if the exit signs need to be relocated behind the installed crash cushions. 
Released 
 
Frequency 
Severity 
Rating 
Crashes are likely to be 
Death or serious injury is 
The safety concern is 
infrequent 
unlikely 
minor 
Designer 
Agreed. Chevrons in the gore area of the southbound offramp are included in the 
response 
Hamilton Section plans. Hatching in northbound offramp has been added to the 
drawings, and sign relocation provisionally included if necessary. 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 14 


 
Safety Engineer 
Agree with designer’s response.  
comment 
Client decision 
Agree with SAT and RSE. 
 
Action taken 
The design has been updated. 
 
 
1982
2.3.2  Cyclist signs and markings 
Comment
Cyclists would still be allowed to use the 110 km/h sections of the Waikato Expressway. 
Some sections of the existing Waikato Expressway cater for cyclists in the form of painted buffer strips (e.g. 
Act 
Rangiriri to Ohinewai) and signed crossing points across exit and entrance ramps as shown in Figure 17 
which is in an existing 110 km/h speed limit zone along the Cambridge Bypass not far from the Tamahere 
interchange. Such shoulder buffers and cyclist crossings are not present on the Hampton Downs section or 
the Tamahere section or other recently opened sections such as the Huntly Bypass. 
 
Information 
Official 
the 
under 
 
Figure 17: Exit ramp cyclist crossing at Cambridge (west) interchange (Google, 2019) 
Since the Waikato Expressway looks like a motorway, it would be reasonable to assume that some drivers 
would not expect to encounter cyclists in such an environment and would therefore not be looking out for 
cyclists. 
While the buffer strips and signed crossing points provide no physical protection for cyclists, the signs and 
markings may remind drivers to be on the lookout for cyclists. The converse may also be true—where the 
signs and markings end or are not present, drivers may think that cyclists are not al owed on the 
expressway. 
Released 
A consistent philosophical approach should be taken regarding the provision of cyclist signs and markings 
along the entire length of the Waikato Expressway. 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 15 



 
2.3.3  RRPMs and ATP 
Comment
The drawings do not indicate any change to the existing edge line markings, which do not include ATP but 
do include RRPMs. For consistency along the Waikato Expressway a decision should be made to include 
ATP along all sections, unless they could be annoying for people living close by.  
The ATP markings applied on the recent Longswamp to Rangiriri project (June 2020) coincided with the 
RRPMs. Not only did the application cover the RRPMs in many cases, but the raised portion of the ATP also 
tended to mask the full effectiveness of the RRPM reflectivity, effectively reducing the RRPM to about half 1982
its reflective area when viewed from the low angle of a passenger vehicle. 
Fortunately, it appears that the exiting RRPMs along the Tamahere section are set far enough away from 
the existing edge line for ATP to be applied between the line of RRPs and the edge line. However, the 
foregoing comment should be borne in mind when drawing up any specifications or drawings for ATP. 
Act 
Information 
 
Official 
Figure 18: Existing RRPM position in relation to edge line 
the 
under 
Released 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 16 






 

Audit Statement 
We declare that we remain independent of the design team and have not been influenced in any way by 
any party during this road safety audit. 
We certify that we have used the available plans, and have examined the specified roads and their 
environment, to identify features of the project we have been asked to look at that could be changed, 
removed, or modified in order to improve safety. 
We have noted the safety concerns that have been evident in this audit and have made 
recommendations that may be used to assist in improving safety. 
1982
s 9(2)(a)
Signed 
Date  22 October 2021 Act 
s 9(2)(a)
 
Technical Director – Roads and Highways, Stantec 
s 9(2)(a)
Signed 
Date  26 October 2021 
s 9(2)(a)
 
Project Transportation Engineer, Stantec 
Information 
Signed 
 
Date  26 October 2021 
Heather Liew, BEng(Hons), MET 
Safety Engineer, Waka Kotahi 
Official 
the 
under 
Released 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 17 







 

Response and Decision Statements 
System designers and the people who use the roads must all share responsibility for creating a road system 
where crash forces do not result in death or serious injury. 
4.1 
Designer’s Responses 
I have studied and considered the auditors’ safety concerns and recommendations for safety 
improvements set out in this road safety audit report and I have responded accordingly to each safety 
concern with the most appropriate and practical solutions and actions, which are to be considered further 
1982
by the safety engineer (if applicable) and project manager. 
s 9(2)(a)
Act 
Signed 
Date 17/02/2022 
s 9(2)(a)
 
4.2 
Safety Engineer’s Comments (if applicable) 
I have studied and considered the auditors’ safety concerns and recommendations for safety 
improvements set out in this road safety audit report together with the designer’s responses. Where 
appropriate, I have added comments to be taken into consideration by the project manager when 
deciding on the action to be taken. 
s 9(2)(a)
Information 
Signed 
Date 01/03/2022 
s 9(2)(a)
 
4.3 
Project Manager’s Decisions 
Official 
I have studied and considered the auditors’ safety concerns and recommendations for safety 
improvements set out in this road safety audit report, together with the designer’s responses and the 
comments of the safety engineer (if applicable) and having been guided by the auditor’s ranking of 
concerns have decided the most appropriate and practical action to be taken to address each of the 
the 
safety concerns. 
Signed 
 
Date 02/02/2022 
[Shane Small, BEng(Civil), Project Manager, NZTA] 
under 
4.4 
Designer’s Statement 
I certify that the project manager’s decisions and directions for action to be taken to improve safety for 
each of the safety concerns have been carried out. 
s 9(2)(a)
Signed 
Date 17/02/2022 
Released 
s 9(2)(a)
 
4.5 
Safety Audit Close Out 
The project manager is to distribute the audit report incorporating the decisions to the designer, safety 
audit team leader, safety engineer, and project file. 
Date:………………………………. 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 18 

 
 
1982
Act 
Information 
Official 
the 
under 
Released 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 19 

 

References 
Google. (2019, December). Street View. 
Google. (2021, May). Street View. 
Google. (2021, February). Street View. 
 
 
1982
 
Act 
Information 
Official 
the 
under 
Released 
26 October 2021 │ Status: Final │ Project No.: 310201124 Child No.: 100.0101906 │ Our ref: WEX 110 Tamahere Detail RSA - Designer RSE 
Client Response (v2) (002) 
Page 20 


 
 
 
Auckland 
Level 3 Stantec House, 111 Carlton Gore Road 
Newmarket, Auckland 1023 
PO Box 13-052, Armagh 
Christchurch 8141 
Tel  +64 9 580 4500 
 
1982
Please visit www.stantec.com to learn more about how 
Stantec design with community in mind. 
Act 
Information 
Official 
the 
under 
Released